Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Iron County, Utah.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
82 N 100 E #102, Cedar City, UT 84720
Phone
(435) 865-5350
Email
Office hours
Monday–Friday, 7:30 AM to 4:30 PM, per ironcountyut.gov/building. Building Official: Terry Palmer; Assistant Building Official/Zoning Officer: Nate Dennett.

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing/Foundation

    Per Geotechnical Form — Footing Foundation submittal requirement.

  2. 2

    Backfill/Final Grade (Geotechnical)

    Second-stage geotechnical sign-off per Geotechnical Form — Backfill Final Grade.

  3. 3

    Framing / Structural

    Structural framing verified against engineer-stamped plans; specific county inspection checklist not separately published online as of 2026-07-19.

  4. 4

    Final

    Final building inspection prior to occupancy.

Applies to: Residential Building Permit (Single Family Dwelling, New Construction)

  1. 1

    Footing/Foundation

    Per Geotechnical Form — Footing Foundation submittal requirement, Iron County Forms index.

  2. 2

    Backfill/Final Grade (Geotechnical)

    Second-stage geotechnical sign-off per Geotechnical Form — Backfill Final Grade, distinct from the footing-stage form, per Iron County Forms index.

  3. 3

    Framing

    Structural framing inspection consistent with adopted IBC/IRC requirements; specific county inspection checklist not separately published online as of 2026-07-04.

  4. 4

    Final

    Final building inspection prior to occupancy.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural

    Verified against submitted plans where the tenant improvement affects structural or fire-rated elements.

  2. 2

    Rough MEP

    Mechanical/electrical/plumbing rough-in applicable to the tenant improvement scope.

  3. 3

    Final

    Final inspection prior to occupancy.

Applies to: Remodel / Basement Finish Permit

  1. 1

    Framing

    Wall framing and fire-blocking inspection for basement finish or remodel scope.

  2. 2

    Rough MEP

    Mechanical/electrical/plumbing rough-in applicable to remodel/basement-finish scope.

  3. 3

    Final

    Final inspection.

Applies to: Swimming Pool Permit

  1. 1

    Excavation/Steel

    Pool shell excavation, rebar, and plumbing before shell placement, consistent with adopted ISPSC.

  2. 2

    Electrical/Bonding

    Pool bonding grid and GFCI protection per NEC Article 680.

  3. 3

    Final

    Final inspection including barrier/fence compliance.

Applies to: Electrical Permit (Service Upgrade, New Meter Base)

  1. 1

    Rough Electrical

    Wiring, panel, and grounding inspection consistent with adopted 2023 NEC; specific county inspection checklist not separately published online as of 2026-07-04.

  2. 2

    Final

    Final electrical inspection.

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    Wiring, panel, and grounding inspection consistent with adopted 2023 NEC; specific county inspection checklist not separately published online.

  2. 2

    Final

    Final electrical inspection.

Applies to: Fire Sprinkler / Fire Alarm Permit

  1. 1

    Rough-In (Sprinkler Piping / Alarm Wiring)

    Rough inspection of sprinkler piping or fire alarm wiring and devices prior to concealment. The specific inspecting authority (Utah State Fire Marshal, local fire district, or county Building Department) and checklist are not independently confirmed for unincorporated Iron County as of 2026-07-22.

  2. 2

    Final Acceptance Test

    Final fire alarm and/or automatic sprinkler system acceptance test consistent with NFPA 72/NFPA 13 as referenced by the adopted IBC/IFC. The specific inspecting authority is not independently confirmed for unincorporated Iron County.

Applies to: Mechanical Permit (Furnace, Gas Line/Meter, etc.)

  1. 1

    Rough Mechanical

    Ductwork, gas line, and equipment inspection consistent with adopted IMC/IFGC; specific county inspection checklist not separately published online as of 2026-07-04.

  2. 2

    Final

    Final mechanical inspection.

Applies to: Plumbing Permit (Water Heater, etc.)

  1. 1

    Rough Plumbing

    Pipe sizing, slope, and pressure test consistent with adopted IPC; specific county inspection checklist not separately published online as of 2026-07-04.

  2. 2

    Final

    Final plumbing inspection.

Applies to: Residential Solar Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect and rapid-shutdown placement per the adopted 2023 NEC.

  2. 2

    Final

    Final electrical/structural inspection prior to energizing.

Final inspection only: Change of Use Permit

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Iron County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Unincorporated Iron County building permits

Get alerts for Unincorporated Iron County

We'll email you when Unincorporated Iron County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.