Commercial Tenant Improvement / Tenant Finish Permit in Unincorporated Iron County, Utah

Required for tenant improvement and remodel work inside an existing commercial building in unincorporated Iron County. Iron County's Fee Schedule does not publish a tenant-improvement-specific line; the county's 'Remodel' fee line (valued at Contractor's Estimate rather than the per-occupancy-classification valuation table) is the closest published match, alongside the $500 Commercial Building Application/Plan Review Submittal Fee.

Reviewed 2026-07-19 · Source

When you need this permit

  • Tenant improvement or remodel work within an existing commercial building
  • Architectural, structural, plumbing, mechanical, and electrical plans as applicable to the scope of work

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

RemodelIron County Fee Schedule, adopted May 26, 2026 — the only Building Department fee line valued by contractor estimate rather than the per-occupancy-classification valuation table; the closest published match for commercial tenant improvement work, though the fee schedule does not explicitly label this line as commercial-only (it also covers residential remodels).
B.P. Contractor's Estimate, P.C. 40% to 65% + State Fee
Building Application/Plan Review Submittal Fee (Commercial)Iron County Fee Schedule, adopted May 26, 2026, Legend note (d) — applies to commercial projects generally; not distinguished between new construction and tenant improvement.
$500 (non-refundable, applied to the building permit)
Utah State FeeIron County Fee Schedule, adopted May 26, 2026.
1% of the Building Permit Fee

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Unincorporated Iron County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing / Structural

    Verified against submitted plans where the tenant improvement affects structural or fire-rated elements.

  2. 2

    Rough MEP

    Mechanical/electrical/plumbing rough-in applicable to the tenant improvement scope.

  3. 3

    Final

    Final inspection prior to occupancy.

See the full Unincorporated Iron County inspection guide — scheduling & re-inspection fees →

Tips

  • Iron County's 'Remodel' fee line (Contractor's Estimate valuation, Plan Check 40–65%) is not labeled commercial-only on the Fee Schedule — it also covers residential remodels; confirm with the Building Department, (435) 865-5350, whether a distinct commercial tenant-improvement rate applies to your project.
  • The $500 Commercial Building Application/Plan Review Submittal Fee (versus $250 for a Dwelling) applies to commercial permits generally, including tenant improvement work, per the Fee Schedule's Legend note (d).

Frequently asked questions

Unincorporated Iron County requires a commercial tenant improvement / tenant finish permit for: Tenant improvement or remodel work within an existing commercial building; Architectural, structural, plumbing, mechanical, and electrical plans as applicable to the scope of work. If your project isn't listed, confirm with Iron County Building Department at (435) 865-5350 before starting work.

No dedicated tenant-improvement fee line is published. The closest match on the Iron County Fee Schedule (adopted May 26, 2026) is the general 'Remodel' line, valued at the Contractor's Estimate with a 40% to 65% Plan Check fee, plus the $500 Commercial Building Application/Plan Review Submittal Fee. Contact the Building Department at (435) 865-5350 to confirm which line item applies to a specific tenant finish scope.

Unincorporated Iron County does not publish a plan-review timeline for this permit. Contact Iron County Building Department at (435) 865-5350 for current turnaround.

You'll need: Building Permit Application; Plans for Affected Scope. See the required-documents checklist on this page for details on each.

Unincorporated Iron County requires 3 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Framing / Structural, Rough MEP, Final. Schedule each through Iron County Building Department ((435) 865-5350).

Apply through Iron County Building Department at 82 N 100 E #102, Cedar City, UT 84720. Phone: (435) 865-5350. Office hours: Monday–Friday, 7:30 AM to 4:30 PM, per ironcountyut.gov/building. Building Official: Terry Palmer; Assistant Building Official/Zoning Officer: Nate Dennett.. Official information: https://ironcountyut.gov/building.

Unincorporated Iron County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C & J — Utah Code § 15A-2-103(1)(a); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026). Iron County's own building.gov page and forms index do not publish a distinct county code-adoption page; per Utah's Title 15A compliance-agency model, unincorporated Iron County (like unincorporated Washington County in this corpus) is bound by the statewide-adopted specific editions absent its own published amendment.; 2021 International Residential Code (IRC), including Appendix Q — Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 revision — only the IRC (and NEC) held at their prior editions while the other codes advanced to 2024 — still the current edition.; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026).; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026).; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026).; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); NEC remains 2023 across the 7/1/2026 statutory rollover (not superseded by a 2024/2026 NEC edition in that cycle) — still the current edition.; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); statute has no residential/commercial split — one edition applies to both.; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026).; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026).; NOTE (verified 2026-07-16 against the live Utah Code § 15A-2-103 text, version headed 'Effective 7/1/2026 / Superseded 1/1/2027'): the 2024 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC listed above took effect July 1, 2026, replacing the 2021 editions; IRC (2021) and NEC (2023) did not change. The 1/1/2027 version of the statute carries identical editions, so no further flip is expected then. This entry previously (as of lastVerified 2026-07-03) correctly flagged that the rollover had occurred in a trailing note, but the individual code lines above it still led with the 2021 editions as the primary/current statement — corrected on this date so the lines themselves state the current editions. Iron County's own building.gov/building page and its Forms index (ironcountyut.gov/building/forms) do not independently republish specific code-edition numbers, so this file reports the statutory default rather than a county-specific citation — flagged here rather than silently assumed identical to Cedar City's page, which does publish its own distinct Current Adopted Codes list.. Local amendments apply — see the Unincorporated Iron County overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Iron County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Iron County.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.