Riverton building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Riverton, Utah.
Verified 2026-07-01 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 12830 S Redwood Road, Room 105, Riverton, UT 84065
- Phone
- (801) 208-3138
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM
- Website
- Official site
Published scheduling rules
- All inspection requests must be made at least one working day in advance, before 1:00 PM — call (801) 208-3138. (Residential Building Permit)
- Inspections must be requested at least one working day in advance before 1:00 PM — call (801) 208-3138. (Roofing Permit (Re-Roof))
- All inspection requests must be made at least one working day in advance before 1:00 PM at (801) 208-3138. (General)
Inspection sequence
Applies to: Residential Building Permit
- 1
Temporary Power
After pedestal/panel and GFCI outlets are installed and grounding electrode system is visible.
- 2
Footing
After footings have been dug and rebar has been placed.
- 3
Foundation
After forms have been set and rebar is placed and supported with 3-inch clearance to earth.
- 4
Underground Plumbing
After all pipes have been installed and system is being tested and before backfilling.
- 5
Underground Electrical
After all conduit is installed and metal joints protected.
- 6
Underground Mechanical
After all duct is installed and sloped to an approved location.
- 7
Underground Gas
After gas line is installed, tracer wire is placed and gas lines are being tested.
- 8
Plumbing Rough-In
After all plumbing drains, vents, and water lines are installed and being tested.
- 9
Electrical Rough-In
After all electrical wires and boxes are installed.
- 10
Mechanical Rough-In
After all duct, vents, flues, and combustion air are installed that will not be exposed for final.
- 11
Framing
After plumbing, electrical, and mechanical have been installed and framing is completed, including windows and doors. Before any weather barrier is installed.
- 12
Insulation
After insulation (except attic blown-in) has been installed, including foam at windows, doors, and top and bottom plate penetrations.
- 13
Final
After building is complete and ready for occupancy. Includes grading, concrete, address, and landscaping if required. Engineering and Land Disturbance Permit approval are needed.
Applies to: Accessory Dwelling Unit (ADU)
- 1
Foundation
Footings, forms, rebar — before concrete pour.
- 2
Framing
Structure, fire separation, egress windows.
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-ins before walls closed.
- 4
Insulation
Insulation and vapor barrier before drywall.
- 5
Final
All work complete, smoke/CO detectors, address posted, ready for occupancy.
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window wells and openings verified.
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed.
- 3
Insulation
Insulation on exterior walls (except attic blown-in), including foam at windows, doors, and plate penetrations.
- 4
Final
Drywall, fixtures, smoke and CO detectors, and all finishes complete.
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Underground / Rough-In (MEP)
Before backfill and before closing walls or ceilings
- 3
Framing
After framing, sheathing, and rough-in mechanical/electrical/plumbing
- 4
Final
All work complete — certificate of occupancy issued upon passing final inspection
Applies to: Electrical Permit
- 1
Underground Electrical
After all conduit is installed and metal joints protected.
- 2
Electrical Rough-In
After all electrical wires and boxes are installed, before walls are closed.
- 3
Power to Panel
After grounding electrode system and main breakers are installed.
- 4
Final
All devices installed, GFCI/AFCI protection verified, panel labeled.
Applies to: Deck Permit
- 1
Footings
Verify footing depth (below 30-inch frost line), diameter, and rebar before concrete pour.
- 2
Framing
Posts, beams, joists, ledger connection, and hardware verified.
- 3
Final
Decking, stairs, guards, and railings complete. Guards required when deck surface is 30 inches or more above grade.
Applies to: Plumbing Permit
- 1
Underground Plumbing
After all pipes have been installed and system is being tested, before backfilling.
- 2
Plumbing Rough-In
After all plumbing drains, vents, and water lines are installed and being tested.
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified.
Applies to: Change of Use / Certificate of Occupancy Compliance
- 1
Zoning Verification (Planning Department)
Development Services/Planning confirms the proposed use complies with Riverton's zoning ordinance — required before a business license is issued for the new use.
- 2
Certificate of Occupancy Commercial Checklist Sign-offs
For new construction or an occupancy-classification change, the Building Official must receive electronic approval from each required department/agency (Public Works-Bonding, Planning, LTSWMP, LDP & SWPPP, Engineering, Water/Meter Set, Fire, Backflow Technician, and — as needed — Jordan Basin Improvement District, Salt Lake County Health Department, State Boiler Inspector, State Elevator Inspector, and Special Inspection Agency) before a Certificate of Occupancy is issued.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Rough-In (MEP)
After framing and rough-in mechanical, electrical, and plumbing work
- 2
Final
All work complete; space approved for occupancy under the tenant's use classification
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify utility disconnects are complete and asbestos/lead clearance is obtained before work begins.
- 2
Final / Site Clear
Site cleared, foundation removed or capped, erosion control in place.
Applies to: Mechanical / HVAC Permit
- 1
Mechanical Rough-In
After all duct, vents, flues, and combustion air are installed that will not be exposed for final.
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional.
Applies to: Roofing Permit (Re-Roof)
- 1
Deck / Substrate
After tear-off — verify sheathing condition, replace damaged decking before proceeding.
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern.
Applies to: Sign Permit
- 1
Monument Sign Footing
Verification of stamped engineered footing for monument/freestanding signs before or during construction.
- 2
Final
Completed sign matches approved plans — dimensions, illumination, and placement verified.
Applies to: Solar Panel Permit
- 1
Electrical Rough-In
Conduit runs, wire sizing, disconnect placement. Provide approved photos of rough wiring, roof rack bonding, all junction boxes, flashing, bonding, and grounding per Riverton's solar inspection requirements.
- 2
Final
Panel mounting, racking attachment, roof penetration sealing, electrical connections verified. A company representative familiar with the installation must be on site. Verify all tags, signs, stickers, overcurrent protections, and components per the adopted NEC.
Final inspection only: EV Charger / EVSE Permit, Fire Sprinkler & Fire Alarm Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Riverton building permits
Get alerts for Riverton
We'll email you when Riverton's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.