Inspection sequence, scheduling, and re-inspection fees for building permits in Riverton, Utah.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
12830 S Redwood Road, Room 105, Riverton, UT 84065
Phone
(801) 208-3138
Office hours
Mon–Fri 8:00 AM – 5:00 PM

Published scheduling rules

  • All inspection requests must be made at least one working day in advance, before 1:00 PM — call (801) 208-3138. (Residential Building Permit)
  • Inspections must be requested at least one working day in advance before 1:00 PM — call (801) 208-3138. (Roofing Permit (Re-Roof))
  • All inspection requests must be made at least one working day in advance before 1:00 PM at (801) 208-3138. (General)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Temporary Power

    After pedestal/panel and GFCI outlets are installed and grounding electrode system is visible.

  2. 2

    Footing

    After footings have been dug and rebar has been placed.

  3. 3

    Foundation

    After forms have been set and rebar is placed and supported with 3-inch clearance to earth.

  4. 4

    Underground Plumbing

    After all pipes have been installed and system is being tested and before backfilling.

  5. 5

    Underground Electrical

    After all conduit is installed and metal joints protected.

  6. 6

    Underground Mechanical

    After all duct is installed and sloped to an approved location.

  7. 7

    Underground Gas

    After gas line is installed, tracer wire is placed and gas lines are being tested.

  8. 8

    Plumbing Rough-In

    After all plumbing drains, vents, and water lines are installed and being tested.

  9. 9

    Electrical Rough-In

    After all electrical wires and boxes are installed.

  10. 10

    Mechanical Rough-In

    After all duct, vents, flues, and combustion air are installed that will not be exposed for final.

  11. 11

    Framing

    After plumbing, electrical, and mechanical have been installed and framing is completed, including windows and doors. Before any weather barrier is installed.

  12. 12

    Insulation

    After insulation (except attic blown-in) has been installed, including foam at windows, doors, and top and bottom plate penetrations.

  13. 13

    Final

    After building is complete and ready for occupancy. Includes grading, concrete, address, and landscaping if required. Engineering and Land Disturbance Permit approval are needed.

Applies to: Accessory Dwelling Unit (ADU)

  1. 1

    Foundation

    Footings, forms, rebar — before concrete pour.

  2. 2

    Framing

    Structure, fire separation, egress windows.

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed.

  4. 4

    Insulation

    Insulation and vapor barrier before drywall.

  5. 5

    Final

    All work complete, smoke/CO detectors, address posted, ready for occupancy.

Applies to: Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, egress window wells and openings verified.

  2. 2

    MEP Rough-In

    Electrical, plumbing, and HVAC rough-ins before walls closed.

  3. 3

    Insulation

    Insulation on exterior walls (except attic blown-in), including foam at windows, doors, and plate penetrations.

  4. 4

    Final

    Drywall, fixtures, smoke and CO detectors, and all finishes complete.

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Underground / Rough-In (MEP)

    Before backfill and before closing walls or ceilings

  3. 3

    Framing

    After framing, sheathing, and rough-in mechanical/electrical/plumbing

  4. 4

    Final

    All work complete — certificate of occupancy issued upon passing final inspection

Applies to: Electrical Permit

  1. 1

    Underground Electrical

    After all conduit is installed and metal joints protected.

  2. 2

    Electrical Rough-In

    After all electrical wires and boxes are installed, before walls are closed.

  3. 3

    Power to Panel

    After grounding electrode system and main breakers are installed.

  4. 4

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled.

Applies to: Deck Permit

  1. 1

    Footings

    Verify footing depth (below 30-inch frost line), diameter, and rebar before concrete pour.

  2. 2

    Framing

    Posts, beams, joists, ledger connection, and hardware verified.

  3. 3

    Final

    Decking, stairs, guards, and railings complete. Guards required when deck surface is 30 inches or more above grade.

Applies to: Plumbing Permit

  1. 1

    Underground Plumbing

    After all pipes have been installed and system is being tested, before backfilling.

  2. 2

    Plumbing Rough-In

    After all plumbing drains, vents, and water lines are installed and being tested.

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified.

Applies to: Change of Use / Certificate of Occupancy Compliance

  1. 1

    Zoning Verification (Planning Department)

    Development Services/Planning confirms the proposed use complies with Riverton's zoning ordinance — required before a business license is issued for the new use.

  2. 2

    Certificate of Occupancy Commercial Checklist Sign-offs

    For new construction or an occupancy-classification change, the Building Official must receive electronic approval from each required department/agency (Public Works-Bonding, Planning, LTSWMP, LDP & SWPPP, Engineering, Water/Meter Set, Fire, Backflow Technician, and — as needed — Jordan Basin Improvement District, Salt Lake County Health Department, State Boiler Inspector, State Elevator Inspector, and Special Inspection Agency) before a Certificate of Occupancy is issued.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Rough-In (MEP)

    After framing and rough-in mechanical, electrical, and plumbing work

  2. 2

    Final

    All work complete; space approved for occupancy under the tenant's use classification

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete and asbestos/lead clearance is obtained before work begins.

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped, erosion control in place.

Applies to: Mechanical / HVAC Permit

  1. 1

    Mechanical Rough-In

    After all duct, vents, flues, and combustion air are installed that will not be exposed for final.

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional.

Applies to: Roofing Permit (Re-Roof)

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition, replace damaged decking before proceeding.

  2. 2

    Final

    Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern.

Applies to: Sign Permit

  1. 1

    Monument Sign Footing

    Verification of stamped engineered footing for monument/freestanding signs before or during construction.

  2. 2

    Final

    Completed sign matches approved plans — dimensions, illumination, and placement verified.

Applies to: Solar Panel Permit

  1. 1

    Electrical Rough-In

    Conduit runs, wire sizing, disconnect placement. Provide approved photos of rough wiring, roof rack bonding, all junction boxes, flashing, bonding, and grounding per Riverton's solar inspection requirements.

  2. 2

    Final

    Panel mounting, racking attachment, roof penetration sealing, electrical connections verified. A company representative familiar with the installation must be on site. Verify all tags, signs, stickers, overcurrent protections, and components per the adopted NEC.

Re-inspection fees

Residential Building PermitRe-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Electrical PermitRe-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Plumbing PermitRe-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Mechanical / HVAC PermitRe-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Roofing Permit (Re-Roof)Re-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Solar Panel PermitRe-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Deck PermitRe-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Basement Finish PermitRe-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Demolition PermitRe-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Accessory Dwelling Unit (ADU)Re-Inspection Fee · Riverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence
Commercial Building PermitRe-Inspection Fee · Riverton City FY2026-27 Adopted Fee Schedule, line 180
$50.00 per occurrence
Commercial Tenant Improvement / Tenant Finish PermitRe-Inspection Fee · Riverton City FY2026-27 Adopted Fee Schedule, line 180
$50.00 per occurrence
Change of Use / Certificate of Occupancy ComplianceRe-Inspection Fee · Riverton City FY2026-2027 Adopted Fee Schedule, BUILDING section, line 180.
$50.00 per occurrence

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Riverton building permits

Get alerts for Riverton

We'll email you when Riverton's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.