Residential Building Permit — Riverton, Utah · Requirements sheet
Verified 2026-06-30 · Source: https://www.rivertonutah.gov/building/applications.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit in Riverton, Utah
Required for new residential construction, additions, structural alterations, and any work regulated by the adopted International Building Code or International Residential Code in Riverton. Riverton City Code § 15.10.010 adopts the state-current building codes by reference.
Verified 2026-06-30 · Source
When you need this permit
- New single-family dwelling or multi-family construction
- Additions or structural modifications to any existing structure
- Enlarging, altering, repairing, moving, or demolishing any building or structure
- Installing, enlarging, altering, repairing, or replacing electrical, gas, mechanical, or plumbing systems
- NOTE: A Lot-Specific Geotechnical Soils Report is required on all new single-family dwelling permits — rivertonutah.gov/building/index.php
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Temporary Power
After pedestal/panel and GFCI outlets are installed and grounding electrode system is visible.
- 2
Footing
After footings have been dug and rebar has been placed.
- 3
Foundation
After forms have been set and rebar is placed and supported with 3-inch clearance to earth.
- 4
Underground Plumbing
After all pipes have been installed and system is being tested and before backfilling.
- 5
Underground Electrical
After all conduit is installed and metal joints protected.
- 6
Underground Mechanical
After all duct is installed and sloped to an approved location.
- 7
Underground Gas
After gas line is installed, tracer wire is placed and gas lines are being tested.
- 8
Plumbing Rough-In
After all plumbing drains, vents, and water lines are installed and being tested.
- 9
Electrical Rough-In
After all electrical wires and boxes are installed.
- 10
Mechanical Rough-In
After all duct, vents, flues, and combustion air are installed that will not be exposed for final.
- 11
Framing
After plumbing, electrical, and mechanical have been installed and framing is completed, including windows and doors. Before any weather barrier is installed.
- 12
Insulation
After insulation (except attic blown-in) has been installed, including foam at windows, doors, and top and bottom plate penetrations.
- 13
Final
After building is complete and ready for occupancy. Includes grading, concrete, address, and landscaping if required. Engineering and Land Disturbance Permit approval are needed.
See the full Riverton inspection guide — scheduling & re-inspection fees →
Tips
- All inspection requests must be made at least one working day in advance, before 1:00 PM — call (801) 208-3138.
- Submit all permit applications, plans, and engineering documents digitally to building@rivertonutah.gov. For commercial inquiries contact Mark Smith (Chief Building Official) at 801-208-3111; for residential contact Kenneth Leany at 801-208-3123.
- A Lot-Specific Geotechnical Soils Report is required on ALL new single-family dwelling and commercial permits in Riverton — budget for this in your pre-construction timeline.
- A Land Disturbance Permit from Riverton's Stormwater Division (stormwater@rivertonutah.gov) is required before any new construction building permit is approved.
- Riverton City Code § 15.10.010 adopts the current state-approved building codes by reference. As of July 1, 2026, the 2024 IBC, IPC, IMC, IFGC, and IECC are in effect.
- For sewer connections contact South Valley Sewer District at (801) 571-1166.
- Provide approved plans, engineering letters, specifications, truss specs, REScheck, and Manual J&D at all inspections.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Riverton
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Riverton project checklist
Describe your project once and get every permit, document, and fee it triggers in Riverton — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →