Demolition Permit — Riverton, Utah · Requirements sheet
Verified 2026-06-30 · Source: https://www.rivertonutah.gov/building/applications.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Riverton, Utah
Required for partial or complete demolition of structures in Riverton. Must include utility disconnection letters from all four utility providers and an asbestos/lead clearance letter from Utah DAQ before the permit is issued.
Verified 2026-06-30 · Source
When you need this permit
- Complete demolition of any structure
- Partial demolition involving structural elements
- Removal of load-bearing walls
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition
Verify utility disconnects are complete and asbestos/lead clearance is obtained before work begins.
- 2
Final / Site Clear
Site cleared, foundation removed or capped, erosion control in place.
See the full Riverton inspection guide — scheduling & re-inspection fees →
Tips
- Riverton requires formal disconnect letters from all four utilities (Rocky Mountain Power, Enbridge Gas, Riverton City Water, and Jordan Basin Improvement District) before a demolition permit is issued — per rivertonutah.gov/building/applications.php.
- An asbestos and lead survey letter from the Utah Division of Air Quality (801-536-4000) is required, as is a pre-demo letter from Salt Lake County Health.
- The demolition permit flat fee is $50 — one of Riverton's lowest permit fees.
- Notify adjacent property owners before demolition; Riverton may also require erosion control for the cleared site.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fee schedules
Applications & forms
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Riverton's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Riverton yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Riverton lands. Privacy.
Other permits in Riverton
Demolition Permit in other cities
Compare demolition permit fees across Utah →
Look up this fee in a different city →