Demolition Permit in Riverton, Utah

Required for partial or complete demolition of structures in Riverton. Must include utility disconnection letters from all four utility providers and an asbestos/lead clearance letter from Utah DAQ before the permit is issued.

Verified 2026-06-30 · Source

When you need this permit

  • Complete demolition of any structure
  • Partial demolition involving structural elements
  • Removal of load-bearing walls

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 7 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition PermitRiverton City FY2025-26 Adopted Fee Schedule, line 181
$50.00 flat fee
Re-Inspection FeeRiverton City FY2025-26 Adopted Fee Schedule, line 180
$50.00 per occurrence

Review timeline

Plan reviewTypical estimate — confirm current times with the Riverton building department
~5–14 business days

How long did your Demolition Permit permit actually take in Riverton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete and asbestos/lead clearance is obtained before work begins.

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped, erosion control in place.

See the full Riverton inspection guide — scheduling & re-inspection fees →

Tips

  • Riverton requires formal disconnect letters from all four utilities (Rocky Mountain Power, Enbridge Gas, Riverton City Water, and Jordan Basin Improvement District) before a demolition permit is issued — per rivertonutah.gov/building/applications.php.
  • An asbestos and lead survey letter from the Utah Division of Air Quality (801-536-4000) is required, as is a pre-demo letter from Salt Lake County Health.
  • The demolition permit flat fee is $50 — one of Riverton's lowest permit fees.
  • Notify adjacent property owners before demolition; Riverton may also require erosion control for the cleared site.

Frequently asked questions

Yes. Riverton requires a demolition permit for all structural demolitions. The flat fee is $50 per the FY2025-26 Adopted Fee Schedule. You must provide utility disconnect letters from Rocky Mountain Power, Enbridge Gas, Riverton City Water, and Jordan Basin Improvement District, plus asbestos/lead letters from Utah DAQ and Salt Lake County Health.

In Riverton, the published Demolition Permit is: $50.00 flat fee. Additional published fees: Re-Inspection Fee — $50.00 per occurrence. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for a demolition permit in Riverton typically runs 5–14 business days. This is an estimate, not a published figure — confirm current review times with Riverton City Building Division at (801) 208-3138.

You'll need: Building Permit Application; Letter of utility disconnect — Rocky Mountain Power; Letter of utility disconnect — Enbridge Gas; Letter of utility disconnect — Riverton City Water; Letter of utility disconnect — Jordan Basin Improvement District (Sewer); Asbestos and Lead Survey Letter — Utah Division of Air Quality; Health Department Pre-Demo Letter. See the required-documents checklist on this page for details on each.

Riverton requires 2 inspection(s) for a demolition permit, in order: Pre-Demolition, Final / Site Clear. Schedule each through Riverton City Building Division ((801) 208-3138).

Apply through Riverton City Building Division at 12830 S Redwood Road, Room 105, Riverton, UT 84065. Phone: (801) 208-3138, email: building@rivertonutah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.rivertonutah.gov/building/.

Riverton, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — Riverton City Code § 15.10.010 (dynamic adoption clause: 'the most recent version... adopted by the state of Utah... [with] adoption of updated versions by the state of Utah after the date of this chapter [having] the effect of updating Riverton City's building code(s)'); Utah Code § 15A-2-103(1)(a); effective 2026-07-01, superseded the 2021 edition that had been in effect since July 1, 2023; 2021 International Residential Code (IRC), including Appendices AE and AQ — Riverton City Code § 15.10.010; Utah Code § 15A-2-103(1)(b)/(c)/(k); unchanged by the 7/1/2026 code cycle; 2024 International Plumbing Code (IPC) — Riverton City Code § 15.10.010; Utah Code § 15A-2-103(1)(d); effective 2026-07-01, superseded the 2021 edition that had been in effect since July 1, 2023; 2024 International Mechanical Code (IMC) — Riverton City Code § 15.10.010; Utah Code § 15A-2-103(1)(e); effective 2026-07-01, superseded the 2021 edition that had been in effect since July 1, 2023; 2024 International Fuel Gas Code (IFGC) — Riverton City Code § 15.10.010; Utah Code § 15A-2-103(1)(f); effective 2026-07-01, superseded the 2021 edition that had been in effect since July 1, 2023; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide adoption; unchanged by the 7/1/2026 code cycle; also listed on rivertonutah.gov/building/code.php; Residential provisions of Chapter 11, Energy Efficiency, of the 2015 International Residential Code — rivertonutah.gov/building/code.php item 7 (verified live 2026-07-16, wording unchanged from before this fix); Riverton's own residential-energy baseline citation, distinct from the statewide IECC line below and NOT altered by the 7/1/2026 code cycle per the city's own current page; 2024 International Energy Conservation Code (IECC), commercial provisions — Riverton City Code § 15.10.010; Utah Code § 15A-2-103(1)(h); effective 2026-07-01, superseded the 2021 edition that had been in effect since July 1, 2023; 2024 International Existing Building Code (IEBC) — Riverton City Code § 15.10.010; Utah Code § 15A-2-103(1)(i); effective 2026-07-01, superseded the 2021 edition that had been in effect since July 1, 2023; ICC/ANSI A117.1-2009 — rivertonutah.gov/building/code.php item 10; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective 2026-07-01, superseded the 2021 edition that had been in effect since July 1, 2023; NOTE (verified 2026-07-16): Riverton's own 'Building Codes in Use in Riverton City' list at rivertonutah.gov/building/code.php is headed 'Effective July 1, 2023' and still enumerates the 2021 IBC/IRC/IPC/IMC/IFGC, 2021 IEBC, and 2021 ISPSC, plus 'Commercial provisions of the 2021 International Energy Conservation Code' — that page has NOT been updated for the 7/1/2026 code cycle. However, Riverton City Code § 15.10.010 itself dynamically adopts 'the most recent version... adopted by the state of Utah' and states that state updates automatically update Riverton's code with no separate city action required — so as a matter of law the 2024 editions already govern in Riverton regardless of the outdated summary page. Confirmed directly against Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027) at le.utah.gov.. Local amendments apply — see the Riverton overview page for the full list.

Riverton requires: (1) asbestos and lead survey letter from Utah Division of Air Quality (call 801-536-4000 or email Asbestos@utah.gov / leadbasedpaint@utah.gov); and (2) a pre-demo letter from Salt Lake County Water Quality Bureau (385-468-3862). Both are required before the demolition permit is issued.

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Riverton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.