Demolition Permit in Unincorporated Salt Lake County, Utah
Required for partial or complete demolition of structures in unincorporated Salt Lake County, including utility disconnection coordination and any required asbestos surveys. Issued by MSD; fee is valuation-based on declared demolition cost.
Verified 2026-07-01 · Source
When you need this permit
- Complete demolition of any structure
- Partial demolition involving structural elements
- Removal of load-bearing walls
- Demolition of structures with potential asbestos or lead paint (pre-1980 construction)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Grounded and re-confirmed 2026-07-01 against the current MSD FY2025/FY2026 Fee Schedule PDF (msd.utah.gov/DocumentCenter/View/1471/FY-2026-SLCo-Fee-Schedule), Building Permit Fees table, page 5… Show full citationHide
Grounded and re-confirmed 2026-07-01 against the current MSD FY2025/FY2026 Fee Schedule PDF (msd.utah.gov/DocumentCenter/View/1471/FY-2026-SLCo-Fee-Schedule), Building Permit Fees table, page 5 (rendered to PNG and read positionally): Demolition Permit fee is listed as "Varies" with footnote (d): "Permit fees for demolition and window/door replacement are based on declared valuation," applied to the standard building-permit valuation fee table (same schedule as residential-building-permit). This is a published, cited valuation-based fee — verified per the assessment rule.Review timeline
Inspection process
- 1
Pre-Demolition
Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins.
- 2
Final / Site Clear
Site cleared, foundation removed or capped, erosion control in place.
See the full Unincorporated Salt Lake County inspection guide — scheduling & re-inspection fees →
Tips
- Utilities must be formally disconnected by the respective utility companies before demolition begins — MSD will verify.
- Structures built before approximately 1980 may require a NESHAP asbestos inspection before a demolition permit is issued — coordinate with Utah DEQ.
- MSD offers pre-inspection services to assess damage and determine permits needed after a fire or disaster.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fee schedules
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Salt Lake County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Unincorporated Salt Lake County's permit history is searchable by address
11,396 permits in our copy of Unincorporated Salt Lake County's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Unincorporated Salt Lake County has issued.
All 11,396 carry an issued date, running from 2021 to 2026.
Other permits in Unincorporated Salt Lake County
Demolition Permit in other cities
Compare demolition permit fees across Utah →
Look up this fee in a different city →