How to schedule

Inspections are requested through the building department below.

Address
110 S. Center Street, Santaquin, UT 84655
Phone
(801) 754-1011
Email
Office hours
Mon–Thu 9:00 AM – 5:00 PM, Fri 9:00 AM – 1:00 PM

Published scheduling rules

  • Inspections must be scheduled at least 24 hours in advance by calling (801) 754-1011 during office hours (Mon–Thu 9 AM–5 PM, Fri 9 AM–1 PM); to get a Monday inspection, call by 1 PM the preceding Friday. (Residential Building Permit)

Inspection sequence

Applies to: Residential Building Permit

  1. 1

    Footings / Setbacks

    Required Building Inspection Checklist item 1, per Santaquin City's official checklist.

  2. 2

    Foundation

    Required Building Inspection Checklist item 2.

  3. 3

    Under-Slab Plumbing / Under-Slab Heating

    Required Building Inspection Checklist items 3–4.

  4. 4

    Water Lateral / Sewer Lateral

    Required Building Inspection Checklist items 5–6.

  5. 5

    Temporary Power / Underground Power Trench / Permanent Power

    Required Building Inspection Checklist items 7–9.

  6. 6

    Bond Beam / Shear Panels / Tie Downs

    Required Building Inspection Checklist items 10–11.

  7. 7

    4-Way (Rough Plumbing, Rough Electrical, Rough Heating, Framing)

    Combined rough-in inspection, Required Building Inspection Checklist item 12.

  8. 8

    Gas Piping / Masonry Veneer-Moisture Barrier / Stucco-Lath / Drywall / Insulation

    Required Building Inspection Checklist items 13–17; an Insulation Certificate must be attached.

  9. 9

    Water Meter

    Required Building Inspection Checklist item 18.

  10. 10

    Final

    Required Building Inspection Checklist item 19, including site grading, curb & gutter, sidewalk, driveways & streets.

Applies to: Accessory Structure Building Permit

  1. 1

    Footings / Foundation

    Required if the accessory structure has a foundation plan submitted.

  2. 2

    Framing

    Framing inspection per the Required Building Inspection Checklist.

  3. 3

    Final

    Final inspection to close out the accessory-structure permit.

Applies to: Basement Finish Permit

  1. 1

    4-Way (Rough Plumbing, Rough Electrical, Rough Heating, Framing)

    Applicable rough-in inspections for basement finish work, per Santaquin's Required Building Inspection Checklist.

  2. 2

    Insulation / Drywall

    Insulation Certificate must be attached before the insulation inspection; drywall inspection follows framing/rough-in sign-off.

  3. 3

    Final

    Final inspection to close out the basement-finish permit.

Applies to: Commercial Building Permit

  1. 1

    Footings / Foundation

    Before concrete pour, per Santaquin's Required Building Inspection Checklist (items 1–2), applied to any structure type.

  2. 2

    Under-Slab / Rough-In (4-Way)

    Combined rough plumbing, rough electrical, rough heating, and framing inspection per the Required Building Inspection Checklist item 12.

  3. 3

    Final

    Required Building Inspection Checklist item 19, all work complete before occupancy.

Applies to: Solar PV (Photovoltaic) Installation Permit

  1. 1

    Building / Structural Inspection

    Verifies roof or ground-mount structural attachment per submitted plans.

  2. 2

    Electrical Inspection

    Verifies the PV system's electrical tie-in (inverter, disconnect, interconnection wiring) per the 2023 NEC.

  3. 3

    Final

    Final inspection to close out the permit before the system is energized.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural

    Wall sections and rebar verified per submitted plans before close-in, where structural work is part of the scope.

  2. 2

    Final

    All work complete before occupancy.

Re-inspection fees

Residential Building PermitRe-inspection Fee · Santaquin City official Building Permit Fees schedule (Updated 04-02-2026): charged when more than two inspections (one initial + one follow-up) are required for a particular inspection type, or when the job site is not ready at the scheduled time.
$75.00
Commercial Building PermitRe-inspection Fee · Santaquin City official Building Permit Fees schedule (Updated 04-02-2026).
$75.00
Commercial Tenant Improvement / Tenant Finish PermitRe-inspection Fee · Santaquin City official Building Permit Fees schedule (Updated 04-02-2026).
$75.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santaquin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Santaquin building permits

Get alerts for Santaquin

We'll email you when Santaquin's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.