Commercial Tenant Improvement / Tenant Finish Permit in Santaquin, Utah

Required for commercial tenant improvement / tenant finish work in Santaquin. As with new commercial construction, Santaquin's published fee schedule does not maintain a separate tenant-improvement fee line — the same valuation-based Building Permit Fee (from the current IRC Building Valuation Data sheet) applies.

Verified 2026-07-19 · Source

When you need this permit

  • Interior remodel or finish work within existing commercial space
  • Electronic copy of plans and engineering where applicable, site plan, wall section and rebar details where structural work is involved
  • Contractor license number or Owner-Builder Certification Form Owner-builderContractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeSantaquin City official Building Permit Fees schedule (Updated 04-02-2026); the schedule does not publish a distinct tenant-improvement or commercial-remodel line, so the same generic valuation-based fee applies.
Cost based on the valuation of the project, per the current Building Valuation Data sheet from the IRC
Plan Review FeeSantaquin City official Building Permit Fees schedule (Updated 04-02-2026).
65% of the Building Permit Fee
Permit Tracking FeeSantaquin City official Building Permit Fees schedule (Updated 04-02-2026).
$70.00
State Building FeeSantaquin City official Building Permit Fees schedule (Updated 04-02-2026).
1% of Building Permit Fee
Re-inspection FeeSantaquin City official Building Permit Fees schedule (Updated 04-02-2026).
$75.00

Review timeline

Plan reviewSantaquin’s published plan-review target
10–14 business days

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Santaquin?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing / Structural

    Wall sections and rebar verified per submitted plans before close-in, where structural work is part of the scope.

  2. 2

    Final

    All work complete before occupancy.

See the full Santaquin inspection guide — scheduling & re-inspection fees →

Tips

  • Santaquin's fee-schedule PDF labels the $500 Plan Review Deposit 'new construction only,' which creates ambiguity for a tenant-improvement project that is not literally new construction — the Building Permits page's broader statement ('New single-family, multi-family, or commercial permits require a $500.00 Plan Review Deposit') is not itself scoped to exclude tenant improvements, but the discrepancy is not resolved anywhere in Santaquin's published materials. Confirm directly with the Building Department (801-754-1011) whether a specific TI project is billed the deposit.
  • No separate tenant-improvement or commercial-remodel fee line exists in Santaquin's schedule — budget using the same valuation-based Building Permit Fee formula as new construction.
  • No distinct 'Change of Use' or 'Certificate of Occupancy' permit, application, or fee line was found anywhere in Santaquin's published materials as of a direct check on 2026-07-20 — checked the Updated Building Permit Fees PDF (04-02-2026), the Resolution 06-04-2026 consolidated fee schedule, the Building Permits and Business Licensing pages on ut-santaquin.civicplus.com, and the CitizenServe online permit portal, with zero matches for either term. Santaquin's own municipal code (santaquin.municipalcodeonline.com) could not be searched directly — it renders through a JavaScript application that returns no server-side text to automated fetch tools — so a code-level 'Certificate of Occupancy Required' or 'Change of Use' section, if one exists, could not be confirmed or ruled out. Confirm directly with the Building Department, (801) 754-1011, before assuming a tenant use change with no construction scope is (or is not) processed as a standard building permit.

Frequently asked questions

Santaquin requires a commercial tenant improvement / tenant finish permit for: Interior remodel or finish work within existing commercial space; Electronic copy of plans and engineering where applicable, site plan, wall section and rebar details where structural work is involved; Contractor license number or Owner-Builder Certification Form. If your project isn't listed, confirm with Santaquin City Building and Safety Division (Community Development Department) at (801) 754-1011 before starting work.

No distinct tenant-improvement fee line is published. Santaquin applies the same valuation-based Building Permit Fee (from the current IRC Building Valuation Data sheet) plus the standard 65% Plan Review Fee, 1% State Building Fee, and $70 Permit Tracking Fee used for other permit types.

Santaquin's published plan-review target for a commercial tenant improvement / tenant finish permit is 10–14 business days.

You'll need: Online Building Permit Application (Citizenserve Portal); Floor Plan. Depending on your project, Santaquin may also ask for: Electronic Copy of Plans and Engineering (if applicable). See the required-documents checklist on this page for details on each.

Santaquin requires 2 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Framing / Structural, Final. Schedule each through Santaquin City Building and Safety Division (Community Development Department) ((801) 754-1011).

Apply through Santaquin City Building and Safety Division (Community Development Department) at 110 S. Center Street, Santaquin, UT 84655. Phone: (801) 754-1011. Office hours: Mon–Thu 9:00 AM – 5:00 PM, Fri 9:00 AM – 1:00 PM. Official information: https://ut-santaquin.civicplus.com/1479/Building-Permits.

Santaquin, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a); supersedes the 2021 edition previously listed here. Santaquin's Building Department page (live-checked 2026-07-16) states generically that the division enforces 'health, safety, International Building Code, and City Code requirements' without itemizing an edition year.; 2021 International Residential Code (IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 statewide transition. Santaquin's official fee schedule and basement-finish/accessory-structure submittal packets repeatedly reference 'the current Building Valuation Data sheet from the IRC' (a cost-valuation table, not an edition-year assertion).; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not itemized anywhere on Santaquin's own Building Department pages, added here per statute.; 2024 International Plumbing Code (IPC) — CORRECTED: this file previously combined IPC/IMC/IECC into one undated entry described as tracking 'alongside the IBC/IRC,' which is no longer accurate now that IBC (2024), IRC (2021), and these trade codes (2024) diverge in edition year. CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d); Santaquin does not publish a separate municipal amendment to this trade code.; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e); Santaquin does not publish a separate municipal amendment to this trade code.; 2024 International Fuel Gas Code (IFGC) — statewide per Utah Code § 15A-2-103(1)(f); not itemized on Santaquin's own Building Department pages, added here per statute since the City's own materials omit it.; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h); Santaquin does not publish a separate municipal amendment to this trade code.; 2023 National Electrical Code (NEC) — statewide per Utah Code § 15A-2-103(1)(g); MISSING ENTIRELY from this file's prior codesAdopted list despite being a statute-mandated code — added here since electrical work is explicitly listed among Santaquin's permit-required categories (see 'Do You Need a Permit?' form) but no electrical-code edition was itemized anywhere on the City's own pages.; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); not itemized on Santaquin's own Building Department pages, added here per statute since the City's own materials omit it.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — statewide per Utah Code § 15A-2-103(1)(n); not itemized on Santaquin's own Building Department pages, added here per statute since the City's own materials omit it.; Santaquin City Code — local building-permit administration and requirements (permit-required project list, accessory-structure setback/fire-rating rules, sign-permit rules) are published on the Building Department's official pages (ut-santaquin.civicplus.com); the full underlying municipal code text (historically hosted at sterlingcodifiers.com, book_id=303) was not renderable via automated fetch as of this file's verification date (the sterlingcodifiers.com domain did not resolve/timed out on repeated attempts) — the specific requirements below are sourced directly from Santaquin's own Building Department PDFs and pages, not from the codifier mirror.; NOTE (2026-07-16 re-verification): Utah Code § 15A-2-103, version effective 7/1/2026 (superseded 1/1/2027), took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Santaquin's Building Department page (ut-santaquin.civicplus.com/1478/Building-Department) was live-checked 2026-07-16 and states only the generic phrase 'International Building Code' with no edition year and no separate mention of IRC/IPC/IMC/IECC/NEC at all — so no page-vs-statute lag could be detected; the statute is cited directly as governing throughout. This re-verification also corrected a genuine defect: NEC was entirely absent from the prior codesAdopted list, and IPC/IMC/IECC had been lumped into one undated entry implying they track IBC/IRC in lockstep, which stopped being accurate once IBC (2024) and IRC (2021) diverged.. Local amendments apply — see the Santaquin overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santaquin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Santaquin.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.