Residential Building Permit in Santaquin, Utah
Required for new single-family and multi-family residential construction, and for any project that constructs, enlarges, alters, moves, demolishes, or changes a building or structure, per Santaquin City's official 'Do You Need a Permit?' guidance. Fees are valuation-based, calculated from the current IRC Building Valuation Data sheet, plus a 65% plan review fee, 1% state building fee, and applicable impact fees. Rooftop or ground-mounted solar PV installation falls under this general Building Permit (structural mounting) plus the standard electrical-alteration permit requirement — Santaquin does not publish a distinct solar-specific permit type or fee line (confirmed: no 'solar' entry anywhere in the City's official Building Permit Fees schedule, updated 04-02-2026, or its 'Do You Need a Permit?' checklist, both re-checked 2026-07-19); both 'Construct, Enlarge, Alter... a building or structure' and 'Install or Alter Electrical' are marked permit-required on that checklist, and solar falls under those two categories using the same valuation-based fee.
Verified 2026-07-20 · Source
When you need this permit
- New single-family or multi-family residential construction
- Any project that constructs, enlarges, alters, moves, demolishes, or changes a building or structure
- Installation or alteration of electrical, gas, mechanical, or plumbing systems
- Installation of a new furnace, heating, or air conditioning unit
- Plan Review Deposit of $500.00 required up front for new construction (applied to the 65% plan review fee)
- All required documents must be uploaded to the online permit application before the Building Official will review it (first-come, first-served basis)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footings / Setbacks
Required Building Inspection Checklist item 1, per Santaquin City's official checklist.
- 2
Foundation
Required Building Inspection Checklist item 2.
- 3
Under-Slab Plumbing / Under-Slab Heating
Required Building Inspection Checklist items 3–4.
- 4
Water Lateral / Sewer Lateral
Required Building Inspection Checklist items 5–6.
- 5
Temporary Power / Underground Power Trench / Permanent Power
Required Building Inspection Checklist items 7–9.
- 6
Bond Beam / Shear Panels / Tie Downs
Required Building Inspection Checklist items 10–11.
- 7
4-Way (Rough Plumbing, Rough Electrical, Rough Heating, Framing)
Combined rough-in inspection, Required Building Inspection Checklist item 12.
- 8
Gas Piping / Masonry Veneer-Moisture Barrier / Stucco-Lath / Drywall / Insulation
Required Building Inspection Checklist items 13–17; an Insulation Certificate must be attached.
- 9
Water Meter
Required Building Inspection Checklist item 18.
- 10
Final
Required Building Inspection Checklist item 19, including site grading, curb & gutter, sidewalk, driveways & streets.
See the full Santaquin inspection guide — scheduling & re-inspection fees →
Tips
- Inspections must be scheduled at least 24 hours in advance by calling (801) 754-1011 during office hours (Mon–Thu 9 AM–5 PM, Fri 9 AM–1 PM); to get a Monday inspection, call by 1 PM the preceding Friday.
- Job sites must be ready for inspection by 8:00 AM on the requested day — the office does NOT do timed inspections except for Footings, Foundations, or inspections requiring entry into an occupied home (e.g., basement finishing, remodeling).
- Each inspection type (foundation, drywall, etc.) is allowed one first-time inspection plus one follow-up; a third inspection for the same type triggers a $75.00 Re-inspection Fee, payable only by check or cash at the City Office (not accepted on-site).
- New single-family, multi-family, or commercial permits require a $500.00 Plan Review Deposit before the permit moves forward — this is applied to the 65% Plan Review Fee.
- The office accepts checks and cash only for permit-related fees (no card payments noted on the official fee/process pages).
- Call Before You Dig — Blue Stakes of Utah (811) is required before any excavation, per the Building Permits page's Underground Utilities link.
- Solar panel (PV) installations require a building permit (for roof/structural mounting) and are also covered under the 'Install or Alter Electrical' permit-required category — Santaquin does not publish a distinct solar permit type or fee; both use the same valuation-based Building Permit Fee formula as of 2026-07-19.
- EV charger/EVSE installation is electrical work and falls under the same 'Install or Alter Electrical' permit-required category used for solar above — Santaquin's official Building Permit Fees schedule (updated 04-02-2026, purely valuation-based with no trade breakout) and 'Do You Need a Permit?' checklist contain no EV-charger-specific or electric-vehicle line item (re-checked 2026-07-20); a charger installation is billed under the same valuation-based Building Permit Fee formula, not a dedicated EV rate.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Santaquin building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Santaquin
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Santaquin project checklist
Describe your project once and get every permit, document, and fee it triggers in Santaquin — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →