Inspection sequence, scheduling, and re-inspection fees for building permits in Washington City, Utah.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
111 N 100 E, Washington, UT 84780
Phone
(435) 656-6326
Email
Office hours
Mon–Thu 7:30am–5:30pm, Fri 8am–Noon

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    SWPPP Notice of Intent (NOI)

    Required for initiation of the Stormwater Permit; must be scheduled at footings, per the Commercial New Build and Additions submittal requirements.

  2. 2

    Foundation / Footing

    Before concrete pour, per standard IBC inspection sequence.

  3. 3

    Structural / Framing

    Framing and structural elements, including truss layout and truss packet conformance, verified against submitted structural calculations.

  4. 4

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans.

  5. 5

    Final / Certificate of Occupancy

    Final inspection and approvals required from Building, Planning, Fire, Public Works, Power, Parks, and St. George Treatment (and any other permit-reviewing party) before Certificate of Occupancy is released. Four certifications — Soils Compliance Letter, Insulation Certification, Stucco Certification, and Termite Certification — must all be uploaded to the Building Permit before a CO can be released.

Applies to: Residential Building Permit (Single Family)

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete — inspections scheduled through the Builder Account on CityInspect

Applies to: Accessory Dwelling Unit (ADU)

  1. 1

    Foundation

    Footings, forms, rebar before concrete pour

  2. 2

    Framing

    Structure and fire separation from primary unit

  3. 3

    Final

    All work complete, deed restriction on file, ready for occupancy

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural (if applicable)

    Wall construction and any structural modifications verified before close-in, where applicable to the scope of work.

  2. 2

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in verified against submitted plans.

  3. 3

    Final

    Accessible route of travel to the remodeled area and all finishes verified before occupancy; Building, Planning, Fire, Public Works, Power, and other reviewing departments sign off per Washington City's Packet Review process.

Applies to: Swimming Pool Permit

  1. 1

    Excavation / Steel

    Pool shell excavation, rebar, and plumbing before shotcrete/gunite

  2. 2

    Barrier

    Pool fencing and gates verified per Washington City Code Title 4 Ch. 6 and ISPSC 305.3.3/305.3.4

  3. 3

    Final

    Pool complete, equipment operational, barriers in place

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify asbestos clearance and any required Fire Department explosives approval before work begins

  2. 2

    Final / Site Clear

    Site cleared per WCSW requirements

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, lockable disconnect placement before energizing

  2. 2

    Final

    Panel mounting, electrical connections, and point of utility connection verified

Washington City building permits

Get alerts for Washington City

We'll email you when Washington City's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.