Required for solar photovoltaic installation in Washington City. Washington City imposes two local prerequisites not found in the sibling St. George or Washington County files: installer pre-approval by the Washington City Power Department, and mandatory third-party plan pre-approval.

Verified 2026-07-19 · Source

When you need this permit

  • Installer must be an approved installer with the Washington City Power Department PRIOR to submitting for permit (required as of May 15, 2023)
  • All plans must be pre-approved by an approved third-party reviewer PRIOR to submitting for permit (required as of July 1, 2023)
  • Renewable Resource Agreement (RRA) with original notarized property-owner signature required for properties in the Washington City Power service area
  • Properties in the Dixie Power service area instead require a Dixie Power Net Meter Agreement

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar PermitWashington City's Solar Permit Submittal Requirements page (washingtonutah.gov/development/building/solarpermitrequirements, re-verified 2026-07-19; formerly hosted at washingtoncity.org, which now 301-redirects to the same page on the washingtonutah.gov domain) requires a 'Valuation' field correlated to the RRA project cost, but does not publish a separate flat solar-specific fee — assessed on the same Building Permit Fee Table as other permit types. This is a grounded valuation-based fee, not an estimate.
Valuation-based per the Washington City Building Permit Fee Table (see residential building permit fees above)

Review timeline

Plan review
Not published — contact the department

How long did your Solar Panel Permit permit actually take in Washington City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, lockable disconnect placement before energizing

  2. 2

    Final

    Panel mounting, electrical connections, and point of utility connection verified

See the full Washington City inspection guide — scheduling & re-inspection fees →

Tips

  • Washington City requires solar installers to be pre-approved by the Washington City Power Department (435-656-6329) before they can even submit a permit application — this is a local requirement not seen in the sibling St. George or Washington County files.
  • Washington City additionally requires all solar plans to be pre-approved by an approved third-party reviewer before permit submittal, effective July 1, 2023.
  • The original notarized Renewable Resource Agreement must be physically delivered to the Washington City Power Department — a digital signature (docu-sign) is explicitly not accepted.

Frequently asked questions

Yes — two layers. As of May 15, 2023, your installer must be pre-approved by the Washington City Power Department. As of July 1, 2023, your plans must also be pre-approved by an approved third-party reviewer. Both must happen before you submit the permit application. Contact the Power Department at (435) 656-6329.

In Washington City, the published Solar Permit is: Valuation-based per the Washington City Building Permit Fee Table (see residential building permit fees above). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Washington City does not publish a plan-review timeline for this permit. Contact Washington City Building Department at (435) 656-6326 for current turnaround.

You'll need: Online Permit Application (CityInspect Builder Account); Renewable Resource Agreement; Site Plan / Single-Line Drawing. Depending on your project, Washington City may also ask for: Dixie Power Net Meter Agreement. See the required-documents checklist on this page for details on each.

Washington City requires 2 inspection(s) for a solar panel permit, in order: Rough Electrical, Final. Schedule each through Washington City Building Department ((435) 656-6326).

Apply through Washington City Building Department at 111 N 100 E, Washington, UT 84780. Phone: (435) 656-6326. Office hours: Mon–Thu 7:30am–5:30pm, Fri 8am–Noon. Official information: https://washingtonutah.gov/development/building.

Washington City, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(a). Washington City Building Department's own 'Climatic and Geographic Design Criteria' notice was live-checked 2026-07-16 (raw HTML, not an AI summary) and STILL displays '2021 IBC' — the city page has NOT been updated to reflect the statewide 7/1/2026 transition; 2021 Utah State Residential Code (based on IRC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(b) did not change this edition in the 7/1/2026 amendment. Washington City's own page (live-checked 2026-07-16) correctly still shows '2021 UTAH STATE RESIDENTIAL CODE'; Appendix AQ of the 2021 IRC — statewide per Utah Code § 15A-2-103(1)(c); not separately itemized on Washington City's own page, added here per statute; 2024 International Plumbing Code (IPC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(d). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 IPC' — the city page has NOT been updated; 2024 International Mechanical Code (IMC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 IMC' — the city page has NOT been updated; 2024 International Fuel Gas Code (IFGC, listed on city page as 'IFCI') — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(f). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 IFCI' — the city page has NOT been updated; 2023 National Electrical Code (NEC) — REMAINS CURRENT; Utah Code § 15A-2-103(1)(g) did not change this edition in the 7/1/2026 amendment. Washington City Building Department page explicitly updated 'MAY 7 2025 UPDATE OF ADOPTED CODES BY THE STATE OF UTAH: 2023 NEC code update' (superseding the previously listed 2020 NEC, still shown struck-through/superseded on the live page as of 2026-07-16); this is one of the few Washington County-area jurisdiction pages independently confirmed current on the electrical code edition, not just inferred from state law; 2024 International Energy Conservation Code (IECC), single unsplit statewide edition — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(h). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 IECC' — the city page has NOT been updated; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — CURRENT statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(n). Washington City's own page was live-checked 2026-07-16 and STILL displays '2021 ISPSC', and the city's Swimming Pool permit instructions (ISPSC sections 305.3.3/305.3.4, 807, 809, 323) likewise still cite the 2021 edition — the city has NOT updated either page; 2024 International Existing Building Code (IEBC) — statewide per Utah Code § 15A-2-103(1)(i); NOT listed at all on Washington City's own Building Department page (live-checked 2026-07-16), added here per statute since the City's own materials omit it entirely; ICC A117.1-2009 or 2017 (Accessibility Standard) — listed on Washington City Building Department page; not part of Utah Code § 15A-2-103's construction-code list, left unchanged; 2018 IBC construction-type valuation table (ICC Building Valuation Data) — used directly in the city's own published 'Square Foot Construction Costs Table B' on its fee schedule; a fee-calculation reference table, not a code edition, left unchanged; NOTE (2026-07-16 re-verification): The Utah Code § 15A-2-103 version effective 7/1/2026 (superseded 1/1/2027) took effect 15 days before this re-verification. IBC/IPC/IMC/IFGC/IECC/IEBC/residential ISPSC are now 2024 statewide; IRC (2021) and NEC (2023) did NOT change. Washington City's own Building Department page ('Climatic and Geographic Design Criteria' notice) was independently re-fetched 2026-07-16 (raw HTML, not an AI summary, to guard against summarizer fabrication) and STILL displays 2021 editions for IBC/IMC/IPC/IFCI(IFGC)/IECC/ISPSC — confirmed NOT updated to reflect the statutory transition, unlike its NEC line which was separately updated in May 2025. This file now states the governing statutory codes (2024/2021/2023 editions per subsection) as current per Utah's statewide-mandatory code regime (Utah Code § 15A-1-204), while preserving the City's own (lagging) page text above as historical/local-document context. The Utah Code § 15A-2-103 citation in the sources array below has been updated to the current in-force version link. Local amendments apply — see the Washington City overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Washington City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.