Solar Panel Permit in Herriman, Utah
Required for installation of rooftop or ground-mounted solar photovoltaic systems and battery storage in Herriman. The permit fee is a flat residential solar fee per the Master Fee Schedule.
Verified 2026-06-30 · Source
When you need this permit
- Rooftop solar panel installation
- Ground-mounted solar array installation
- Battery storage system installation (e.g., Powerwall)
- Electrical service upgrade for solar interconnection
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
See the full Herriman inspection guide — scheduling & re-inspection fees →
Tips
- Herriman charges a flat $118 residential solar permit fee per the Master Fee Schedule (effective July 1, 2026) — not valuation-based.
- Rocky Mountain Power interconnection approval is required before the system can be energized.
- The 2023 NEC (adopted in Herriman) governs solar electrical installations including rapid shutdown requirements.
- A separate electrical permit may be required for the wiring/inverter portion — confirm with Herriman Building at (801) 446-5327.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Herriman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Herriman's permit history is searchable by address
29,242 permits in our copy of Herriman's register — searchable by street address, with permit type, status, issued date and valuation where the city publishes them. This is what we hold, not a statement of everything Herriman has issued.
27,701 of these 29,242 permits — 94.7% — carry an issued date, and those run from 1985 to 2026. The remaining 1,541 have no date at all.
Other permits in Herriman
Solar Panel Permit in other cities
Compare solar panel permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Herriman project checklist
Describe your project once and get every permit, document, and fee it triggers in Herriman — in one checklist. Free, for any city and any number of projects.
Get started →