Herriman building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Herriman, Utah.
Verified 2026-07-01 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 5355 W Herriman Main St, Herriman, UT 84096
- Phone
- (801) 446-5327
- Office hours
- Mon–Fri 7:30 AM – 5:30 PM (call before 4:00 PM for inspection requests)
- Website
- Official site
Published scheduling rules
- Herriman Building Department hours are 7:30 AM – 5:30 PM Monday–Friday; call before 4:00 PM for inspection requests. (Residential Building Permit)
- The re-inspection fee in Herriman is $265 — among the higher fees in Salt Lake County; ensure work is ready before scheduling inspections. (General)
- Call before 4:00 PM to request an inspection for the next business day — inspections are done Monday through Friday, 8:00 AM – 4:30 PM per the FAQs. (General)
Inspection sequence
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window wells and openings
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls, vapor barrier placement
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Underground / Rough-In (MEP)
Before backfill and before closing walls or ceilings
- 3
Framing
After framing, sheathing, and rough-in mechanical/electrical/plumbing
- 4
Final
All work complete — certificate of occupancy issued upon passing final inspection
Applies to: Residential Building Permit
- 1
Foundation
Before concrete pour — verify forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and roof — before insulation
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete, ready for occupancy
Applies to: Swimming Pool Permit
- 1
Excavation / Steel
Pool shell excavation, rebar, and plumbing before gunite/shotcrete
- 2
Electrical / Bonding
Pool bonding grid, equipment connections, GFCI protection per 2023 NEC Article 680
- 3
Barrier
Pool fence/barrier — 48-inch minimum height, self-closing/self-latching gates per the residential provisions of the 2024 ISPSC (Utah Code § 15A-2-103(1)(n), effective 7/1/2026); Herriman's own Building Codes and Design Criteria page still lists the 2021 ISPSC as of live-check 2026-07-16, but the statute controls
- 4
Final
Pool complete, filled, equipment operational, all barriers in place
Applies to: Deck Permit
- 1
Footings
Verify footing depth (minimum 30 inches — Herriman frost depth), diameter, and rebar before concrete pour
- 2
Framing
Posts, beams, joists, ledger connection, and hardware
- 3
Final
Decking, stairs, guards, and railings complete — 36-inch guard height required when deck is over 30 inches above grade
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: Plumbing Permit
- 1
Underground / Slab
Before concrete pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed — pressure test required
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Rough-In (MEP)
After framing and rough-in mechanical, electrical, and plumbing work
- 2
Final
All work complete; space approved for occupancy under the tenant's use classification
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped, site conditions verified
Applies to: EV Charger / EVSE Permit
- 1
Rough-In / Circuit
New dedicated EV charger circuit verified before closing walls, if applicable — box placement, wire sizing, proper support.
- 2
Final
Charger connection, GFCI/breaker protection, and panel labeling verified complete.
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition and replace damaged decking before proceeding
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Final inspection only: Fence Permit, Sign Permit, Water Heater Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Herriman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Herriman building permits
Get alerts for Herriman
We'll email you when Herriman's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.