Herriman building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Herriman, Utah.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
5355 W Herriman Main St, Herriman, UT 84096
Phone
(801) 446-5327
Office hours
Mon–Fri 7:30 AM – 5:30 PM (call before 4:00 PM for inspection requests)

Published scheduling rules

  • Herriman Building Department hours are 7:30 AM – 5:30 PM Monday–Friday; call before 4:00 PM for inspection requests. (Residential Building Permit)
  • The re-inspection fee in Herriman is $265 — among the higher fees in Salt Lake County; ensure work is ready before scheduling inspections. (General)
  • Call before 4:00 PM to request an inspection for the next business day — inspections are done Monday through Friday, 8:00 AM – 4:30 PM per the FAQs. (General)

Inspection sequence

Applies to: Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, egress window wells and openings

  2. 2

    MEP Rough-In

    Electrical, plumbing, and HVAC rough-ins before walls closed

  3. 3

    Insulation

    Insulation on exterior walls, vapor barrier placement

  4. 4

    Final

    Drywall, fixtures, smoke/CO detectors, and all finishes complete

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Underground / Rough-In (MEP)

    Before backfill and before closing walls or ceilings

  3. 3

    Framing

    After framing, sheathing, and rough-in mechanical/electrical/plumbing

  4. 4

    Final

    All work complete — certificate of occupancy issued upon passing final inspection

Applies to: Residential Building Permit

  1. 1

    Foundation

    Before concrete pour — verify forms, rebar, and anchor bolts

  2. 2

    Framing

    After framing, sheathing, and roof — before insulation

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Swimming Pool Permit

  1. 1

    Excavation / Steel

    Pool shell excavation, rebar, and plumbing before gunite/shotcrete

  2. 2

    Electrical / Bonding

    Pool bonding grid, equipment connections, GFCI protection per 2023 NEC Article 680

  3. 3

    Barrier

    Pool fence/barrier — 48-inch minimum height, self-closing/self-latching gates per the residential provisions of the 2024 ISPSC (Utah Code § 15A-2-103(1)(n), effective 7/1/2026); Herriman's own Building Codes and Design Criteria page still lists the 2021 ISPSC as of live-check 2026-07-16, but the statute controls

  4. 4

    Final

    Pool complete, filled, equipment operational, all barriers in place

Applies to: Deck Permit

  1. 1

    Footings

    Verify footing depth (minimum 30 inches — Herriman frost depth), diameter, and rebar before concrete pour

  2. 2

    Framing

    Posts, beams, joists, ledger connection, and hardware

  3. 3

    Final

    Decking, stairs, guards, and railings complete — 36-inch guard height required when deck is over 30 inches above grade

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

Applies to: Plumbing Permit

  1. 1

    Underground / Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Rough-In (MEP)

    After framing and rough-in mechanical, electrical, and plumbing work

  2. 2

    Final

    All work complete; space approved for occupancy under the tenant's use classification

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped, site conditions verified

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In / Circuit

    New dedicated EV charger circuit verified before closing walls, if applicable — box placement, wire sizing, proper support.

  2. 2

    Final

    Charger connection, GFCI/breaker protection, and panel labeling verified complete.

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed — verify clearances and support

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional

Applies to: Roofing Permit

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition and replace damaged decking before proceeding

  2. 2

    Final

    Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified

Re-inspection fees

Residential Building PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Electrical PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
EV Charger / EVSE PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Plumbing PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Mechanical / HVAC PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Roofing PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Solar Panel PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Deck PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Basement Finish PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Fence PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Demolition PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Swimming Pool PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Water Heater PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265
Commercial Building PermitReinspection Fee · Herriman Master Fee Schedule, effective July 1, 2026, per occurrence
$265.00
Commercial Tenant Improvement / Tenant Finish PermitReinspection Fee · Herriman Master Fee Schedule, effective July 1, 2026, per occurrence
$265.00
Sign PermitRe-Inspection Fee · Herriman Master Fee Schedule, effective July 1, 2026
$265

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Herriman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Herriman building permits

Get alerts for Herriman

We'll email you when Herriman's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.