Fire Sprinkler System Permit — Herriman, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://unifiedfireut.gov/prevention/plan-reviews/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Fire Sprinkler System Permit in Herriman, Utah
Fire protection system permitting in Herriman is handled by Unified Fire Authority (UFA), a special fire district separate from the Herriman City Building Department. Herriman City is listed among UFA's member communities. UFA requires a permit for installation or modification of any automatic fire sprinkler system, plus mandatory third-party peer review of the design (except for minor work below specific device-count thresholds). UFA itself charges no permit fee for this — confirmed against UFA's own FY26/27 Adopted Budget, which itemizes the Fire Prevention division's entire fee revenue as Hazardous Materials & Tank Permits, Firewatch Reimbursements, and Fireworks Permits only. The applicant instead pays a privately-set fee directly to one of UFA's approved third-party peer-review firms.
Verified 2026-07-20 · Source
When you need this permit
- Permit required from the fire code official (UFA) before beginning work on any fire protection system, per International Fire Code Section 105.1.1 — beginning work before permit issuance and plan approval is done at the contractor's own risk
- Fire Sprinkler System plans must be submitted to a UFA-approved Third Party Review company before final submittal to UFA (ufaplansubmittal@unifiedfire.org)
- Third-party peer review required for automatic fire sprinkler system installation/modification, EXCEPT: installation of fire hydrants/underground supply lines, pre-engineered kitchen hood suppression systems, or installation/relocation of fewer than 20 sprinkler heads
- System designer must be NICET Level III (Water-Based Fire Protection Systems Layout) or better, a Fire Protection Engineer, or a licensed engineer with specific additional fire protection training
- Design and installation per the most recent NFPA 13, 13-R, or 13-D adopted by the State of Utah
- Systems with 20 or more sprinkler heads (with limited 13-D/13-R exceptions) require off-site remote monitoring from an approved monitoring company
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Herriman inspection guide — scheduling & re-inspection fees →
Tips
- Fire sprinkler permitting in Herriman runs through Unified Fire Authority (UFA), NOT the Herriman City Building Department — Herriman's own Master Fee Schedule has no fire sprinkler permit fee line item because UFA handles this separately.
- UFA itself charges no plan-review or permit fee for fire sprinkler systems — confirmed by UFA's FY26/27 Adopted Budget, which lists the Fire Prevention division's entire fee revenue (Hazmat & Tank Permits, Firewatch, Fireworks Permits) with no sprinkler/alarm line item. The real cost to the applicant is the market rate charged by whichever UFA-approved third-party peer reviewer they hire.
- Herriman's Master Fee Schedule 'Fire Impact Fee' ($0.43/sq ft non-residential, per the Commercial Building Permit entry in this file) is a development impact fee unrelated to the sprinkler system installation permit itself.
- Design and third-party peer review must be completed BEFORE final plans go to UFA — starting sprinkler work before permit issuance and plan approval is done at the contractor's own risk with no special allowances.
- Any change to a fire sprinkler system's hazard classification design requires a new permit and a new third-party plan review.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Herriman building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Herriman
Fire Sprinkler System Permit in other cities
Compare fire sprinkler system permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Herriman project checklist
Describe your project once and get every permit, document, and fee it triggers in Herriman — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →