Required for installation of rooftop or ground-mounted solar photovoltaic (PV) systems in Millcreek. The FY25 fee schedule lists a flat $70 base permit fee plus a $30 per-kW fee and a $100 plan review fee. The 2021 IRC and 2023 NEC govern the installation.

Verified 2026-07-19 · Source

When you need this permit

  • Rooftop solar panel installation
  • Ground-mounted solar array installation
  • Battery storage system installation
  • Electrical service upgrade for solar interconnection

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 5 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Base Solar PermitMillcreek FY25 Consolidated Fee Schedule, Item 8 (Base Solar Permit, charged with KWA fee), MKC § 15-08-030 (dated 8/12/2024)
$70
KWA Fee (per kW, in addition to base permit)Millcreek FY25 Consolidated Fee Schedule, Item 9, MKC § 15-08-030
$30 per kW
Plan Review Fee (Solar)Millcreek FY25 Consolidated Fee Schedule, Item 10, MKC § 15-08-030
$100 flat
Re-Inspection FeeMillcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
State SurchargeMillcreek FY25 Consolidated Fee Schedule, Item 29, MKC § 15-08-040
1% of permit fee

Review timeline

Plan reviewMillcreek’s published plan-review target
14–14 business days

How long did your Solar Panel Permit permit actually take in Millcreek?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Solar Panels & Equipment — Electrical and Final

    Panels, arrays, wiring, boxes, switches, batteries, bonding, and grounding complete per Millcreek Required Inspections guide.

See the full Millcreek inspection guide — scheduling & re-inspection fees →

Tips

  • Millcreek solar permit fee = $70 base + $30/kW + $100 plan review per the FY25 Consolidated Fee Schedule. Example: 8 kW system = $70 + (8 × $30) + $100 = $410, plus 1% state surcharge.
  • A structural engineer letter approving the new PV system on the existing roof is required per Millcreek's Rooftop Solar PV Requirements guide.
  • Show fire department access pathway setbacks from roof ridge and eave on the site plan.
  • Rocky Mountain Power interconnection approval is required before the system can be energized.
  • The 2023 NEC (Articles 690 and 705) governs solar electrical installations in Millcreek.

Frequently asked questions

Yes. Millcreek requires a solar permit for all rooftop and ground-mounted PV installations. The fee is $70 base + $30 per kW + $100 flat plan review per the FY25 Consolidated Fee Schedule (MKC § 15-08-030, dated 8/12/2024). A structural engineer letter and detailed one-line electrical diagram are required.

Per the Millcreek FY25 Consolidated Fee Schedule (MKC § 15-08-030, dated 8/12/2024): $70 base + $30 per kW + $100 plan review, plus a 1% state surcharge. A 5 kW system costs $70 + $150 + $100 = $320 before the surcharge.

Millcreek's published plan-review target for a solar panel permit is 14–14 business days.

You'll need: Building Permit Application (iWorQ portal); Solar Site Plan / Roof Plan; Electrical One-Line Diagram; Mounting System / Structural Approval; Module and Inverter Specification Sheets. Depending on your project, Millcreek may also ask for: Interconnection Agreement. See the required-documents checklist on this page for details on each.

Millcreek requires 1 inspection(s) for a solar panel permit, in order: Solar Panels & Equipment — Electrical and Final. Schedule each through Millcreek Building Department ((801) 214-2700).

Apply through Millcreek Building Department at 1330 East Chambers Avenue, Millcreek, UT 84106. Phone: (801) 214-2700, email: buildingservices@millcreekut.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://millcreekut.gov/165/Building-Services.

Millcreek, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — currently in effect as of July 1, 2026, superseding the 2021 IBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(a)); see NOTE below on Millcreek's own page lagging this update; 2021 International Residential Code (IRC), including Appendix AQ (Tiny Houses) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(b)); 2024 International Plumbing Code (IPC) — currently in effect as of July 1, 2026, superseding the 2021 IPC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(d)); 2024 International Mechanical Code (IMC) — currently in effect as of July 1, 2026, superseding the 2021 IMC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(e)); 2024 International Fuel Gas Code (IFGC) — currently in effect as of July 1, 2026, superseding the 2021 IFGC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(f)); 2023 National Electrical Code (NEC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(g)). Millcreek's Building Services page previously referenced a 2020 NEC edition (recorded as of 2026-06-30); the 2023 NEC supersedes it statewide regardless of the page's wording; 2024 International Energy Conservation Code (IECC) — currently in effect statewide as of July 1, 2026, a single edition with no residential/commercial split under current law (Utah Code § 15A-2-103(1)(h)); Historical (superseded): prior to July 1, 2026, Millcreek's Building Services page cited a 2015 IECC edition for residential and a separate 2021 IECC edition for commercial — both are now superseded by the single 2024 IECC per § 15A-2-103(1)(h); re-checked live 2026-07-16 and Millcreek's page (millcreekut.gov/165/Building-Services, via its Building Department overview page and 'Adopted Construction Codes' resource) still displayed this superseded 2015/2021 split — city page lags the statute; 2024 International Existing Building Code (IEBC) — currently in effect as of July 1, 2026, superseding the 2021 IEBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(i)); Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — currently in effect as of July 1, 2026, superseding the 2021 ISPSC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(n)); 2006 International Wildland-Urban Interface Code (IWUIC) — millcreekut.gov/165/Building-Services; applies to Foothills/Canyons Overlay Zone properties; NOTE (updated 2026-07-16): the July 1, 2026 transition forecast in the prior version of this entry has now occurred — confirmed live against Utah Code § 15A-2-103, current version (effective 7/1/2026, superseded 1/1/2027), read at le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html. Millcreek's own Building Department page (millcreekut.gov, live 2026-07-16) still displays a banner reading 'On July 1, 2026, the State of Utah will adopt all 2024 I-Codes with State Amendments. Any Commercial project submitted on or after July 1st will need to be designed to these standards' — forward-looking, present-tense-stale wording that also narrows the transition to Commercial projects only; the statute imposes no residential/commercial distinction for IBC/IPC/IMC/IFGC/IECC/IEBC/ISPSC, so this record treats the full 2024 edition set as governing for all project types as of 2026-07-16, and flags the city page as not yet updated to reflect that the date has passed. Local amendments apply — see the Millcreek overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Millcreek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.