Millcreek building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Millcreek, Utah.

Verified 2026-06-30 · Source

How to schedule

Inspections are requested through the building department below.

Address
1330 East Chambers Avenue, Millcreek, UT 84106
Phone
(801) 214-2700
Office hours
Mon–Fri 8:00 AM – 5:00 PM

Published scheduling rules

  • Apply online via the iWorQ permit portal at millcreekpermit.portal.iworq.net. Inspection requests must be submitted through the same portal. (Residential Building Permit)
  • Inspection requests are submitted through the iWorQ portal at millcreekpermit.portal.iworq.net/MILLCREEKUT/permits/600. (General)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing

    Forms, rebar, and grade complete before concrete poured.

  2. 2

    Foundation

    Forms, rebar, and grade complete before concrete poured.

  3. 3

    Four-Way (Framing / Mechanical / Electrical / Plumbing)

    Rough framing, mechanical, electrical, and plumbing complete before insulation or wall cover. Millcreek requires a combined four-way inspection for projects with any MEP work.

  4. 4

    Fire Sprinkler / Alarm

    Where required by occupancy group, per the New Commercial Building Permit Requirements checklist's code/design analysis section.

  5. 5

    Final

    All permitted work complete.

Applies to: Residential Building Permit

  1. 1

    Footing

    Forms, rebar, and grade complete before concrete poured. Footings for new homes require an elevation certificate to verify height.

  2. 2

    Foundation

    Forms, rebar, and grade complete before concrete poured.

  3. 3

    Four-Way (Framing / Mechanical / Electrical / Plumbing)

    Rough framing, mechanical, electrical, and plumbing all complete before insulation or drywall. Millcreek requires a combined four-way inspection for projects with any MEP work — separate trade inspections will NOT be scheduled.

  4. 4

    Insulation

    Insulation, vapor barrier, windows, baffles, depth markers, and supports complete; all penetrations sealed. Prescriptive requirements or REScheck required to verify R-values and U-factors.

  5. 5

    Final

    All permitted work complete.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Fire-Rated Assembly

    Wall construction, fire-rated assemblies, and seismic bracing for suspended ceilings verified before close-in, per the Commercial Alteration Building Permit Requirements checklist.

  2. 2

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in — including grease interceptor and gas line diagram verification for food service tenants.

  3. 3

    Fire Sprinkler / Alarm

    Coordinated with Unified Fire Authority approval, per the checklist.

  4. 4

    Final

    All permitted work complete.

Applies to: Electrical Permit

  1. 1

    Electrical Rough-In (part of Four-Way inspection for MEP projects)

    Wiring, boxes, panels, and supports complete before drywall or insulation. Millcreek requires a combined four-way inspection for projects with any MEP work — separate trade inspections are not scheduled.

  2. 2

    Power to Panel

    Panel, wiring, bonding, and UFER ground complete. Load calculations required to verify panel size.

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled.

Applies to: Fire Alarm System Permit

  1. 1

    Rough-In

    Device and wiring placement verified against approved plans before wall cover, including notification appliance (horn/strobe) locations.

  2. 2

    Battery / Standby Power Test

    Battery calculations and standby power supply verified per submitted plans.

  3. 3

    Final Acceptance Test / Record of Completion

    Full functional test of devices and notification appliances, remote annunciator check, and — for Institutional, Hazardous, Large Shopping Mall, and High-Rise occupancies — verification of the required Knox brand 1300 series cabinet with building floor plans and utility shut-off information.

Applies to: Fire Sprinkler System Permit

  1. 1

    Underground Piping Test

    Material and Test Certificate — Underground Piping documenting flush and pressure testing prior to connection, per UFA's published completion form.

  2. 2

    Aboveground Piping Rough-In / Hydrostatic Test

    Material and Test Certificate — Aboveground Piping documenting hydrostatic testing before concealment, per UFA's published completion form.

  3. 3

    Final Acceptance Test

    Full system flow/alarm test; verification of remote monitoring connection (systems with 20+ heads), Knox brand locking FDC caps, supervised/locked post indicator valves, and the required 'RISER ROOM' sign.

Applies to: Plumbing Permit

  1. 1

    Plumbing Rough-In (part of Four-Way inspection for MEP projects)

    Distribution piping, drain waste vent piping, traps, manifolds, backwater valves, and supports complete and under test before insulation or drywall. Millcreek requires a combined four-way inspection for projects with any MEP work.

  2. 2

    Gas Line

    Piping, supports, drip legs, and test tees complete and under test before connecting to meters, appliances, or regulators. A gas line diagram is required to verify pipe sizing.

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified. Shower pans do not require a separate inspection per Millcreek's Required Inspections guide.

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Utility disconnections verified and any required asbestos clearance obtained before work begins.

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped per approved plan.

Applies to: EV Charger / EVSE Permit

  1. 1

    Power to Panel

    Panel, wiring, bonding, and UFER ground complete. Load calculations required to verify panel size.

  2. 2

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled.

Applies to: Mechanical / HVAC Permit

  1. 1

    Mechanical Rough-In (part of Four-Way inspection for MEP projects)

    Supply ducts, return air plenums, boots, duct and plenum sealing, transfer air grills, and supports complete. Manual J/D/S may be required to verify equipment sizing. Millcreek requires a combined four-way inspection for projects with any MEP work.

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional.

Re-inspection fees

Residential Building PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Electrical PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Plumbing PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Mechanical / HVAC PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Roofing PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Solar Panel PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Water Heater PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Demolition PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Window and Door Replacement PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Commercial Building PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
Commercial Tenant Improvement / Tenant Finish PermitRe-Inspection Fee · Millcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence

Sources & verification

Verified against official sources. Last reviewed 2026-06-30.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Millcreek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Millcreek building permits

Get alerts for Millcreek

We'll email you when Millcreek's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.