Millcreek building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Millcreek, Utah.
Verified 2026-06-30 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 1330 East Chambers Avenue, Millcreek, UT 84106
- Phone
- (801) 214-2700
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM
- Website
- Official site
Published scheduling rules
- Apply online via the iWorQ permit portal at millcreekpermit.portal.iworq.net. Inspection requests must be submitted through the same portal. (Residential Building Permit)
- Inspection requests are submitted through the iWorQ portal at millcreekpermit.portal.iworq.net/MILLCREEKUT/permits/600. (General)
Inspection sequence
Applies to: Commercial Building Permit
- 1
Footing
Forms, rebar, and grade complete before concrete poured.
- 2
Foundation
Forms, rebar, and grade complete before concrete poured.
- 3
Four-Way (Framing / Mechanical / Electrical / Plumbing)
Rough framing, mechanical, electrical, and plumbing complete before insulation or wall cover. Millcreek requires a combined four-way inspection for projects with any MEP work.
- 4
Fire Sprinkler / Alarm
Where required by occupancy group, per the New Commercial Building Permit Requirements checklist's code/design analysis section.
- 5
Final
All permitted work complete.
Applies to: Residential Building Permit
- 1
Footing
Forms, rebar, and grade complete before concrete poured. Footings for new homes require an elevation certificate to verify height.
- 2
Foundation
Forms, rebar, and grade complete before concrete poured.
- 3
Four-Way (Framing / Mechanical / Electrical / Plumbing)
Rough framing, mechanical, electrical, and plumbing all complete before insulation or drywall. Millcreek requires a combined four-way inspection for projects with any MEP work — separate trade inspections will NOT be scheduled.
- 4
Insulation
Insulation, vapor barrier, windows, baffles, depth markers, and supports complete; all penetrations sealed. Prescriptive requirements or REScheck required to verify R-values and U-factors.
- 5
Final
All permitted work complete.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Fire-Rated Assembly
Wall construction, fire-rated assemblies, and seismic bracing for suspended ceilings verified before close-in, per the Commercial Alteration Building Permit Requirements checklist.
- 2
MEP Rough-In
Electrical, mechanical, and plumbing rough-in — including grease interceptor and gas line diagram verification for food service tenants.
- 3
Fire Sprinkler / Alarm
Coordinated with Unified Fire Authority approval, per the checklist.
- 4
Final
All permitted work complete.
Applies to: Electrical Permit
- 1
Electrical Rough-In (part of Four-Way inspection for MEP projects)
Wiring, boxes, panels, and supports complete before drywall or insulation. Millcreek requires a combined four-way inspection for projects with any MEP work — separate trade inspections are not scheduled.
- 2
Power to Panel
Panel, wiring, bonding, and UFER ground complete. Load calculations required to verify panel size.
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled.
Applies to: Fire Alarm System Permit
- 1
Rough-In
Device and wiring placement verified against approved plans before wall cover, including notification appliance (horn/strobe) locations.
- 2
Battery / Standby Power Test
Battery calculations and standby power supply verified per submitted plans.
- 3
Final Acceptance Test / Record of Completion
Full functional test of devices and notification appliances, remote annunciator check, and — for Institutional, Hazardous, Large Shopping Mall, and High-Rise occupancies — verification of the required Knox brand 1300 series cabinet with building floor plans and utility shut-off information.
Applies to: Fire Sprinkler System Permit
- 1
Underground Piping Test
Material and Test Certificate — Underground Piping documenting flush and pressure testing prior to connection, per UFA's published completion form.
- 2
Aboveground Piping Rough-In / Hydrostatic Test
Material and Test Certificate — Aboveground Piping documenting hydrostatic testing before concealment, per UFA's published completion form.
- 3
Final Acceptance Test
Full system flow/alarm test; verification of remote monitoring connection (systems with 20+ heads), Knox brand locking FDC caps, supervised/locked post indicator valves, and the required 'RISER ROOM' sign.
Applies to: Plumbing Permit
- 1
Plumbing Rough-In (part of Four-Way inspection for MEP projects)
Distribution piping, drain waste vent piping, traps, manifolds, backwater valves, and supports complete and under test before insulation or drywall. Millcreek requires a combined four-way inspection for projects with any MEP work.
- 2
Gas Line
Piping, supports, drip legs, and test tees complete and under test before connecting to meters, appliances, or regulators. A gas line diagram is required to verify pipe sizing.
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified. Shower pans do not require a separate inspection per Millcreek's Required Inspections guide.
Applies to: Demolition Permit
- 1
Pre-Demolition
Utility disconnections verified and any required asbestos clearance obtained before work begins.
- 2
Final / Site Clear
Site cleared, foundation removed or capped per approved plan.
Applies to: EV Charger / EVSE Permit
- 1
Power to Panel
Panel, wiring, bonding, and UFER ground complete. Load calculations required to verify panel size.
- 2
Final
All devices installed, GFCI/AFCI protection verified, panel labeled.
Applies to: Mechanical / HVAC Permit
- 1
Mechanical Rough-In (part of Four-Way inspection for MEP projects)
Supply ducts, return air plenums, boots, duct and plenum sealing, transfer air grills, and supports complete. Manual J/D/S may be required to verify equipment sizing. Millcreek requires a combined four-way inspection for projects with any MEP work.
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional.
Final inspection only: Roofing Permit, Solar Panel Permit, Water Heater Permit, Window and Door Replacement Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Millcreek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Millcreek building permits
Get alerts for Millcreek
We'll email you when Millcreek's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.