Electrical Permit in Millcreek, Utah

Required for electrical work in Millcreek including new circuits, panel upgrades, service changes, and new construction wiring. Governed by the 2023 National Electrical Code (NEC) statewide per Utah Code § 15A-2-103(1)(g). EV charger/EVSE installation is electrical work and falls under this general Electrical Permit; the Millcreek FY25 Consolidated Fee Schedule does not publish an EV-specific line item, so a charger install is billed under the standard Electrical Permit Base Fee.

Verified 2026-07-20 · Source

When you need this permit

  • New electrical circuits or wiring installations
  • Electrical panel upgrades or replacements
  • Service entrance changes
  • Adding or relocating outlets, switches, or fixtures
  • Generator or solar panel electrical connections

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Base FeeMillcreek FY25 Consolidated Fee Schedule, Item 3, MKC § 15-16-020 (dated 8/12/2024). Covers circuit, electrical service charge, power to panel, temporary panel.
$70
Additional Appliance or FixtureMillcreek FY25 Consolidated Fee Schedule, Item 4, MKC § 15-16-020
$20 per additional item
Re-Inspection FeeMillcreek FY25 Consolidated Fee Schedule, Item 23, MKC § 15-08-040
$75 per occurrence
State SurchargeMillcreek FY25 Consolidated Fee Schedule, Item 29, MKC § 15-08-040
1% of permit fee

Review timeline

Plan reviewMillcreek’s published plan-review target
14–14 business days

How long did your Electrical Permit permit actually take in Millcreek?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Rough-In (part of Four-Way inspection for MEP projects)

    Wiring, boxes, panels, and supports complete before drywall or insulation. Millcreek requires a combined four-way inspection for projects with any MEP work — separate trade inspections are not scheduled.

  2. 2

    Power to Panel

    Panel, wiring, bonding, and UFER ground complete. Load calculations required to verify panel size.

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled.

See the full Millcreek inspection guide — scheduling & re-inspection fees →

Tips

  • All electrical work in Millcreek must comply with the 2023 NEC (statewide per Utah Code § 15A-2-103(1)(g)); Millcreek's own building services page referenced 2020 NEC as of the verification date.
  • Utah law allows homeowners to perform electrical work on their own primary residence, but a permit and all required inspections remain mandatory.
  • AFCI protection is required on all 15A and 20A bedroom circuits under the 2023 NEC.
  • GFCI protection is required in kitchens, bathrooms, garages, outdoors, and crawl spaces.
  • EV charger (EVSE) installation is not a separate permit category in Millcreek — it is filed as a standard electrical permit under the $70 Electrical Permit Base Fee (Item 3, MKC § 15-16-020).

Frequently asked questions

Millcreek requires an electrical permit for: New electrical circuits or wiring installations; Electrical panel upgrades or replacements; Service entrance changes; Adding or relocating outlets, switches, or fixtures; Generator or solar panel electrical connections. If your project isn't listed, confirm with Millcreek Building Department at (801) 214-2700 before starting work.

Per the Millcreek FY25 Consolidated Fee Schedule (MKC § 15-16-020, dated 8/12/2024): the base fee is $70 for the first circuit/service/panel, plus $20 for each additional appliance or fixture. A 1% state surcharge and $75 re-inspection fee (if needed) also apply.

Millcreek's published plan-review target for an electrical permit is 14–14 business days.

You'll need: Building Permit Application (iWorQ portal). Depending on your project, Millcreek may also ask for: Electrical Single-Line Diagram; Contractor License. See the required-documents checklist on this page for details on each.

Millcreek requires 3 inspection(s) for an electrical permit, in order: Electrical Rough-In (part of Four-Way inspection for MEP projects), Power to Panel, Final. Schedule each through Millcreek Building Department ((801) 214-2700).

Apply through Millcreek Building Department at 1330 East Chambers Avenue, Millcreek, UT 84106. Phone: (801) 214-2700, email: buildingservices@millcreekut.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://millcreekut.gov/165/Building-Services.

Millcreek, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — currently in effect as of July 1, 2026, superseding the 2021 IBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(a)); see NOTE below on Millcreek's own page lagging this update; 2021 International Residential Code (IRC), including Appendix AQ (Tiny Houses) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(b)); 2024 International Plumbing Code (IPC) — currently in effect as of July 1, 2026, superseding the 2021 IPC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(d)); 2024 International Mechanical Code (IMC) — currently in effect as of July 1, 2026, superseding the 2021 IMC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(e)); 2024 International Fuel Gas Code (IFGC) — currently in effect as of July 1, 2026, superseding the 2021 IFGC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(f)); 2023 National Electrical Code (NEC) — currently in effect; unchanged by the July 1, 2026 statewide code-edition update (Utah Code § 15A-2-103(1)(g)). Millcreek's Building Services page previously referenced a 2020 NEC edition (recorded as of 2026-06-30); the 2023 NEC supersedes it statewide regardless of the page's wording; 2024 International Energy Conservation Code (IECC) — currently in effect statewide as of July 1, 2026, a single edition with no residential/commercial split under current law (Utah Code § 15A-2-103(1)(h)); Historical (superseded): prior to July 1, 2026, Millcreek's Building Services page cited a 2015 IECC edition for residential and a separate 2021 IECC edition for commercial — both are now superseded by the single 2024 IECC per § 15A-2-103(1)(h); re-checked live 2026-07-16 and Millcreek's page (millcreekut.gov/165/Building-Services, via its Building Department overview page and 'Adopted Construction Codes' resource) still displayed this superseded 2015/2021 split — city page lags the statute; 2024 International Existing Building Code (IEBC) — currently in effect as of July 1, 2026, superseding the 2021 IEBC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(i)); Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — currently in effect as of July 1, 2026, superseding the 2021 ISPSC that was in effect through June 30, 2026 (Utah Code § 15A-2-103(1)(n)); 2006 International Wildland-Urban Interface Code (IWUIC) — millcreekut.gov/165/Building-Services; applies to Foothills/Canyons Overlay Zone properties; NOTE (updated 2026-07-16): the July 1, 2026 transition forecast in the prior version of this entry has now occurred — confirmed live against Utah Code § 15A-2-103, current version (effective 7/1/2026, superseded 1/1/2027), read at le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html. Millcreek's own Building Department page (millcreekut.gov, live 2026-07-16) still displays a banner reading 'On July 1, 2026, the State of Utah will adopt all 2024 I-Codes with State Amendments. Any Commercial project submitted on or after July 1st will need to be designed to these standards' — forward-looking, present-tense-stale wording that also narrows the transition to Commercial projects only; the statute imposes no residential/commercial distinction for IBC/IPC/IMC/IFGC/IECC/IEBC/ISPSC, so this record treats the full 2024 edition set as governing for all project types as of 2026-07-16, and flags the city page as not yet updated to reflect that the date has passed. Local amendments apply — see the Millcreek overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Millcreek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.