Commercial Building Permit — Washington City, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://washingtonutah.gov/development/building/commercialpermitprocess
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit in Washington City, Utah
Required for new commercial construction, additions, and common area buildings in Washington City. Building permit applications and plans will not be accepted until Civil Plans are approved. Washington City publishes its own detailed 'Commercial Plans Submittal Checklist' and a step-by-step CityInspect submittal guide distinct from the residential process, and calculates the fee from the city's own current valuation-based Building Permit Fee Table plus a Square Foot Construction Costs table (2018 IBC) covering commercial occupancy classifications such as B Business and M Mercantile — with a Plan Review Fee equal to 45% of the total calculated building permit fee.
Verified 2026-07-19 · Source
When you need this permit
- All Commercial/Industrial building permits require completion of the Pre-Submittal Process before submitting complete building plans — contact the Building Department at (435) 656-6326 to begin, per the city's official Commercial Plans Submittal Checklist
- Completed and approved Washington City Commercial Building Permit Pre-submittal Information form (Commercial Pre-Submittal Packet, washingtoncity.org/downloads/building/CommercialPreSubmittalPacketWashingtonCity.pdf) — 'Commercial/Industrial building permit submittals will not be accepted without this item'
- For Commercial New Construction, Additions, and Common Area Buildings, building permit applications and plans will not be accepted until Civil Plans are approved — this is not a deferral item
- Approved Civil Drawings (Site Construction Plans) — city-stamped and signed civil plans uploaded with the application
- SWPPP (Stormwater Pollution Prevention Plan) and SWPPP Notice of Intent (NOI) — the NOI inspection is required for initiation of the Stormwater Permit and must be scheduled at footings
- Commercial Checklist, completed and signed — 'permit applications will not be accepted without a Commercial Checklist'
- Fire Review Information Form, Fire & Life Safety (F&LS) plan, fire sprinkler and fire alarm plans as applicable
- Washington County Water Conservancy District (WCWCD) receipt confirming the impact fee has been paid
- Applications submitted via the CityInspect Builder Account, selecting 'Commercial (New Build)' or 'Commercial Addition' for permit type
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Washington City Building Department Master Fee Schedule (Google Sheets PDF linked from washingtonutah.gov/development/building/buildingfeeschedule), fetched 2026-07-19 — the same current,… Show full citationHide
Washington City Building Department Master Fee Schedule (Google Sheets PDF linked from washingtonutah.gov/development/building/buildingfeeschedule), fetched 2026-07-19 — the same current, city-specific ICC-style valuation table used for the Residential Building Permit entry in this record; no separate residential/commercial split is published.Washington City Building Department Master Fee Schedule, 'SQUARE FOOT CONSTRUCTION COSTS TABLE B — Group 2018 IBC', row 'B Business': IA 127.83, IB 123.20, IIA 119.28, IIB 113.70, IIIA 101.74, IIIB… Show full citationHide
Washington City Building Department Master Fee Schedule, 'SQUARE FOOT CONSTRUCTION COSTS TABLE B — Group 2018 IBC', row 'B Business': IA 127.83, IB 123.20, IIA 119.28, IIB 113.70, IIIA 101.74, IIIB 101.18, IV 109.36, VA 90.86, VB 87.43. This table is labeled '2018 IBC' — stale relative to the current statewide-mandatory 2024 IBC (Utah Code § 15A-2-103(1)(a), effective 7/1/2026); use with the same caution noted for the checklist's code-edition list.Review timeline
Inspection process
- 1
SWPPP Notice of Intent (NOI)
Required for initiation of the Stormwater Permit; must be scheduled at footings, per the Commercial New Build and Additions submittal requirements.
- 2
Foundation / Footing
Before concrete pour, per standard IBC inspection sequence.
- 3
Structural / Framing
Framing and structural elements, including truss layout and truss packet conformance, verified against submitted structural calculations.
- 4
MEP Rough-In
Electrical, mechanical, and plumbing rough-in verified against submitted plans.
- 5
Final / Certificate of Occupancy
Final inspection and approvals required from Building, Planning, Fire, Public Works, Power, Parks, and St. George Treatment (and any other permit-reviewing party) before Certificate of Occupancy is released. Four certifications — Soils Compliance Letter, Insulation Certification, Stucco Certification, and Termite Certification — must all be uploaded to the Building Permit before a CO can be released.
See the full Washington City inspection guide — scheduling & re-inspection fees →
Tips
- Washington City's 'Packet Review' process runs all reviewing departments (Building, Planning, Power, Public Works, Fire) concurrently in CityInspect — corrections must be viewed (not edited) until every department has completed its pass, the same process used for New Single Family permits.
- Building permit applications and plans 'will not be accepted' for Commercial New Construction, Additions, and Common Area Buildings until Civil Plans are approved — this is explicitly stated as not a deferral item.
- Four separate certifications (Soils Compliance, Insulation, Stucco, Termite) must all be uploaded before a Certificate of Occupancy will be released, in addition to final sign-off from Building, Planning, Fire, Public Works, Power, Parks, and St. George Treatment.
- Washington City's Square Foot Construction Costs Table B is explicitly labeled '2018 IBC' — five code cycles behind the current statewide-mandatory 2024 IBC (Utah Code § 15A-2-103, effective 7/1/2026) — confirm current valuation guidance with the Building Department, (435) 656-6326, rather than relying on the table's stated edition alone.
- Plan review fee is 45% of the calculated building permit fee — the same rate used for residential permits in this record, and notably higher than St. George's or Ivins'/Santa Clara's 10% and Ivins' plan-check structure, though built on Washington City's own distinct (and generally lower at low valuations) base fee table.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fee schedules
Applications & forms
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Washington City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Washington City.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Property Access
Washington City's permit history is searchable by address
359 permits on record for Washington City, 1971–2022 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Washington City
Commercial Building Permit in other cities
Compare commercial building permit fees across Utah →
Look up this fee in a different city →