Excavation Permit — West Haven, Utah · Requirements sheet
Verified 2026-07-07 · Source: https://cms3.revize.com/revize/cityofwesthaven/Documents/Departments/Community%20Development/Building%20Department/Excavation%20Permit%20Application.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Excavation Permit in West Haven, Utah
Required for excavation and street-cut work in West Haven, governed by West Haven City Excavation Ordinance 5-92 (adopted February 5, 1992) and the Amendment to West Haven City's Street Cut Policy, Ordinance 19-98 (adopted July 1998), per the city's official Excavation Permit Application form.
Verified 2026-07-07 · Source
When you need this permit
- Permit required for excavation work including road cuts, trenching, and bore holes
- Compaction test required within 5 working days maximum after excavation (permittee-completed; the city is not responsible for the compaction test)
- Permittee responsible for patching after the compaction test is completed and passes, per the attached pavement cutting and patching policy
- Applicant must sign the Applicant's Agreement, assuming all duties/obligations/responsibilities under Ordinance 5-92 and Ordinance 19-98
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full West Haven inspection guide — scheduling & re-inspection fees →
Tips
- The Excavation Permit Application form's own 'Basic Fee Schedule' and the city's separate Consolidated Fees & Fines Schedule agree on most figures (Permit Charge/Basic Application Fee $150, Renewal $75, Extension $75, Reinspection $50, Working-without-permit $500, Violation $1,000, Street Cut $2.50/sq.ft., 3-10-year road cut $125) but diverge on the Emergency fee ($500 per the application form vs. $125 in one row of the consolidated schedule) — both figures are documented here rather than silently picking one.
- Ordinance 5-92 (1992) and Ordinance 19-98 (1998) are the two governing excavation/street-cut ordinances explicitly cited on the official application form.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Haven building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in West Haven
Excavation Permit in other cities
Compare excavation permit fees across Utah →