Required for installation of a fire alarm system in West Haven. As with fire sprinkler permits, fire alarm plan review and permitting is handled by Weber Fire District (WFD), which West Haven City contracts with for fire protection, separately from the City's own building permit process.

Verified 2026-07-19 · Source

When you need this permit

  • Installation or modification of a fire alarm system
  • Plan review and permit from Weber Fire District's Fire Marshal's Office, in addition to the City building permit
  • Submit plans electronically to prevention@weberfiredistrict.gov

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Fire Alarm System Plan Review/Re-Review — 1-20,000 Sq FtWeber Fire District Fee Schedule (effective January 1, 2026), 'Fire Protection Systems: Fire Alarm System, Plan Review / Re-Review' table, confirmed via direct page-image review of the PDF fetched live 2026-07-19.
$100.00
Fire Alarm System Plan Review/Re-Review — 20,001-50,000 Sq FtWeber Fire District Fee Schedule (effective January 1, 2026).
$200.00
Fire Alarm System Plan Review/Re-Review — 50,001+ Sq FtWeber Fire District Fee Schedule (effective January 1, 2026).
$300.00
Fire Alarm System Permit (includes 2 inspections) — 1-20,000 Sq FtWeber Fire District Fee Schedule (effective January 1, 2026), 'Fire Alarm System, Permit - Includes 2 Inspections' table.
$165.00
Fire Alarm System Permit (includes 2 inspections) — 20,001-50,000 Sq FtWeber Fire District Fee Schedule (effective January 1, 2026).
$330.00
Fire Alarm System Permit (includes 2 inspections) — 50,001+ Sq FtWeber Fire District Fee Schedule (effective January 1, 2026).
$495.00
Routine Fire Alarm Inspection (business license / building approval)Weber Fire District Fee Schedule (effective January 1, 2026), 'Inspections' table: 'Fire Sprinkler, Kitchen Hood System, Fire Alarm System, Business License, Building Approval — $65.00.' This is a separate routine/annual inspection fee, distinct from the alarm system installation permit above.
$65.00

Review timeline

Plan reviewWest Haven’s published plan-review target
14–14 business days

How long did your Fire Alarm System Permit permit actually take in West Haven?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    First Inspection

    Included in the permit fee; Weber Fire District alarm permits include 2 inspections total.

  2. 2

    Final Inspection

    Second of the 2 inspections included in the permit fee.

See the full West Haven inspection guide — scheduling & re-inspection fees →

Tips

  • West Haven contracts with Weber Fire District (WFD) for fire protection — fire alarm plan review and permitting go through WFD's Fire Marshal's Office (prevention@weberfiredistrict.gov, 801-782-3580), not the City Building Department.
  • Fire alarm fees scale by building square footage, not by device count — a small building (up to 20,000 sq ft) totals $265 for plan review + permit ($100 + $165), while a large building (50,001+ sq ft) totals $795 ($300 + $495).

Frequently asked questions

West Haven requires a fire alarm system permit for: Installation or modification of a fire alarm system; Plan review and permit from Weber Fire District's Fire Marshal's Office, in addition to the City building permit; Submit plans electronically to prevention@weberfiredistrict.gov. If your project isn't listed, confirm with West Haven City Building Department (Community Development Department) at 385-389-2690 before starting work.

West Haven's fire protection is handled by Weber Fire District. Per WFD's fee schedule (effective January 1, 2026), fire alarm plan review ranges from $100 (up to 20,000 sq ft) to $300 (50,001+ sq ft), and the permit (including 2 inspections) ranges from $165 to $495, scaling with building square footage.

West Haven's published plan-review target for a fire alarm system permit is 14–14 business days.

You'll need: Plan Submittal Application; Fire Alarm System Plans. See the required-documents checklist on this page for details on each.

West Haven requires 2 inspection(s) for a fire alarm system permit, in order: First Inspection, Final Inspection. Schedule each through West Haven City Building Department (Community Development Department) (385-389-2690).

Apply through West Haven City Building Department (Community Development Department) at 4150 S 3900 W, West Haven, UT 84401. Phone: 385-389-2690, email: buildinginspections@westhavenut.gov. Office hours: Monday–Thursday, 7:00 AM – 5:00 PM (closed Friday), per the city's official Building Department page. Building permit submittal and inspection requests are handled online via the CityInspect portal (registration required) or by email to the Building Department.. Official information: https://www.westhavenut.gov/departments/community_development/building_department.php.

West Haven, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide code per Utah Code § 15A-2-103(1)(a), in force since July 1, 2026 (superseded the 2021 IBC). NOTE: West Haven City's own official Building Department page has NOT been updated for this flip — re-checked live 2026-07-16, it still reads '2021 International Building Code (IBC) (Effective July 1, 2026, the 2024 codes will be required)', future-tense language that is now stale since that date has passed. The statewide-adopted 2024 edition governs regardless of the city's unrevised page.; 2021 International Residential Code (IRC) — current statewide code per Utah Code § 15A-2-103(1)(b), unchanged by the July 1, 2026 code cycle flip; matches West Haven City's official Building Department page as re-checked live 2026-07-16.; 2024 International Mechanical Code (IMC) — current statewide code per Utah Code § 15A-2-103(1)(e), in force since July 1, 2026 (superseded the 2021 IMC). NOTE: West Haven's official Building Department page still reads '2021 International Mechanical Code (IMC) (Effective July 1, 2026, the 2024 codes will be required)' as re-checked live 2026-07-16 — stale future-tense language; the statewide-adopted 2024 edition governs.; 2024 International Plumbing Code (IPC) — current statewide code per Utah Code § 15A-2-103(1)(d), in force since July 1, 2026 (superseded the 2021 IPC). NOTE: West Haven's official Building Department page uses the same stale future-tense '2021 ... (Effective July 1, 2026, the 2024 codes will be required)' phrasing, re-confirmed live 2026-07-16; the statewide-adopted 2024 edition governs.; 2024 International Fuel Gas Code (IFGC) — current statewide code per Utah Code § 15A-2-103(1)(f), in force since July 1, 2026 (superseded the 2021 IFGC). NOTE: West Haven's official Building Department page uses the same stale future-tense phrasing, re-confirmed live 2026-07-16. The city's Residential Basement Finish guide separately cites IFGC 406.4 (concealed gas piping air test) as an active code reference, unaffected by the edition-number update.; 2024 International Energy Conservation Code (IECC) — current statewide code per Utah Code § 15A-2-103(1)(h), in force since July 1, 2026 (superseded the 2021 IECC; one edition applies statewide, no separate residential/commercial split). NOTE: West Haven's official Building Department page uses the same stale future-tense phrasing, re-confirmed live 2026-07-16.; 2023 National Electrical Code (NEC) — current statewide code per Utah Code § 15A-2-103(1)(g), unchanged by the July 1, 2026 code cycle flip. NOTE: this is a SEPARATE, pre-existing error on West Haven's official Building Department page (unrelated to the July 1, 2026 code-cycle flip) — the page states '2020 National Electrical Code (NEC) remains in effect,' re-confirmed live 2026-07-16. The 2023 NEC has been the statewide-adopted edition since before this file's prior verification (2026-07-07); the city's page has not been corrected.; Utah Code Title 15A, Chapter 3 (State Amendments to the adopted construction codes) — referenced directly by the city's Building Department page via a 'Utah State Amendments' link to the Utah Legislature's own code text.. Local amendments apply — see the West Haven overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Haven building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.