EV Charger / EVSE Permit in West Haven, Utah

West Haven City has not published a distinct EV-charger fee category. The city's Consolidated Fees & Fines Schedule (Resolution, adopted September 17, 2025) publishes only a single 'Building Permit Fee ... Established in WHCC § 151.15, as amended' with no separate electrical-permit line item at all; the city's own Shed & Detached Garage Guide confirms that adding electrical work of any kind triggers this same general Building Permit requirement. EV charger/EVSE installation is billed the same way as any other electrical work under this general Building Permit Fee.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
  • New dedicated electrical circuit or panel capacity to serve the charger

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit FeeWest Haven City Consolidated Fees & Fines Schedule (Resolution, adopted September 17, 2025), BUILDING/ENGINEERING section: 'Building Permit Fee ... Established in WHCC § 151.15 as amended.' No flat, valuation-based, or EV-specific dollar figure is published in the fee schedule itself — the fee is set by the referenced municipal code section, the same mechanism used for all other building-permit-triggering work in the city.
Established in WHCC § 151.15, as amended
Residential Plan Review FeeWest Haven City Consolidated Fees & Fines Schedule, adopted 9/17/2025.
20% of the Building Permit Fee
Basic Application FeeWest Haven City Consolidated Fees & Fines Schedule, adopted 9/17/2025, BUILDING/ENGINEERING section.
$150.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in West Haven?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Scheduled through the West Haven City Building Department; a Reinspection Fee ($50 general / $100 under the separate Re-inspection Fees subsection) applies if missed or failed.

See the full West Haven inspection guide — scheduling & re-inspection fees →

Tips

  • West Haven has no dedicated EV-charger permit, fee category, or submittal guide — file the install as a standard Building Permit; adding electrical work of any kind (including an EV charger circuit) triggers the same general Building Permit Fee under WHCC § 151.15, per the same rule the city applies to sheds and other accessory structures once electrical is added.

Frequently asked questions

West Haven requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property; New dedicated electrical circuit or panel capacity to serve the charger. If your project isn't listed, confirm with West Haven City Building Department (Community Development Department) at 385-389-2690 before starting work.

No. West Haven's Consolidated Fees & Fines Schedule publishes only a single Building Permit Fee (set by WHCC § 151.15) with no separate electrical-permit or EV-charger line item; an EV charger install is billed under this same general Building Permit Fee, as with any other electrical work.

West Haven does not publish a plan-review timeline for this permit. Contact West Haven City Building Department (Community Development Department) at 385-389-2690 for current turnaround.

You'll need: Building Permit Application. See the required-documents checklist on this page for details on each.

West Haven requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical Inspection. Schedule each through West Haven City Building Department (Community Development Department) (385-389-2690).

Apply through West Haven City Building Department (Community Development Department) at 4150 S 3900 W, West Haven, UT 84401. Phone: 385-389-2690, email: buildinginspections@westhavenut.gov. Office hours: Monday–Thursday, 7:00 AM – 5:00 PM (closed Friday), per the city's official Building Department page. Building permit submittal and inspection requests are handled online via the CityInspect portal (registration required) or by email to the Building Department.. Official information: https://www.westhavenut.gov/departments/community_development/building_department.php.

West Haven, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide code per Utah Code § 15A-2-103(1)(a), in force since July 1, 2026 (superseded the 2021 IBC). NOTE: West Haven City's own official Building Department page has NOT been updated for this flip — re-checked live 2026-07-16, it still reads '2021 International Building Code (IBC) (Effective July 1, 2026, the 2024 codes will be required)', future-tense language that is now stale since that date has passed. The statewide-adopted 2024 edition governs regardless of the city's unrevised page.; 2021 International Residential Code (IRC) — current statewide code per Utah Code § 15A-2-103(1)(b), unchanged by the July 1, 2026 code cycle flip; matches West Haven City's official Building Department page as re-checked live 2026-07-16.; 2024 International Mechanical Code (IMC) — current statewide code per Utah Code § 15A-2-103(1)(e), in force since July 1, 2026 (superseded the 2021 IMC). NOTE: West Haven's official Building Department page still reads '2021 International Mechanical Code (IMC) (Effective July 1, 2026, the 2024 codes will be required)' as re-checked live 2026-07-16 — stale future-tense language; the statewide-adopted 2024 edition governs.; 2024 International Plumbing Code (IPC) — current statewide code per Utah Code § 15A-2-103(1)(d), in force since July 1, 2026 (superseded the 2021 IPC). NOTE: West Haven's official Building Department page uses the same stale future-tense '2021 ... (Effective July 1, 2026, the 2024 codes will be required)' phrasing, re-confirmed live 2026-07-16; the statewide-adopted 2024 edition governs.; 2024 International Fuel Gas Code (IFGC) — current statewide code per Utah Code § 15A-2-103(1)(f), in force since July 1, 2026 (superseded the 2021 IFGC). NOTE: West Haven's official Building Department page uses the same stale future-tense phrasing, re-confirmed live 2026-07-16. The city's Residential Basement Finish guide separately cites IFGC 406.4 (concealed gas piping air test) as an active code reference, unaffected by the edition-number update.; 2024 International Energy Conservation Code (IECC) — current statewide code per Utah Code § 15A-2-103(1)(h), in force since July 1, 2026 (superseded the 2021 IECC; one edition applies statewide, no separate residential/commercial split). NOTE: West Haven's official Building Department page uses the same stale future-tense phrasing, re-confirmed live 2026-07-16.; 2023 National Electrical Code (NEC) — current statewide code per Utah Code § 15A-2-103(1)(g), unchanged by the July 1, 2026 code cycle flip. NOTE: this is a SEPARATE, pre-existing error on West Haven's official Building Department page (unrelated to the July 1, 2026 code-cycle flip) — the page states '2020 National Electrical Code (NEC) remains in effect,' re-confirmed live 2026-07-16. The 2023 NEC has been the statewide-adopted edition since before this file's prior verification (2026-07-07); the city's page has not been corrected.; Utah Code Title 15A, Chapter 3 (State Amendments to the adopted construction codes) — referenced directly by the city's Building Department page via a 'Utah State Amendments' link to the Utah Legislature's own code text.. Local amendments apply — see the West Haven overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Haven building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.