Certificate of Occupancy / Change of Use in West Haven, Utah
West Haven City Code (WHCC) § 157.691 (Certificate of Occupancy Required) provides that no land shall be used or occupied, and no building shall be used or changed in use (except for agricultural purposes), until a certificate of occupancy has been issued by the Building Inspector confirming the building or proposed use complies with the zoning ordinance; the same requirement governs maintaining, renewing, changing, or extending a nonconforming use. Under WHCC § 157.690 (Building Permit Required), the underlying use, construction, alteration, or occupancy itself also requires a written building permit from the City Building Inspector. West Haven does not publish a standalone certificate-of-occupancy or change-of-use application form or fee — per § 157.691, the certificate of occupancy 'shall be applied for coincidentally with the application for a building permit,' and is billed under the same general WHCC § 151.15 Building Permit Fee mechanism used for all other building-permit-triggering work in the city.
Verified 2026-07-22 · Source
When you need this permit
- No land may be used or occupied, and no building may be used or changed in use (except for agricultural purposes), until a certificate of occupancy is issued by the Building Inspector, per WHCC § 157.691
- A like certificate is required to maintain, renew, change, or extend a nonconforming use, per WHCC § 157.691
- The certificate of occupancy application is filed coincidentally with the building permit application — West Haven does not publish a separate standalone certificate-of-occupancy or change-of-use application form
- The underlying use, construction, alteration, repair, removal, or occupancy also requires a written building permit from the City Building Inspector, per WHCC § 157.690, unless the work is minor in character as determined by the Building Inspector
- Certificate of occupancy is to be issued within 10 days after the erection or structural alteration of the building (or applicable part) is completed in conformity with the zoning ordinance, per WHCC § 157.691
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Building Inspection
Confirms the completed work (or existing building/use, for a change-of-use or nonconforming-use certificate) complies with the zoning ordinance, per WHCC § 157.691, prior to certificate of occupancy issuance.
See the full West Haven inspection guide — scheduling & re-inspection fees →
Tips
- West Haven has no standalone certificate-of-occupancy or change-of-use permit product, application form, or fee — per WHCC § 157.691, it is applied for coincidentally with the building permit application and billed under the same general Building Permit Fee (WHCC § 151.15).
- A certificate of occupancy is also required to maintain, renew, change, or extend a nonconforming use, per WHCC § 157.691 — not just for new construction or a literal change in a building's use.
- Occupying a structure before the certificate of occupancy is issued carries a published penalty of $300.00 per day, per the city's Consolidated Fees & Fines Schedule (adopted 9/17/2025).
- The 10-working-day issuance window in WHCC § 157.691 runs from completion of the erection or structural alteration, not from application submittal — it is not directly comparable to the city's separately published 7-14/14-21 working-day initial plan-review figures.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Haven building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in West Haven
Certificate of Occupancy / Change of Use in other cities
Compare certificate of occupancy / change of use fees across Utah →
Look up this fee in a different city →
Now live
Build your West Haven project checklist
Describe your project once and get every permit, document, and fee it triggers in West Haven — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →