Required for plumbing installations, alterations, and repairs in Laramie. Governed by the 2024 International Plumbing Code (IPC). Charged per the City's Plumbing Unit Fee Schedule (a base permit fee plus itemized per-fixture/system fees), separate from the valuation-based building permit table.

Verified 2026-07-17 · Source

When you need this permit

  • Base plumbing permit fee plus itemized per-item fees for fixtures, sewer/water service, gas piping, boilers, and water heaters
  • Applications submitted through the Civic Access portal
  • 24-hour advance notice required to schedule inspections
  • Separate permit from the general building permit — required even when submitted alongside a building permit application

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Base Permit FeeCity of Laramie Plumbing Permit Application form / Plumbing Unit Fee Schedule
$20.00
Supplemental Permit
$10.00
Sewer Service Installation or Replacement
$15.00
Water Service Installation or Replacement
$15.00
Each Plumbing Fixture or Trap
$7.00
Gas Piping, up to and including 5 outlets
$5.00 (each additional outlet over 5: $1.00)
Water Heater
$7.00
Each New or Enlarged Water or Sewer Service Tap at MainCity of Laramie Plumbing Unit Fee Schedule (Electrical, Mechanical and Plumbing Permit Fee Schedules document)
$20.00
Boiler System to 500,000 Btu/hPlumbing Unit Fee Schedule item 9
$27.15
Boiler System to 1,000,000 Btu/h
$37.25
Lawn Sprinkler System
$7.00

Review timeline

Plan reviewTypical estimate — confirm current times with the Laramie building department
~1–21 business days

How long did your Plumbing Permit permit actually take in Laramie?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Underground / Rough-In

    Before pipes are concealed — verify slope, materials, connections

  2. 2

    Final

    All fixtures connected, no leaks, proper venting verified

See the full Laramie inspection guide — scheduling & re-inspection fees →

Tips

  • Laramie uses the 2024 International Plumbing Code (IPC), not the Uniform Plumbing Code used by some other Wyoming/western jurisdictions.
  • The plumbing fee schedule is itemized per fixture/system (not valuation-based) — add the base permit fee plus each applicable line item.
  • Call at least 24 hours in advance to schedule any plumbing inspection.

Frequently asked questions

Laramie requires a plumbing permit for: Base plumbing permit fee plus itemized per-item fees for fixtures, sewer/water service, gas piping, boilers, and water heaters; Applications submitted through the Civic Access portal; 24-hour advance notice required to schedule inspections; Separate permit from the general building permit — required even when submitted alongside a building permit application. If your project isn't listed, confirm with City of Laramie Code Administration Division (Building Department) at (307) 721-5271 before starting work.

No. Plumbing permits in Laramie use an itemized unit fee schedule (a base permit fee plus per-fixture and per-system charges), unlike the building permit, which is valuation-based.

Plan review for a plumbing permit in Laramie typically runs 1–21 business days. This is an estimate, not a published figure — confirm current review times with City of Laramie Code Administration Division (Building Department) at (307) 721-5271.

You'll need: Plumbing Permit Application (via Civic Access portal, or the City's paper Plumbing/Mechanical/Electrical Permit Application form). See the required-documents checklist on this page for details on each.

Laramie requires 2 inspection(s) for a plumbing permit, in order: Underground / Rough-In, Final. Schedule each through City of Laramie Code Administration Division (Building Department) ((307) 721-5271).

Apply through City of Laramie Code Administration Division (Building Department) at 320 E. Grand Avenue, Laramie, WY 82070 (temporary location while the Historic Carnegie Building at 405 Grand Avenue undergoes renovations; mailing address P.O. Box C, Laramie, WY 82073). Phone: (307) 721-5271, email: codeadmin@cityoflaramie.org. Office hours: Mon–Fri, 9:00 a.m.–3:00 p.m. (per Building Department Staff page, current); older bulletins/forms list Mon–Thu 8 a.m.–4 p.m., Fri 8 a.m.–2 p.m. — confirm current hours by phone. Official information: https://www.cityoflaramie.org/432/Building-Permits-and-Informational-Bulletins.

Laramie, Wyoming has adopted: 2024 International Building Code (IBC) — adopted by the City of Laramie (Bulletin #2 Codes and Design Information, Feb. 2026 edition); Contractor Licensing page confirms the City adopted the 2024 ICC cycle effective September 1, 2024; 2024 International Residential Code (IRC) for One- and Two-Family Dwellings; 2024 International Existing Building Code (IEBC); 2024 International Mechanical Code (IMC); 2024 International Plumbing Code (IPC) — Laramie uses IPC (per Building Department (Code Administration) page), not the Uniform Plumbing Code; 2024 International Fuel Gas Code (IFGC); 2024 International Property Maintenance Code (IPMC); 2024 International Fire Code (IFC); 2024 International Energy Conservation Code (IECC); 2026 National Electrical Code (NEC), published by NFPA, adopted with certain local amendments, additions and deletions [2026-07-17 re-verification RESOLVED: LMC § 15.24.030(A)(1) adopts the NEC ambulatorily — "the most recently issued editions of the National Electrical Code is adopted by reference" — in a dedicated NEC-specific section (not merely inherited from the ICC cycle), so the governing edition tracks whatever NFPA's current edition is. The Wyoming State Fire Marshal confirms the 2026 NEC took effect statewide July 1, 2026 (wsfm.wyo.gov/electrical-safety). The City's Informational Bulletin #2 (dated Feb. 2026, i.e. before that July 1 transition) still lists "(2023)" — accurate when written, now stale, not a genuine ordinance/bulletin conflict. The 2023 NEC is retained here only as prior-edition history; see electrical-permit tips for the full resolution]; ICC A117.1 (2017) — ADA/accessibility standard; Laramie Municipal Code (LMC) Title 15.24 — Buildings and Construction (local amendments to the above codes); most recently amended by Ordinance No. 1881 (effective May 23, 2026) and Ordinance No. 1870 (effective Sept. 19, 2025). Local amendments apply — see the Laramie overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-17.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Laramie building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.