Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Campbell County, Wyoming.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
500 S. Gillette Ave., Suite 1500, Gillette, WY 82716
Phone
(307) 682-1970
Office hours
Mon–Fri, 8:00 a.m.–5:00 p.m.

Published scheduling rules

  • Call (307) 682-1970 at least 24 hours in advance to schedule inspections; appointments are honored on a first-come, first-served basis. (Residential Building Permit (New Construction))
  • Construction inspections are scheduled directly with the Fire Department (307-682-5319) with a minimum of 48 hours advance notice (Fire Sprinkler & Fire Alarm System Permit)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing

    Before concrete pour

  2. 2

    Stemwall

    Foundation stemwall inspection

  3. 3

    Service Utility Lines

    Water, gas, sewer service connections

  4. 4

    Rough-In (framing, electric, plumbing, HVAC)

    After framing and MEP rough-in, before drywall

  5. 5

    Drywall

    Before finishing

  6. 6

    Small Wastewater System (Septic/Leach field)

    Tank, pipe, chambers, and rock left exposed for inspection

  7. 7

    Final

    All work complete; required for Certificate of Occupancy

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Foundation

    For new-construction detached or attached ADUs

  2. 2

    Framing

    Structural framing, fire/sound separation if attached

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-in

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Commercial Building Permit / Tenant Improvement

  1. 1

    Foundation/Footing

    Before concrete pour

  2. 2

    Framing/Structural

    Structural, fire-resistant construction verification

  3. 3

    MEP Rough-In

    Electrical, plumbing, mechanical, fire protection rough-in

  4. 4

    Final

    All work complete, ready for Certificate of Occupancy

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Sprinkler Rough-In

    Underground/rough piping inspection before concealment, per Fire Department construction inspection types

  2. 2

    Sprinkler Hydrostatic Test

    Hydrostatic pressure test of the completed sprinkler system

  3. 3

    Fire Alarm Acceptance

    Final acceptance test of the installed fire alarm system

  4. 4

    Knox Box Mounting/Key

    Verification of Knox Box key-box installation and Fire Department key deposit, required for new commercial occupancies before occupancy is granted

Applies to: Deck Permit

  1. 1

    Footers

    Before concrete is poured

  2. 2

    Framing

    Required only when the deck is close to the ground, making floor joist/beam/post inspection otherwise impossible after decking is installed

  3. 3

    Final

    All framing installed and deck completed

Applies to: Plumbing Permit

  1. 1

    Underground/Under-slab

    Before concrete pour or backfill — verify pipe slope, materials, cleanouts

  2. 2

    Rough-In

    After piping installed, before walls closed

  3. 3

    Final

    All fixtures connected, no leaks

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing/Foundation (if new footings)

    Before concrete pour

  2. 2

    Rough-In (framing, electric, plumbing, HVAC)

    Before walls closed

  3. 3

    Final

    All work complete per approved plans

Applies to: Electrical Permit

  1. 1

    Rough-In

    Wiring and boxes installed before walls closed

  2. 2

    Final

    All devices installed, system energized

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough-In

    Wiring/conduit for the EV charger circuit installed before walls closed, if applicable

  2. 2

    Final

    Charger circuit/equipment installed, breaker sized correctly, system energized

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In/Equipment

    Equipment installation and ductwork before walls closed

  2. 2

    Final

    Equipment operational, venting/combustion air verified

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement

  2. 2

    Final

    Racking/structural and electrical interconnection verified

Re-inspection fees

Commercial Building Permit / Tenant ImprovementCommercial Building Inspection — re-inspection · Chapter 4 Section 1.8.C — the first two inspections for each portion of work are free; each additional re-inspection for incorrectly performed work is $60, payable in person before scheduling
$60.00 per re-inspection

Unincorporated Campbell County building permits

Get alerts for Unincorporated Campbell County

We'll email you when Unincorporated Campbell County's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.