Residential Building Permit (New Construction) in Unincorporated Campbell County, Wyoming

Verified

Required for new single-family and two-family dwellings located INSIDE a Platted Subdivision in unincorporated Campbell County, governed by the 2024 IRC per Chapter 4 Section 4. Building Permits are NOT required for one- or two-family dwellings built OUTSIDE a platted subdivision (Chapter 4 Section 1.4.A.3) — see 'Building a Home on Rural Property' guidance — though electrical, mechanical, plumbing, and septic permits still apply in that case.

Verified 2026-07-01 · Source

No feeResidential Building Permit

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Residential Building PermitNo feeCampbell County Chapter 4 Rules Regulating Construction, Section 1.8.E 'All Other Permits: No fees.' (Amended June 2026) — applies to one- and two-family residential building permits; only Commercial Building Permits carry the $250 fee under Section 1.8.A.
Zoning CertificateNo feeChapter 7 Zoning Regulations, Section 10.25(7)(a)(i)
Work commenced before obtaining required permit$60.00Chapter 4 Section 1.8.D

Review timeline

310 business days

Unincorporated Campbell County’s published plan-review target

Inspection process

  1. 1

    Footing

    Before concrete pour

  2. 2

    Stemwall

    Foundation stemwall inspection

  3. 3

    Service Utility Lines

    Water, gas, sewer service connections

  4. 4

    Rough-In (framing, electric, plumbing, HVAC)

    After framing and MEP rough-in, before drywall

  5. 5

    Drywall

    Before finishing

  6. 6

    Small Wastewater System (Septic/Leach field)

    Tank, pipe, chambers, and rock left exposed for inspection

  7. 7

    Final

    All work complete; required for Certificate of Occupancy

Tips

Frequently asked questions

Do I need a building permit to build a home on rural (unplatted) property in Campbell County?
No building permit is required for a one- or two-family dwelling located outside a platted subdivision, per Chapter 4 Rules Regulating Construction § 1.4.A.3. However, you still need electrical, mechanical, plumbing, and Small Wastewater System (septic) permits, a completed Building Permit & Zoning Certificate Application for zoning/addressing purposes, an approved site plan, and proof of your water source.
How much does a residential building permit cost in unincorporated Campbell County?
There is no fee. Per Chapter 4 Section 1.8.E ('All Other Permits'), residential building, electrical, mechanical, plumbing, and small wastewater system permits are issued at no charge. Only Commercial Building Permits carry a $250 fee.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Campbell County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Unincorporated Campbell County

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.