PermitBaseMountain West

One and Two Family Building Permit in Jackson, Wyoming

Verified

Required to construct any new one- and two-family dwelling, accessory building, addition, alteration, or repair in the Town of Jackson. Governed by the 2024 IRC. All submittals are electronic to townbuilding@jacksonwy.gov; no over-the-counter permitting.

Verified 2026-07-01 · Source

$564.00Deposit on Building Permit (non-refundable, applied to full fee)

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Deposit on Building Permit (non-refundable, applied to full fee)$564.00JMC 15.04.020(7); Resolution 25-18 Appendix A Fee Schedule, effective July 22, 2025
Building Permit — Single Family Residence / Warehouse, storage and similar$1.70 per square footJMC 15.04.090; Resolution 25-18 Appendix A
Building Permit — Commercial, Office, Multi-family and similar$1.13 per square footResolution 25-18 Appendix A
Building Permit — Remodels and Alterations (valuation-based)$1 to $17,000 valuation = $288.00; $17,001-$40,000 = $288 + $12/additional $1,000; $40,001-$100,000 = $549 + $10/additional $1,000; $100,001-$500,000 = $1,157 + $8/additional $1,000; $500,001-$1,000,000 = $4,313 + $6/additional $1,000; $1,000,001-$5,000,000 = $7,130 + $4/additional $1,000; over $5,000,000 = $20,654 + $2/additional $1,000Resolution 25-18 Appendix A, Total Valuation fee calculation table
Plan Review Fee65% of the building permit feeResolution 25-18 Appendix A
Re-inspection / Outside-normal-hours / Plan revision review$85.00/hr to $113.00/hr depending on typeResolution 25-18 Appendix A, 'Other Inspections' line items
WUI Permit Review Fee (prerequisite, paid to Jackson Hole Fire/EMS)$150.00 non-refundable invoice feeTeton County / Jackson Hole Fire/EMS WUI Information for Contractors page

Review timeline

~4545 business days

Typical estimate — confirm current times with the Jackson building department

Inspection process

  1. 1

    Foundation / Footings

    Before concrete pour — footings below the 34-inch frost line or as specified by the soils engineer of record

  2. 2

    Rough Electrical

    Conducted by Jackson Hole Fire/EMS Electrical Division; required combination Rough Gas/Rough Plumbing/Rough Mechanical/Framing inspections can only be scheduled after a passed Rough Electrical inspection

  3. 3

    Combination Rough (Gas/Plumbing/Mechanical/Framing)

    Scheduled together after Rough Electrical passes

  4. 4

    Final / Certificate of Occupancy

    All departments (Building, Engineering, Fire/Electrical, Planning) must sign off on the Permit/Inspection Card before a Certificate of Occupancy or Completion is issued

Tips

Frequently asked questions

Do I need a WUI permit before I can apply for a building permit in Jackson?
Yes. Effective January 1, 2025, all private land in the Town of Jackson and Teton County is within the mapped Wildland-Urban Interface. You must obtain a WUI permit number from Jackson Hole Fire/EMS (via the SmartGov portal, $150 non-refundable review fee) before the Building Department will accept your building permit submittal.
Can I submit a paper building permit application in Jackson?
No. The Town of Jackson does not accept hard/paper copies. All commercial and residential building permit submittals, including addenda, must be emailed to townbuilding@jacksonwy.gov (200 MB max file size).

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Jackson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Jackson

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.