Demolition Permit in Jackson, Wyoming
Required to demolish or remove any building or structure (or 50%+ of exterior walls/roof area, or any street-facing exterior wall) within Town of Jackson limits. All demolition applications are referred to the Teton County Historic Preservation Board (TCHPB) for review.
Verified 2026-07-01 · Source
When you need this permit
- Applies to: any exterior wall facing a public street/right-of-way; 50%+ of exterior walls measured continuously; 50%+ of roof area in plan view
- All demolition applications referred to the Teton County Historic Preservation Board (TCHPB), which has 45 calendar days to determine historic/architectural significance or age (50+ years)
- If TCHPB finds significance, it recommends a stay of 60-100 days on permit issuance for public comment and exploration of alternatives
- Application packet required PER STRUCTURE being demolished, emailed to townbuilding@jacksonwy.gov
- Demolition plans must show extent of work, utility abandonment/patching, finished-conditions plan (backfill to grade, no slopes steeper than 2:1), construction access/stabilization, equipment parking, and silt fencing location
- Elevation photographs (front/back/sides) of each structure to be demolished required
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Pre-Demolition Utility Verification
Confirm gas, electric, water, sewer disconnects arranged
- 2
Final
Site cleared, backfilled to grade, debris removed
See the full Jackson inspection guide — scheduling & re-inspection fees →
Tips
- Budget at least 45 days for the Teton County Historic Preservation Board review alone (before any additional stay if the structure is found historically/architecturally significant or is 50+ years old) — this can add 60-100 more days.
- Submit one application packet per structure being demolished, even if multiple structures are demolished as part of the same project.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Jackson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Jackson's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Jackson yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Jackson lands. Privacy.
Other permits in Jackson
Demolition Permit in other cities
Compare demolition permit fees across Wyoming →