Required for installation of automatic fire-extinguishing (sprinkler) systems and fire alarm/detection systems in the Town of Jackson, administered by the Jackson Hole Fire/EMS Department's Fire Division under the adopted 2024 International Fire Code (JMC 15.08.010). SmartGov tracks these as four distinct application categories (Fire Alarm and Detection Systems, Automatic Extinguishing Systems, Fire Sprinkler Commercial, Fire Sprinkler Residential), but the Town of Jackson's own adopted fee schedule (Resolution 25-18 Appendix A) does not split fees by category — all are billed under the same valuation-based Fire Protection Construction Permit table. Important: the separate 2025/2026 'Jackson Hole Fire/EMS Master Fee Schedule' (Resolution 25-031) is explicitly scoped to 'Unincorporated Areas of Teton County outside of the Town of Jackson' and does NOT apply within Town limits — the Town's own Resolution 25-18 Appendix A fee table governs here instead, even though the same Fire/EMS staff administer both.

Verified 2026-07-22 · Source

When you need this permit

  • A permit and Jackson Hole Fire/EMS plan review are required before installing any fire alarm/detection system or automatic fire-extinguishing (sprinkler) system, per the adopted 2024 IFC (JMC 15.08.010)
  • Structures 5,000 sq ft or larger, regardless of occupancy, must be protected by an approved automatic fire sprinkler system (JMC 15.04.020(b)(14) local amendment, also documented in this file's localAmendments)
  • Applications submitted and inspections requested via the shared SmartGov portal (co-teton-wy.smartgovcommunity.com), used jointly by the Town of Jackson and Teton County, under one of four application categories: Fire Alarm and Detection Systems, Automatic Extinguishing Systems, Fire Sprinkler Commercial, or Fire Sprinkler Residential
  • Use of outside consultants for plan review is billed at actual cost if Fire/EMS staff cannot perform the review in-house
  • Existing buildings with previously-installed fire alarm/sprinkler systems are subject to a separate annual existing-building inspection and, upon new business registration, a separate registration inspection — distinct from the one-time new-installation construction permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

All Construction Plan Reviews (2-hour minimum charge)JMC 15.08.010; Resolution 25-18 Appendix A, Fire Permits (IFC and IWUIC) section — directly re-verified against the downloaded PDF fee schedule, 2026-07-22
$154.00/hr
All Construction Plan Resubmittal Reviews (1/2-hour minimum charge)Resolution 25-18 Appendix A, Fire Permits (IFC and IWUIC) section
$102.00/hr
Fire Protection Construction Permit — valuation-basedResolution 25-18 Appendix A, Fire Protection Construction Permit Valuation table — directly re-verified against the downloaded PDF fee schedule, 2026-07-22; same table already cited in this file's commercial-tenant-improvement-permit entry
$41.00 for the first $500 (Valuation $1.00-$500.00), scaling through defined bands ($75.48 at $2,000; $422.67 at $25,000; $697.72 at $50,000; $1,081.50 at $100,000; $3,537.72 at $500,000) up to $6,096.26 for the first $1,000,000 plus $4.09 per additional $1,000 or fraction thereof over $1,000,000
Operational PermitsResolution 25-18 Appendix A, Fire Permits (IFC and IWUIC) section — covers ongoing/operational fire permits, distinct from the one-time construction permit
$102.00
Re-inspection of New ConstructionResolution 25-18 Appendix A, Fire Permits (IFC and IWUIC) section
$102.00/hr
Annual Existing Building InspectionResolution 25-18 Appendix A — applies to existing fire alarm/sprinkler systems in already-occupied buildings, not new installations
$102.00
For each Fire Sprinkler System (Plumbing Permit line item)JMC 15.24.030; Resolution 25-18 Appendix A, Plumbing Permits section — a separate token per-system fee charged under the Plumbing Permit for the water-supply/piping tie-in, distinct from and in addition to the Fire Division's valuation-based Fire Protection Construction Permit fee above
$18.00

Review timeline

Plan review
Not published — contact the department

How long did your Fire Sprinkler / Fire Alarm Permit permit actually take in Jackson?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough — System Installation

    Sprinkler piping, alarm wiring, and device rough-in inspected before concealment

  2. 2

    Final — Acceptance Test

    Hydrostatic test (sprinkler systems) or functional alarm test witnessed by Jackson Hole Fire/EMS before the system is placed in service

See the full Jackson inspection guide — scheduling & re-inspection fees →

Tips

  • The 2025/2026 Jackson Hole Fire/EMS 'Master Fee Schedule' (Resolution 25-031) does NOT apply inside Town of Jackson limits — its own text scopes it to 'Applicability-Unincorporated Areas of Teton County outside of the Town of Jackson,' effective January 1, 2026. Within the Town, fire permit fees are set by the Town's own Resolution 25-18 Appendix A, 'Fire Permits (IFC and IWUIC)' section, even though Jackson Hole Fire/EMS is the same department administering both areas.
  • SmartGov lists Fire Alarm and Detection Systems, Automatic Extinguishing Systems, Fire Sprinkler Commercial, and Fire Sprinkler Residential as four separate application categories, but the Town's adopted fee schedule does not split fees by category — all are billed under the same valuation-based Fire Protection Construction Permit table.
  • A separate $18.00 'For each Fire Sprinkler System' line exists under the Plumbing Permit fee table (JMC 15.24.030) in addition to the Fire Division's valuation-based construction permit fee — budget for both if the project includes a sprinkler system.

Frequently asked questions

Jackson requires a fire sprinkler / fire alarm permit for: A permit and Jackson Hole Fire/EMS plan review are required before installing any fire alarm/detection system or automatic fire-extinguishing (sprinkler) system, per the adopted 2024 IFC (JMC 15.08.010); Structures 5,000 sq ft or larger, regardless of occupancy, must be protected by an approved automatic fire sprinkler system (JMC 15.04.020(b)(14) local amendment, also documented in this file's localAmendments); Applications submitted and inspections requested via the shared SmartGov portal (co-teton-wy.smartgovcommunity.com), used jointly by the Town of Jackson and Teton County, under one of four application categories: Fire Alarm and Detection Systems, Automatic Extinguishing Systems, Fire Sprinkler Commercial, or Fire Sprinkler Residential; Use of outside consultants for plan review is billed at actual cost if Fire/EMS staff cannot perform the review in-house; Existing buildings with previously-installed fire alarm/sprinkler systems are subject to a separate annual existing-building inspection and, upon new business registration, a separate registration inspection — distinct from the one-time new-installation construction permit. If your project isn't listed, confirm with Town of Jackson Planning & Building Department — Building Division at 307-733-0440, ext. 1352 (Building Inspection Hotline: 307-733-0520, ext. 1351) before starting work.

No. The 2025/2026 Jackson Hole Fire/EMS Master Fee Schedule (Resolution 25-031) is explicitly scoped to unincorporated Teton County outside the Town of Jackson. Inside Town limits, fire permit fees are set by the Town's own Resolution 25-18 Appendix A, 'Fire Permits (IFC and IWUIC)' section, under JMC 15.08.010.

Jackson does not publish a plan-review timeline for this permit. Contact Town of Jackson Planning & Building Department — Building Division at 307-733-0440, ext. 1352 (Building Inspection Hotline: 307-733-0520, ext. 1351) for current turnaround.

You'll need: Fire Alarm/Sprinkler Permit Application (via SmartGov Portal); Fire Protection System Plans. Depending on your project, Jackson may also ask for: Associated Building Permit Number. See the required-documents checklist on this page for details on each.

Jackson requires 2 inspection(s) for a fire sprinkler / fire alarm permit, in order: Rough — System Installation, Final — Acceptance Test. Schedule each through Town of Jackson Planning & Building Department — Building Division (307-733-0440, ext. 1352 (Building Inspection Hotline: 307-733-0520, ext. 1351)).

Apply through Town of Jackson Planning & Building Department — Building Division at 150 E Pearl Avenue, Jackson, WY 83001 (P.O. Box 1687, Jackson, WY 83001). Phone: 307-733-0440, ext. 1352 (Building Inspection Hotline: 307-733-0520, ext. 1351), email: townbuilding@jacksonwy.gov. Office hours: The Town does not do over-the-counter permitting; all submittals are electronic. Inspections conducted virtually Tuesdays/Thursdays and in-person Mondays/Wednesdays/Fridays.. Official information: https://www.jacksonwy.gov/181/Building.

Jackson, Wyoming has adopted: 2024 International Building Code (IBC), including appendices B, I, J — applications on/after Jan 1, 2025 (Jackson Municipal Code 15.04.020); 2024 International Residential Code (IRC) — for one- and two-family dwellings (JMC 15.17.010; Design Criteria page); 2024 International Existing Building Code (IEBC) (JMC 15.06.010); 2021 International Energy Conservation Code (IECC) (per Town of Jackson Design Criteria page); 2024 International Fuel Gas Code (IFGC) (JMC 15.27.010); 2024 International Mechanical Code (IMC) (JMC 15.12.010); 2024 International Plumbing Code (IPC) (JMC 15.24.010); National Electrical Code (NEC), current edition adopted by the Wyoming State Fire Marshal's Office (JMC 15.20.010) — enforced by Jackson Hole Fire/EMS Electrical Division; 2024 International Fire Code (IFC) and 2024 International Wildland-Urban Interface Code (IWUIC) — adopted jointly by Town of Jackson and Teton County; enforced by Jackson Hole Fire/EMS (JMC 15.08.010). Local amendments apply — see the Jackson overview page for the full list.

Not under the Town's adopted fee schedule — both are billed under the same valuation-based Fire Protection Construction Permit table (Resolution 25-18 Appendix A), even though SmartGov tracks them as separate application categories (Fire Alarm and Detection Systems, Automatic Extinguishing Systems, Fire Sprinkler Commercial, Fire Sprinkler Residential).