Required for all permanent wiring installed in buildings and structures in the Town of Jackson. Per the WSFM 'LOCAL AND STATE JURISDICTIONS' chart, Jackson is L/L for electrical (BLDG L/L, ELEC L/L) — the Town holds delegated electrical authority. In practice, electrical permitting/inspection is administered by the Jackson Hole Fire/EMS Department's Electrical Division, a jointly-funded Town of Jackson / Teton County fire district, not a separate program of the Wyoming State Fire Marshal.

Verified 2026-07-01 · Source

$37.00 (up to $500) rising in defined valuation bands to $568.00 (at $24,000.01-$25,000)Valuation of Electrical Work — $1.00 to $25,000 (tiered table)

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Valuation of Electrical Work — $1.00 to $25,000 (tiered table)$37.00 (up to $500) rising in defined valuation bands to $568.00 (at $24,000.01-$25,000)JMC 15.20.010; Resolution 25-18 Appendix A — full tiered table (e.g., $1,000.01-$1,100 = $65.00; $5,000.01-$6,000 = $181.00; $10,000.01-$11,000 = $277.00; $20,000.01-$21,000 = $490.00)
Valuation of Electrical Work — $25,000.01 to $50,000$568 for the first $25,000 plus $11 per additional $1,000 or fraction thereofResolution 25-18 Appendix A
Valuation of Electrical Work — $50,000.01 to $100,000$1,023 for the first $50,000 plus $8 per additional $1,000 or fraction thereofResolution 25-18 Appendix A
Valuation of Electrical Work — $100,000.01 and up$1,554 for the first $100,000 plus $6 per additional $1,000 or fraction thereofResolution 25-18 Appendix A
Connect all temporary services$36.00Resolution 25-18 Appendix A
Work started before permit was issued2x the permit feeResolution 25-18 Appendix A
Electrical Plan Reviews65% of the permit feeResolution 25-18 Appendix A
Failed Final Inspection Fee$102.00Resolution 25-18 Appendix A

Review timeline

~110 business days

Typical estimate — confirm current times with the Jackson building department

Inspection process

  1. 1

    Temporary Service

  2. 2

    Rough Wiring

    Includes a Low Voltage Rough Wiring inspection type where applicable

  3. 3

    Service

  4. 4

    Final

    Includes a Low Voltage Final inspection type where applicable

Tips

Frequently asked questions

Does the Town of Jackson or the State of Wyoming issue electrical permits in Jackson?
The Town of Jackson (jointly with Teton County) issues electrical permits through the Jackson Hole Fire/EMS Department's Electrical Division — a locally-run, jointly-funded fire district program, not the Wyoming State Fire Marshal's statewide default electrical program. This matches the WSFM jurisdictions chart classification of Jackson as ELEC L/L.
Can a homeowner wire their own ARU (accessory dwelling unit) in Jackson?
No. While Jackson allows a homeowner to wire their own occupied residence (including ordinary accessory buildings) without a state license, this exemption explicitly excludes Accessory Residential Units (ARUs) per the Town's contractor licensing rules — ARU electrical work requires a licensed electrical contractor.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Jackson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Jackson

Related guides

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.