Required for electrical installations, alterations, and service changes within the City of Casper. Casper's Building Inspection Division holds delegated local electrical authority and performs its OWN electrical plan review and inspections under the 2023 NFPA 70 NEC — electrical permits here are NOT issued by the Wyoming State Fire Marshal's statewide electrical program.

Verified 2026-07-16 · Source

When you need this permit

  • Electrical Permit Application submitted to the Building Inspection Division (via CSS Portal or in person)
  • Service changes, panel upgrades, new circuits, rewiring for additions/alterations
  • Governed by the 2023 NFPA 70 National Electrical Code
  • Fee based on the value of the work per the City's combined valuation-based fee schedule
  • Casper's Building Inspection Division performs its own electrical plan review and inspections (Temporary Power, Rough Electrical, Service, Final Electrical) per the City's own Inspection Information page, confirmed live 2026-07-16

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Initial Building Permit FeeCity of Casper Permit Fee Schedule (eff. February 2, 2026) — Casper does not publish a separate electrical-only fee table; electrical work is priced off the combined valuation table
$35
Combined Building/Electrical/Plumbing/Mechanical Permit Fee — valuation-basedCity of Casper Permit Fee Schedule (eff. February 2, 2026) — labeled 'Combined Building, Electrical, Plumbing and Mechanical Permit Fee Schedule'
Graduated table from $70 (valuation $1–$1,000) up to $841 (valuation $99,001–$100,000); over $100,000 = $806 + $5.60 per additional $1,000 or fraction thereof

Review timeline

Plan reviewTypical estimate — confirm current times with the Casper building department
~1–10 business days

How long did your Electrical Permit permit actually take in Casper?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Temporary Power

    For a temporary power pole or similar setup used during construction

  2. 2

    Rough Electrical

    Performed after the structure is framed and dried in, and after electrical components are roughed in, before trim out

  3. 3

    Service

    Performed for service replacement and for permanent power to new structures; structure must be secured prior to requesting

  4. 4

    Final Electrical

    Performed when all electrical work is 100% complete; typically coordinated with other trades as part of Final/C.O. inspection

See the full Casper inspection guide — scheduling & re-inspection fees →

Tips

  • IMPORTANT: Casper issues its own electrical permits and runs its own electrical inspections (Temporary Power, Rough Electrical, Service, Final) — this differs from Wyoming jurisdictions that default to the WY State Fire Marshal's statewide electrical program under W.S. § 35-9-119.
  • Casper's Building Inspection Division staff runs its own electrical inspections (per the City's Inspection Information page), confirming delegated local electrical enforcement authority under W.S. § 35-9-121; the City's Building and Fire Code Resources staff listing (re-checked 2026-07-16) currently names a Chief Building Official, Deputy Building Official, and Building Inspector but no longer names a separate Electrical Inspector by title.
  • Confirm current licensing/registration requirements for electrical contractors with Casper's Contractor Licensing program before applying.
  • There is no separate published electrical-only fee table — electrical work valuation is priced off the same combined Building/Electrical/Plumbing/Mechanical table used for building permits.

Frequently asked questions

Casper requires an electrical permit for: Electrical Permit Application submitted to the Building Inspection Division (via CSS Portal or in person); Service changes, panel upgrades, new circuits, rewiring for additions/alterations; Governed by the 2023 NFPA 70 National Electrical Code; Fee based on the value of the work per the City's combined valuation-based fee schedule; Casper's Building Inspection Division performs its own electrical plan review and inspections (Temporary Power, Rough Electrical, Service, Final Electrical) per the City's own Inspection Information page, confirmed live 2026-07-16. If your project isn't listed, confirm with City of Casper Community Development Department — Building Inspection Division at (307) 235-8254 before starting work.

In Casper, the published Initial Building Permit Fee is: $35. Additional published fees: Combined Building/Electrical/Plumbing/Mechanical Permit Fee — valuation-based — Graduated table from $70 (valuation $1–$1,000) up to $841 (valuation $99,001–$100,000); over $100,000 = $806 + $5.60 per additional $1,000 or fraction thereof. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for an electrical permit in Casper typically runs 1–10 business days. This is an estimate, not a published figure — confirm current review times with City of Casper Community Development Department — Building Inspection Division at (307) 235-8254.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Casper requires 4 inspection(s) for an electrical permit, in order: Temporary Power, Rough Electrical, Service, Final Electrical. Schedule each through City of Casper Community Development Department — Building Inspection Division ((307) 235-8254).

Apply through City of Casper Community Development Department — Building Inspection Division at 200 N David St, Casper, WY 82601. Phone: (307) 235-8254, email: building@casperwy.gov. Office hours: Mon–Fri 8:00 AM–5:00 PM (in-person/phone code consultation available 8:00–9:00 AM and 4:00–5:00 PM). Official information: https://www.casperwy.gov/services/building_and_inspections/index.php.

Casper, Wyoming has adopted: 2024 International Building Code (IBC); 2024 International Residential Code (IRC); 2024 International Fire Code (IFC); 2024 International Existing Building Code (IEBC); 2024 International Energy Conservation Code (IECC) — applies to the building thermal envelope ONLY per City of Casper adoption note; 2024 International Plumbing Code (IPC); 2024 International Fuel Gas Code (IFGC); 2024 International Mechanical Code (IMC); 2023 NFPA 70 National Electrical Code (NEC); ICC A117.1-2009 Accessible and Usable Buildings and Facilities. Local amendments apply — see the Casper overview page for the full list.

The City of Casper issues its own electrical permits and performs its own electrical inspections through its Building Inspection Division. This is because Casper holds delegated local building/electrical code enforcement authority under W.S. § 35-9-121, rather than defaulting to the Wyoming State Fire Marshal's statewide electrical program. Confirm current requirements with the Building Inspection Division at (307) 235-8254.

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casper building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.