Inspection sequence, scheduling, and re-inspection fees for building permits in Casper, Wyoming.

Verified 2026-07-16 · Source

How to schedule

Inspections are requested through the building department below.

Address
200 N David St, Casper, WY 82601
Phone
(307) 235-8254
Office hours
Mon–Fri 8:00 AM–5:00 PM (in-person/phone code consultation available 8:00–9:00 AM and 4:00–5:00 PM)

Published scheduling rules

  • The Building Inspection Division recommends submitting all permits and inspection requests through the CSS (EnerGov) Portal at eg.casperwy.gov for status tracking. (Residential Building Permit (New Construction))

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footer / Caisson / Monolithic Slab

    Hole depth and rebar/form placement before concrete pour

  2. 2

    Foundation Wall

    Rebar and form placement for foundation walls

  3. 3

    Framing

    Performed after structure is framed and all electrical, plumbing, and mechanical rough-ins are installed and inspected

  4. 4

    Insulation

    Proper R-values and placement, performed after framing

  5. 5

    Drywall

    Proper thickness/type of drywall and screw placement

  6. 6

    Final / Certificate of Occupancy

    All work 100% complete; required before occupancy of the structure

Applies to: Plumbing Permit

  1. 1

    Outside Water and Sewer

    For outside water and sewer piping and connections prior to backfill

  2. 2

    Underground Plumbing

    For piping/connections under floor slabs or in crawl spaces prior to being covered

  3. 3

    Rough Plumbing (Top-Out)

    After structure is framed and dried in and plumbing is roughed in, before trim out; system should be pressured before inspection

  4. 4

    Gas Line (Inside and Outside Gas)

    After all gas piping installed; lines should be pressurized before inspection

  5. 5

    Final Plumbing

    Performed when all plumbing work is 100% complete

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footer/Foundation (if new footings)

    Before concrete pour, for additions requiring new foundation elements

  2. 2

    Framing

    After framing complete and MEP rough-ins installed and inspected

  3. 3

    Insulation

    Proper R-values and placement before drywall

  4. 4

    Drywall

    Thickness/type and screw placement

  5. 5

    Final

    All work complete per approved plans

Applies to: Accessory Dwelling Unit (ADU) Permit

  1. 1

    Footer/Foundation

    Before concrete pour

  2. 2

    Framing

    Structural framing and MEP rough-ins

  3. 3

    Insulation

    Proper R-values and placement

  4. 4

    Final

    All work complete, ready for occupancy

Applies to: Basement Finish Permit

  1. 1

    Framing

    After framing complete and MEP rough-ins are installed and inspected, including egress window verification

  2. 2

    Insulation

    Proper R-values and placement

  3. 3

    Drywall

    Thickness/type and screw placement

  4. 4

    Final

    All work complete per approved plans

Applies to: Commercial Tenant Improvement Permit

  1. 1

    Framing

    After framing and MEP rough-ins are installed and inspected

  2. 2

    Insulation

    If applicable to the scope of work

  3. 3

    Drywall

    Thickness/type and screw placement

  4. 4

    Final / Certificate of Occupancy

    All work complete; required before occupancy

Applies to: Electrical Permit

  1. 1

    Temporary Power

    For a temporary power pole or similar setup used during construction

  2. 2

    Rough Electrical

    Performed after the structure is framed and dried in, and after electrical components are roughed in, before trim out

  3. 3

    Service

    Performed for service replacement and for permanent power to new structures; structure must be secured prior to requesting

  4. 4

    Final Electrical

    Performed when all electrical work is 100% complete; typically coordinated with other trades as part of Final/C.O. inspection

Applies to: Deck Permit

  1. 1

    Footer

    Footing depth and placement before concrete pour

  2. 2

    Framing

    Deck framing, ledger attachment, and guardrail/handrail before decking installed (as required by inspector)

  3. 3

    Final

    Completed deck per approved plans

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before concealment

  2. 2

    Final Electrical

    All connections, inverter, and interconnection point verified

  3. 3

    Final (Building/Structural)

    Racking attachment and roof penetration sealing verified

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    Performed after electrical components are roughed in, before trim out, if applicable to the installation

  2. 2

    Final Electrical

    Performed when the charger installation is 100% complete and all connections/protections are verified per the 2023 NFPA 70 NEC

Applies to: Fire Sprinkler / Fire Alarm Permit

  1. 1

    Rough-In

    Sprinkler piping or alarm wiring/devices inspected before concealment — standard practice under the adopted IFC/NFPA standards; Casper-specific inspection-sequence naming was not independently confirmed against a published CFD checklist

  2. 2

    Final / Acceptance Test

    Hydrostatic/flow test (sprinkler) or full functional test (alarm), typically witnessed by the fire code official before the system is placed in service — standard practice under the adopted IFC/NFPA standards; Casper-specific procedure was not independently confirmed

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Performed after structure is framed and dried in, and mechanical components are roughed in, before trim out

  2. 2

    Final Mechanical

    Performed when all mechanical work is 100% complete; typically coordinated with other trades as part of Final/C.O. inspection

Re-inspection fees

Fire Sprinkler / Fire Alarm PermitFire Sprinkler/Alarm Plan Review & Permit Fee · No dedicated fee line for fire sprinkler or fire alarm permits/plan review was found in the City of Casper Permit Fee Schedule (eff. February 2, 2026, reviewed in full — 4 pages, no fire-related line item) or the City's central Fee Schedules index page (business/fee_schedules.php, reviewed live 2026-07-22 — lists only 'Community Development Department Fees' and 'Wireless Communication Facilities Application Fees,' no Fire Department fee schedule). Do not confuse with the Fire Self-Inspection Program's $150 initial / $300 re-inspection service fees (Resolution No. 24-77), which apply only to periodic compliance inspections of existing low-hazard occupancies, not to new fire-protection-system installation permits.
Not published

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casper building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Casper building permits

Get alerts for Casper

We'll email you when Casper's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.