Demolition Permit in Casper, Wyoming
VerifiedRequired for demolition of structures in Casper. Residential and commercial demolition are flat-fee permits; an Erosion Control Permit is also required if applicable to the site disturbance.
Verified 2026-07-01 · Source
When you need this permit
- Residential Demolition Permit: $200 flat fee, plus Erosion Control Permit if applicable
- Commercial Demolition Permit: $300 flat fee, plus Erosion Control Permit if applicable
- Erosion Control Permit required if applicable: $50 per acre, plus bond/surety
- Utility disconnects should be coordinated prior to demolition
Required documents
- Req
Building Permit Application
Used for demolition permit applications; specify demolition scope
- Opt
Erosion Control Permit Application
Required in addition to the demolition permit when the site disturbance qualifies for erosion control review
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Residential Demolition Permit | $200, plus Erosion Control Permit if applicable | City of Casper Permit Fee Schedule (eff. February 2, 2026) |
| Commercial Demolition Permit | $300, plus Erosion Control Permit if applicable | City of Casper Permit Fee Schedule (eff. February 2, 2026) |
| Erosion Control Permit | $50 per acre, plus bond/surety | — |
Review timeline
~5–15 business days
Typical estimate — confirm current times with the Casper building department
Inspection process
- 1
Final
Site inspection confirming demolition complete and site secured/cleared per approved scope
Tips
- Budget for the Erosion Control Permit ($50/acre plus bond/surety) in addition to the flat demolition fee if the project disturbs qualifying acreage.
- Coordinate utility disconnects (gas, electric, water, sewer) with the respective utility providers before demolition begins.
Frequently asked questions
- How much does a demolition permit cost in Casper?
- A residential demolition permit is $200 flat, and a commercial demolition permit is $300 flat, per the City of Casper Permit Fee Schedule (effective February 2, 2026). An Erosion Control Permit ($50/acre plus bond/surety) is required in addition if applicable to the site.
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
- City of Casper Community Development Department — Building Inspection Division — official building department
- City of Casper Permit Fee Schedule (eff. February 2, 2026)
- City of Casper — Permit Information
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casper building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Casper
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.