Change of Use / Certificate of Occupancy in Casper, Wyoming

Casper does not issue a standalone 'change of use' permit or a freestanding Certificate of Occupancy (C.O.) product separate from its building permit process — confirmed by direct review of the City's Permit Information page, Licenses and Permits page, and Permit Fee Schedule (eff. Feb 2, 2026), none of which list such a product. Per this file's own residential-building-permit and commercial-tenant-improvement-permit entries, 'Final / Certificate of Occupancy' is the final inspection step WITHIN the standard building permit process, not a separately purchasable permit. A genuine change in use or occupancy classification (without new construction) is governed by the 2024 International Existing Building Code (IEBC) — already listed in this file's codesAdopted — which contains dedicated Change of Occupancy provisions (IEBC Chapter 10) requiring compliance verification before the new use begins. Separately, registering a business at a new or different location is handled through the City's business-licensing process, though the specific 'change of location' mechanics were not independently confirmed.

Reviewed 2026-07-22 · Source

When you need this permit

  • No standalone change-of-use or certificate-of-occupancy permit application or fee line exists on Casper's Permit Information page or Fee Schedule — confirmed by direct review of both, live 2026-07-22
  • A Certificate of Occupancy is issued as the FINAL inspection sign-off of an underlying building permit (new construction, addition, or commercial tenant improvement) — see this file's residential-building-permit and commercial-tenant-improvement-permit entries, both of which list 'Final / Certificate of Occupancy' as their last inspection step
  • A change in use or occupancy classification without new construction is governed by the City's adopted 2024 International Existing Building Code (IEBC), which contains dedicated Change of Occupancy provisions (IEBC Chapter 10) — contact the Building Inspection Division at (307) 235-8254 to determine whether a specific change of use triggers a building permit under the IEBC
  • Business license registration, including registering a business at a new or different location, is handled through the City's business-licensing process via the CSS/EnerGov Portal, separate from the Building Inspection Division's permitting process — specific 'change of location' procedures were not independently confirmed as of this review
  • Contact Planning/Zoning at (307) 235-8241 to confirm the new use is allowed in the property's zoning district before applying for any building permit associated with a use change

Required documents

Check off what you have — your progress is saved on this device.

Fee schedule

Building Permit Fee (if construction/upgrades are triggered by the IEBC review)City of Casper Permit Fee Schedule (eff. February 2, 2026); applies only if the IEBC Chapter 10 change-of-occupancy review determines construction or life-safety upgrades are required
Combined valuation-based fee schedule (same table used for all other Casper building permits, starting at a $35 Initial Building Permit Fee)
Standalone Change-of-Use / Certificate-of-Occupancy FeeConfirmed by direct review of the City of Casper Permit Fee Schedule (eff. Feb 2, 2026), the Building Inspection Division's Permit Information page, and the City's Licenses and Permits page, live 2026-07-22 — none list a standalone change-of-use or certificate-of-occupancy fee
Not published — no such standalone fee line exists

Review timeline

Plan review
Not published — contact the department

How long did your Change of Use / Certificate of Occupancy permit actually take in Casper?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final / Certificate of Occupancy

    Confirms the space complies with applicable code requirements for its new use/occupancy classification before occupancy; performed as the final inspection of any building permit triggered by the change of use, consistent with this file's residential-building-permit and commercial-tenant-improvement-permit entries

See the full Casper inspection guide — scheduling & re-inspection fees →

Tips

  • Casper folds 'change of use' into its existing IEBC Chapter 10 (Change of Occupancy) building-code review rather than offering a separate change-of-use product — don't budget for a standalone C.O. fee that doesn't exist in the City's published fee schedule.
  • If a change of use doesn't require construction, the main obligations are likely a Planning/Zoning use-compatibility check (307-235-8241) and a business-license registration/update, not a Building Inspection Division permit — confirm with both offices, since this was not independently verified end-to-end.
  • Confirm zoning compatibility for the new use BEFORE signing a lease or starting a business-license application — Casper's zoning code (Title 17) determines whether the new use is even allowed in that district.

Frequently asked questions

Possibly — it depends on whether the new use changes the space's occupancy classification under the 2024 IEBC. Contact the Building Inspection Division at (307) 235-8254 and Planning/Zoning at (307) 235-8241 before signing a lease to confirm whether construction, life-safety upgrades, or a new Certificate of Occupancy inspection will be required.

In Casper, the published Building Permit Fee (if construction/upgrades are triggered by the IEBC review) is: Combined valuation-based fee schedule (same table used for all other Casper building permits, starting at a $35 Initial Building Permit Fee). Additional published fees: Standalone Change-of-Use / Certificate-of-Occupancy Fee — Not published — no such standalone fee line exists. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Casper does not publish a plan-review timeline for this permit. Contact City of Casper Community Development Department — Building Inspection Division at (307) 235-8254 for current turnaround.

Depending on your project, Casper may also ask for: Building Permit Application; Business License Application. See the required-documents checklist on this page for details on each.

Casper requires 1 inspection(s) for a change of use / certificate of occupancy permit, in order: Final / Certificate of Occupancy. Schedule each through City of Casper Community Development Department — Building Inspection Division ((307) 235-8254).

Apply through City of Casper Community Development Department — Building Inspection Division at 200 N David St, Casper, WY 82601. Phone: (307) 235-8254, email: building@casperwy.gov. Office hours: Mon–Fri 8:00 AM–5:00 PM (in-person/phone code consultation available 8:00–9:00 AM and 4:00–5:00 PM). Official information: https://www.casperwy.gov/services/building_and_inspections/index.php.

Casper, Wyoming has adopted: 2024 International Building Code (IBC); 2024 International Residential Code (IRC); 2024 International Fire Code (IFC); 2024 International Existing Building Code (IEBC); 2024 International Energy Conservation Code (IECC) — applies to the building thermal envelope ONLY per City of Casper adoption note; 2024 International Plumbing Code (IPC); 2024 International Fuel Gas Code (IFGC); 2024 International Mechanical Code (IMC); 2023 NFPA 70 National Electrical Code (NEC); ICC A117.1-2009 Accessible and Usable Buildings and Facilities. Local amendments apply — see the Casper overview page for the full list.

No. Casper has no standalone change-of-use permit or freestanding C.O. product. A Certificate of Occupancy is issued as the final inspection sign-off within an underlying building permit. A genuine change of occupancy classification without construction is reviewed under the City's adopted 2024 International Existing Building Code (IEBC) Chapter 10; contact the Building Inspection Division at (307) 235-8254 to confirm whether a specific change triggers a permit.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-22.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casper building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.