EV Charger / EVSE Permit in Casper, Wyoming
Casper has no standalone EV-charger/EVSE permit type or fee line item. Installing electric vehicle charging equipment (e.g., a dedicated 240V Level 2 circuit or panel upgrade) is electrical work, and per this file's own electrical-permit entry, Casper's Building Inspection Division holds delegated local electrical authority and performs its own electrical plan review and inspections under the 2023 NFPA 70 NEC -- not the Wyoming State Fire Marshal's statewide electrical program. An EV charger installation is billed under the same 'Combined Building, Electrical, Plumbing and Mechanical Permit Fee Schedule' (City of Casper Permit Fee Schedule, eff. February 2, 2026) used for all electrical work, since no EV-charger-specific line item exists in the City's fee schedule as of this review.
Verified 2026-07-20 · Source
When you need this permit
- Electrical Permit Application submitted to the Building Inspection Division (via CSS Portal or in person) for the EV charger circuit
- Governed by the 2023 NFPA 70 National Electrical Code, same as all electrical work in Casper
- Fee based on the value of the work per the City's combined valuation-based fee schedule, same as any other electrical permit -- no distinct EV-charger tier
- Casper's Building Inspection Division performs its own electrical plan review and inspections (Rough Electrical, Service, Final Electrical) rather than routing to a state electrical authority
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Performed after electrical components are roughed in, before trim out, if applicable to the installation
- 2
Final Electrical
Performed when the charger installation is 100% complete and all connections/protections are verified per the 2023 NFPA 70 NEC
See the full Casper inspection guide — scheduling & re-inspection fees →
Tips
- Casper issues its own electrical permits and runs its own electrical inspections -- unlike some peer states in this corpus where electrical work routes to a state board, an EV charger circuit here goes through the City's Building Inspection Division directly.
- There is no separate EV-charger fee category in Casper -- an EV charger circuit is billed under the same combined valuation-based Building/Electrical/Plumbing/Mechanical fee schedule used for any electrical permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Casper building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Casper
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Wyoming →
Look up this fee in a different city →
Related guides
Now live
Build your Casper project checklist
Describe your project once and get every permit, document, and fee it triggers in Casper — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →