EV Charger / EVSE Permit in Lander, Wyoming

Electric vehicle charging equipment (EVSE) installation in Lander is processed through the City's standard Application for Building Permit under the Trade/Small Project Alteration Permit category, the same category and flat-fee mechanism used for a standalone solar retrofit's electrical scope. Resolution 1359 (Fee Schedule 2025-26) has no dedicated EV-charger/EVSE line item, so an EVSE circuit is billed under the same 'Electrical Alteration' ($30) or 'Electrical Service Inspection' ($75) flat fees used for other electrical trade work, depending on whether the installation requires new/upgraded service equipment.

Verified 2026-07-20 · Source

When you need this permit

  • Completed City of Lander Application for Building Permit, checking the ELECTRICAL box, indicating wiring modifications, service upgrade, panel modification, meter modification/relocation, and electrical service size (amps) as applicable to the EVSE circuit
  • Design/installation work must comply with the City's locally-adopted 2023 NEC (LMC Title 3, Ord. 2025-16), including NEC Article 625 (Electric Vehicle Power Transfer System)
  • No dedicated EVSE fee line exists on Resolution 1359 — a standalone EVSE circuit with no new electrical service is billed at the flat 'Electrical Alteration' rate; a $75 'Electrical Service Inspection' fee applies instead if the project includes new or upgraded service equipment (e.g., a panel upgrade to support the charger's amperage draw)
  • If the EVSE installation is bundled into new construction, it is instead priced per the valuation-based Attachment A table (not independently published online — call the Building Inspector for a quote)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Alteration (standalone EVSE circuit, no new service)Resolution 1359, Fee Schedule 2025-26, 'BUILDING DEPARTMENT' section — no dedicated EV-charger/EVSE line item is published; billed under the general electrical trade fee, the same mechanism used for a standalone PV retrofit's electrical scope on this file's Solar PV Permit entry
$30
Electrical Service Inspection (if new/upgraded service equipment is part of the EVSE installation)Resolution 1359, Fee Schedule 2025-26, 'BUILDING DEPARTMENT' section
$75
New Construction and Remodel/Alterations (if EVSE is bundled into new construction)Resolution 1359, 'BUILDING DEPARTMENT' section; Attachment A itself was not found published as a standalone document — call the Building Inspector for an exact quote
Per Valuation Table Attachment A

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Lander?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring, box placement, and grounding verified before walls are closed, where applicable, consistent with the City's mandatory-inspection list

  2. 2

    Final Inspection

    EVSE circuit, breaker/disconnect, and NEC Article 625 compliance verified; system energized

See the full Lander inspection guide — scheduling & re-inspection fees →

Tips

  • A simple EVSE retrofit with no new electrical service is billed at the flat $30 Electrical Alteration fee — the same rate as any other minor electrical alteration in Lander, including a standalone solar retrofit's electrical scope.
  • A $75 Electrical Service Inspection fee applies instead if the EVSE installation requires new or upgraded service equipment, which is common for a Level 2 charger circuit on an older home's electrical panel.
  • Because Attachment A (the valuation table for new-construction-bundled work) is not published online, call the Building Inspector (307-330-3114) for an exact cost if the EVSE installation is part of a larger new-construction project.

Frequently asked questions

Lander requires an ev charger / evse permit for: Completed City of Lander Application for Building Permit, checking the ELECTRICAL box, indicating wiring modifications, service upgrade, panel modification, meter modification/relocation, and electrical service size (amps) as applicable to the EVSE circuit; Design/installation work must comply with the City's locally-adopted 2023 NEC (LMC Title 3, Ord. 2025-16), including NEC Article 625 (Electric Vehicle Power Transfer System); No dedicated EVSE fee line exists on Resolution 1359 — a standalone EVSE circuit with no new electrical service is billed at the flat 'Electrical Alteration' rate; a $75 'Electrical Service Inspection' fee applies instead if the project includes new or upgraded service equipment (e.g., a panel upgrade to support the charger's amperage draw); If the EVSE installation is bundled into new construction, it is instead priced per the valuation-based Attachment A table (not independently published online — call the Building Inspector for a quote). If your project isn't listed, confirm with City of Lander Building Department at 307-330-3114 or 307-332-2870 x115 (Building Inspector Dustin Springston); 307-332-2870 (City Hall main line) before starting work.

A standalone EVSE circuit with no new electrical service is a flat $30 Electrical Alteration fee, per City of Lander Resolution 1359 (Fee Schedule 2025-26). If the installation requires new or upgraded service equipment, a $75 Electrical Service Inspection fee applies instead. No dedicated EV-charger/EVSE line item is published — these are the same general electrical trade fees used for other alteration work.

Lander does not publish a plan-review timeline for this permit. Contact City of Lander Building Department at 307-330-3114 or 307-332-2870 x115 (Building Inspector Dustin Springston); 307-332-2870 (City Hall main line) for current turnaround.

You'll need: City of Lander Application for Building Permit. See the required-documents checklist on this page for details on each.

Lander requires 2 inspection(s) for an ev charger / evse permit, in order: Rough Electrical, Final Inspection. Schedule each through City of Lander Building Department (307-330-3114 or 307-332-2870 x115 (Building Inspector Dustin Springston); 307-332-2870 (City Hall main line)).

Apply through City of Lander Building Department at 240 Lincoln Street, Lander, WY 82520. Phone: 307-330-3114 or 307-332-2870 x115 (Building Inspector Dustin Springston); 307-332-2870 (City Hall main line), email: dspringston@landerwyoming.org (Building Inspector Dustin Springston). Office hours: Not separately published for the Building Department on the City of Lander website as of 2026-07-18 (checked the Building Inspector contact page and the citywide Contact Us page — neither lists specific hours); call 307-332-2870 or 307-330-3114 to confirm.. Official information: https://www.landerwy.gov/building/page/building-permits.

Lander, Wyoming has adopted: 2024 International Building Code (IBC), including Appendices A, B, G, H, I, J, K and N — adopted as Lander Municipal Code (LMC) Chapter 3.08.10 by Ordinance 2025-16, effective 12/13/2025.; 2024 International Existing Building Code (IEBC) — LMC Chapter 3.09.10, Ordinance 2025-16 (12/13/2025).; 2024 International Residential Code (IRC), including Appendices AA, BA, BB, BC, BE, BJ, BO, CA, and CD — LMC Chapter 3.10.10, Ordinance 2025-16 (12/13/2025).; 2024 International Plumbing Code (IPC), including Appendices B, C, D, and E — LMC Chapter 3.12.10, Ordinance 2025-16 (12/13/2025).; 2024 International Fire Code (IFC) — LMC Chapter 3.14.10, Ordinance 2025-16 (12/13/2025).; 2024 International Mechanical Code (IMC), including Appendix A — LMC Chapter 3.16.10, Ordinance 2025-16 (12/13/2025).; National Electrical Code (NEC), 2023 Edition, as published by the National Fire Protection Association — LMC Chapter 3.20.10, Ordinance 2025-16 (12/13/2025); this is the only Title 3 code NOT on the 2024 ICC cycle.; 2024 International Fuel Gas Code (IFGC), including Appendices A, B, and C — LMC Chapter 3.22.10, Ordinance 2025-16 (12/13/2025).; 2024 International Property Maintenance Code (IPMC) — LMC Chapter 3.24.10, Ordinance 2025-16 (12/13/2025).; Flood Damage Prevention regulations — LMC Chapter 3.32, Ordinance 2025-16 (12/13/2025).; Notably, LMC 3.08.20(B) REPEALS/does not enforce Section 101.4.6 of the IBC ('Energy'), meaning the City of Lander does not separately enforce the International Energy Conservation Code (IECC) as part of its Title 3 building-code adoption — confirmed by reading the full Title 3 code text live on lander.municipalcodeonline.com as of 2026-07-18; no IECC chapter appears anywhere in Title 3's table of contents (3.04 through 3.32).. Local amendments apply — see the Lander overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lander building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.