Jackson building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Jackson, Wyoming.
Verified 2026-07-01 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 150 E Pearl Avenue, Jackson, WY 83001 (P.O. Box 1687, Jackson, WY 83001)
- Phone
- 307-733-0440, ext. 1352 (Building Inspection Hotline: 307-733-0520, ext. 1351)
- Office hours
- The Town does not do over-the-counter permitting; all submittals are electronic. Inspections conducted virtually Tuesdays/Thursdays and in-person Mondays/Wednesdays/Fridays.
- Website
- Official site
Published scheduling rules
- Inspections are scheduled by calling the Inspection Hotline (307-733-0520 ext. 1351), NOT through the SmartGov portal, even if the permit itself was obtained there. (One and Two Family Building Permit)
- Electrical permit required before EV charger/EVSE installation begins; no inspection can be scheduled without a permit (Electric Vehicle (EV) Charger / EVSE Permit)
Inspection sequence
Applies to: Commercial Building Permit / Tenant Improvement
- 1
Rough Electrical
- 2
Combination Rough (Mechanical/Plumbing/Gas/Framing)
- 3
Fire Inspection
Fire alarm, sprinkler, and suppression systems reviewed by Jackson Hole Fire/EMS
- 4
Final / Certificate of Occupancy
Applies to: Electrical Permit
- 1
Temporary Service
- 2
Rough Wiring
Includes a Low Voltage Rough Wiring inspection type where applicable
- 3
Service
- 4
Final
Includes a Low Voltage Final inspection type where applicable
Applies to: One and Two Family Building Permit
- 1
Foundation / Footings
Before concrete pour — footings below the 34-inch frost line or as specified by the soils engineer of record
- 2
Rough Electrical
Conducted by Jackson Hole Fire/EMS Electrical Division; required combination Rough Gas/Rough Plumbing/Rough Mechanical/Framing inspections can only be scheduled after a passed Rough Electrical inspection
- 3
Combination Rough (Gas/Plumbing/Mechanical/Framing)
Scheduled together after Rough Electrical passes
- 4
Final / Certificate of Occupancy
All departments (Building, Engineering, Fire/Electrical, Planning) must sign off on the Permit/Inspection Card before a Certificate of Occupancy or Completion is issued
Applies to: Accessory Residential Unit (ARU) Permit
- 1
Foundation
- 2
Rough Electrical, then Combination Rough (Gas/Plumbing/Mechanical/Framing)
- 3
Final
Applies to: Residential Addition / Remodel Permit
- 1
Rough Electrical
Required before combination rough inspections
- 2
Combination Rough (Gas/Plumbing/Mechanical/Framing)
- 3
Final
Applies to: Solar PV Permit
- 1
Rough Electrical
- 2
Final — Structural/Racking (building permit)
- 3
Final — Electrical
Applies to: Demolition Permit
- 1
Pre-Demolition Utility Verification
Confirm gas, electric, water, sewer disconnects arranged
- 2
Final
Site cleared, backfilled to grade, debris removed
Applies to: Electric Vehicle (EV) Charger / EVSE Permit
- 1
Rough Wiring
Circuit, conduit, and disconnect placement before concealment, if applicable
- 2
Final
Charger mounted, circuit labeled, and installation verified per the adopted National Electrical Code (Article 625, Electric Vehicle Charging System)
Applies to: Fire Sprinkler / Fire Alarm Permit
- 1
Rough — System Installation
Sprinkler piping, alarm wiring, and device rough-in inspected before concealment
- 2
Final — Acceptance Test
Hydrostatic test (sprinkler systems) or functional alarm test witnessed by Jackson Hole Fire/EMS before the system is placed in service
Applies to: Mechanical / Fuel Gas Permit
- 1
Rough Mechanical
Combination inspection with Rough Gas/Plumbing/Framing, scheduled only after a passed Rough Electrical inspection
- 2
Final
Applies to: Plumbing Permit
- 1
Rough Plumbing
Combination inspection with Rough Gas/Mechanical/Framing, scheduled only after a passed Rough Electrical inspection
- 2
Final
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Jackson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Jackson building permits
Get alerts for Jackson
We'll email you when Jackson's fees, documents, or codes change — not often.