Inspection sequence, scheduling, and re-inspection fees for building permits in Jackson, Wyoming.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
150 E Pearl Avenue, Jackson, WY 83001 (P.O. Box 1687, Jackson, WY 83001)
Phone
307-733-0440, ext. 1352 (Building Inspection Hotline: 307-733-0520, ext. 1351)
Office hours
The Town does not do over-the-counter permitting; all submittals are electronic. Inspections conducted virtually Tuesdays/Thursdays and in-person Mondays/Wednesdays/Fridays.

Published scheduling rules

  • Inspections are scheduled by calling the Inspection Hotline (307-733-0520 ext. 1351), NOT through the SmartGov portal, even if the permit itself was obtained there. (One and Two Family Building Permit)
  • Electrical permit required before EV charger/EVSE installation begins; no inspection can be scheduled without a permit (Electric Vehicle (EV) Charger / EVSE Permit)

Inspection sequence

Applies to: Commercial Building Permit / Tenant Improvement

  1. 1

    Rough Electrical

  2. 2

    Combination Rough (Mechanical/Plumbing/Gas/Framing)

  3. 3

    Fire Inspection

    Fire alarm, sprinkler, and suppression systems reviewed by Jackson Hole Fire/EMS

  4. 4

    Final / Certificate of Occupancy

Applies to: Electrical Permit

  1. 1

    Temporary Service

  2. 2

    Rough Wiring

    Includes a Low Voltage Rough Wiring inspection type where applicable

  3. 3

    Service

  4. 4

    Final

    Includes a Low Voltage Final inspection type where applicable

Applies to: One and Two Family Building Permit

  1. 1

    Foundation / Footings

    Before concrete pour — footings below the 34-inch frost line or as specified by the soils engineer of record

  2. 2

    Rough Electrical

    Conducted by Jackson Hole Fire/EMS Electrical Division; required combination Rough Gas/Rough Plumbing/Rough Mechanical/Framing inspections can only be scheduled after a passed Rough Electrical inspection

  3. 3

    Combination Rough (Gas/Plumbing/Mechanical/Framing)

    Scheduled together after Rough Electrical passes

  4. 4

    Final / Certificate of Occupancy

    All departments (Building, Engineering, Fire/Electrical, Planning) must sign off on the Permit/Inspection Card before a Certificate of Occupancy or Completion is issued

Applies to: Accessory Residential Unit (ARU) Permit

  1. 1

    Foundation

  2. 2

    Rough Electrical, then Combination Rough (Gas/Plumbing/Mechanical/Framing)

  3. 3

    Final

Applies to: Residential Addition / Remodel Permit

  1. 1

    Rough Electrical

    Required before combination rough inspections

  2. 2

    Combination Rough (Gas/Plumbing/Mechanical/Framing)

  3. 3

    Final

Applies to: Solar PV Permit

  1. 1

    Rough Electrical

  2. 2

    Final — Structural/Racking (building permit)

  3. 3

    Final — Electrical

Applies to: Demolition Permit

  1. 1

    Pre-Demolition Utility Verification

    Confirm gas, electric, water, sewer disconnects arranged

  2. 2

    Final

    Site cleared, backfilled to grade, debris removed

Applies to: Electric Vehicle (EV) Charger / EVSE Permit

  1. 1

    Rough Wiring

    Circuit, conduit, and disconnect placement before concealment, if applicable

  2. 2

    Final

    Charger mounted, circuit labeled, and installation verified per the adopted National Electrical Code (Article 625, Electric Vehicle Charging System)

Applies to: Fire Sprinkler / Fire Alarm Permit

  1. 1

    Rough — System Installation

    Sprinkler piping, alarm wiring, and device rough-in inspected before concealment

  2. 2

    Final — Acceptance Test

    Hydrostatic test (sprinkler systems) or functional alarm test witnessed by Jackson Hole Fire/EMS before the system is placed in service

Applies to: Mechanical / Fuel Gas Permit

  1. 1

    Rough Mechanical

    Combination inspection with Rough Gas/Plumbing/Framing, scheduled only after a passed Rough Electrical inspection

  2. 2

    Final

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Combination inspection with Rough Gas/Mechanical/Framing, scheduled only after a passed Rough Electrical inspection

  2. 2

    Final

Re-inspection fees

One and Two Family Building PermitRe-inspection / Outside-normal-hours / Plan revision review · Resolution 25-18 Appendix A, 'Other Inspections' line items
$85.00/hr to $113.00/hr depending on type
Plumbing PermitRe-inspection fee / Inspections outside normal business hours / Additional plan review · Resolution 25-18 Appendix A
$85.00/hr to $113.00/hr
Mechanical / Fuel Gas PermitRe-inspection fee / Additional plan review · Resolution 25-18 Appendix A
$85.00/hr to $113.00/hr
Fire Sprinkler / Fire Alarm PermitRe-inspection of New Construction · Resolution 25-18 Appendix A, Fire Permits (IFC and IWUIC) section
$102.00/hr

Jackson building permits

Get alerts for Jackson

We'll email you when Jackson's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.