Residential Building Permit (New Construction) in Rock Springs, Wyoming

Required for new single-family dwellings and other one- and two-family residential construction within Rock Springs city limits. Governed by the 2024 IRC as adopted (with local amendments) by Rock Springs Municipal Code § 150.04. Single-family new construction is charged a flat permit fee rather than the valuation table.

Verified 2026-07-01 · Source

When you need this permit

  • Any person, firm or corporation desiring to construct, enlarge, alter, repair, move, convert, or demolish any building or structure must obtain a building permit from the Building Official before work begins (§ 150.02(A)(1))
  • Contractor/subcontractor/builder must have the permit issued and exhibited before commencing work (§ 150.02(A)(2))
  • Design must account for adopted design criteria: 30 psf ground snow load, 115 mph ultimate wind speed (Exposure C), 42-inch minimum frost depth
  • Mine Subsidence classification must be checked with City Engineering (307-352-1540); classified-area foundations must be designed to mitigate subsidence effects with a design engineer's statement on the plans
  • A dimensioned site plan showing utilities, setbacks, streets, alleys, and parking is required
  • Sewer connection fee is due at permit issuance if the property has not previously been assessed for the sanitary sewer system and a prior connection fee has not been paid (§ 150.02(A)(3))
  • General contractor must be a City of Rock Springs registered contractor ($125 registration fee + insurance certificate on file) Contractor
  • Permit becomes null and void if work is not commenced within 180 days, or is suspended/abandoned for 180 days after commencement

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Single-family home (flat fee)Rock Springs Municipal Code § 150.08(B)(2): 'Single-family homes: building permit fee, $1,100, no plan review fee.'
$1,100.00 flat — no plan review fee charged
Building Permit Fee — general valuation table (used for non-single-family new residential construction, e.g. duplexes)Rock Springs Municipal Code § 150.08(B); this valuation table applies to all adopted codes (mechanical, plumbing, electrical included) unless a specific override applies
$1 to $500: $32.45; $501–$2,000: $32.45 for the first $500 plus $4.20 per additional $100 or fraction; $2,001–$25,000: $95.31 for the first $2,000 plus $19.25 per additional $1,000; $25,001–$50,000: $538.72 for the first $25,000 plus $13.88 per additional $1,000; $50,001–$100,000: $885.22 for the first $50,000 plus $9.62 per additional $1,000; $100,001–$500,000: $1,366.47 for the first $100,000 plus $7.70 per additional $1,000; $500,001–$1,000,000: $4,446.47 for the first $500,000 plus $6.60 per additional $1,000; $1,000,001 and up: $7,712.10 for the first $1,000,000 plus $5.01 per additional $1,000
Plan Review Fee§ 150.08(B)(1); waived for single-family homes and residential alterations/additions per the specific overrides
65% of the building permit fee
Reinspection Fee§ 150.08(B), Other Inspections and Fees table, assessed under IBC Section 305.8
$100 per hour (or total hourly cost to the city, whichever is greater)
Inspections outside normal business hours
$59 per hour

Review timeline

Plan reviewTypical estimate — confirm current times with the Rock Springs building department
~10–30 business days

How long did your Residential Building Permit (New Construction) permit actually take in Rock Springs?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footings

    Before concrete pour — footings must extend below the 42-inch minimum frost depth

  2. 2

    Framing

    After framing complete, before insulation or wall cover

  3. 3

    MEP Rough-In

    Mechanical, electrical, and plumbing rough-in before walls closed; electrical rough-in inspected by the City Electrical Inspector per § 150.33

  4. 4

    Final

    All work complete, ready for occupancy

See the full Rock Springs inspection guide — scheduling & re-inspection fees →

Tips

  • Single-family new construction is a flat $1,100 permit fee with NO separate plan review fee — this is simpler and often cheaper than the valuation-based table used for larger/non-single-family projects.
  • Rock Springs' Mine Subsidence Risk Map matters: contact City Engineering (307-352-1540) early to check whether your parcel falls in a classified area, since it changes the required foundation design and adds a design engineer's statement requirement.
  • General contractors and subcontractors must be registered with the City ($125 fee + insurance certificate) before performing any work — this is separate from any state trade license.
  • The permit becomes null and void after 180 days of no work or a 180-day suspension/abandonment.

Frequently asked questions

Rock Springs requires a residential building permit (new construction) for: Any person, firm or corporation desiring to construct, enlarge, alter, repair, move, convert, or demolish any building or structure must obtain a building permit from the Building Official before work begins (§ 150.02(A)(1)); Contractor/subcontractor/builder must have the permit issued and exhibited before commencing work (§ 150.02(A)(2)); Design must account for adopted design criteria: 30 psf ground snow load, 115 mph ultimate wind speed (Exposure C), 42-inch minimum frost depth; Mine Subsidence classification must be checked with City Engineering (307-352-1540); classified-area foundations must be designed to mitigate subsidence effects with a design engineer's statement on the plans; A dimensioned site plan showing utilities, setbacks, streets, alleys, and parking is required; Sewer connection fee is due at permit issuance if the property has not previously been assessed for the sanitary sewer system and a prior connection fee has not been paid (§ 150.02(A)(3)); General contractor must be a City of Rock Springs registered contractor ($125 registration fee + insurance certificate on file); Permit becomes null and void if work is not commenced within 180 days, or is suspended/abandoned for 180 days after commencement. If your project isn't listed, confirm with City of Rock Springs Public Services Department — Building Inspections & Permits (Chief Building Inspector) at (307) 352-1540 before starting work.

$1,100.00 flat fee, with no separate plan review fee, per Rock Springs Municipal Code § 150.08(B)(2). Larger or non-single-family residential projects are charged under the general valuation-based fee table instead.

Plan review for a residential building permit (new construction) in Rock Springs typically runs 10–30 business days. This is an estimate, not a published figure — confirm current review times with City of Rock Springs Public Services Department — Building Inspections & Permits (Chief Building Inspector) at (307) 352-1540.

You'll need: Building Permit Application; Construction Drawings; Site Plan. Depending on your project, Rock Springs may also ask for: Detail Sheet — Concrete (Foundations/Footings/Slabs). See the required-documents checklist on this page for details on each.

Rock Springs requires 4 inspection(s) for a residential building permit (new construction), in order: Foundation / Footings, Framing, MEP Rough-In, Final. Schedule each through City of Rock Springs Public Services Department — Building Inspections & Permits (Chief Building Inspector) ((307) 352-1540).

Apply through City of Rock Springs Public Services Department — Building Inspections & Permits (Chief Building Inspector) at 212 D Street, Rock Springs, WY 82901. Phone: (307) 352-1540, email: webmaster@rswy.net. Office hours: Mon–Fri, 8:00 a.m. to 5:00 p.m., closed 12:30–1:30 p.m. for lunch. Official information: https://www.rswy.net/departments/public_services/building_inspections_permits.php.

Rock Springs, Wyoming has adopted: 2024 International Building Code (IBC) — with local amendments; adopted per Rock Springs Municipal Code § 150.04, including Appendix E, Appendix I and Appendix J, excluding Chapter 27; 2024 International Residential Code (IRC) — with local amendments per § 150.04(D); including Appendix BF, Appendix B, Appendix C and Appendix CA; excluding R-309, P2904, and several Section R-403.3 subsections/tables/figures; 2024 International Existing Building Code (IEBC) — adopted per § 150.04; 2024 International Mechanical Code (IMC) — with local amendment per § 150.04(C); 2024 International Plumbing Code (IPC) — with local amendment per § 150.04(C); including Appendix D (Degree Day/Design Temperatures), Appendix E (Sizing of Water Pipe Systems) and Appendix C (Structural Safety); 2024 International Fuel Gas Code (IFGC) — including Appendix A, Appendix B and Appendix C; 2024 International Fire Code (IFC) — per City of Rock Springs Building Ordinances page; National Electrical Code, 2023 edition (NFPA) — adopted per § 150.04; enforced locally by the City Electrical Inspector under Rock Springs Municipal Code §§ 150.30–150.36 (city electrical code), NOT the Wyoming State Fire Marshal default program. Local amendments apply — see the Rock Springs overview page for the full list.

For new structures or additions of 5,000 sq ft or larger, yes — architectural plans must be designed and stamped by a Wyoming registered architect, and structural, mechanical/plumbing, and electrical plans must be sealed by the respective Wyoming-licensed engineers, per the City's Nonresidential Building Permit Application checklist.

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Rock Springs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.