EV Charger / EVSE Permit in Unincorporated Campbell County, Wyoming

Campbell County has no dedicated EV-charger/EVSE permit type or fee. Installing a Level 2 or DC fast EV charger requires a dedicated circuit or service equipment, which is administered under the county's general Electrical Permit (NFPA 70/NEC 2026 Edition, Chapter 4 Section 10) — the same permit used for any other electrical work, issued at no charge per Chapter 4 Section 1.8.E.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical Permit required for the EV charger's dedicated circuit/service work — required even where the associated Building Permit is exempt (e.g., rural/unplatted dwellings)
  • Service disconnecting means must be installed at a readily accessible location within 50 feet, in plain view from outside the building (Chapter 4 § 10.A.1, amending NEC 230.70(A)(1)) if the install involves new/upgraded service equipment
  • Installation must comply with NFPA 70 (National Electrical Code), 2026 Edition, per Chapter 4 Section 10
  • County Building Division inspectors perform the electrical inspection locally (Chapter 4 § 10.B.5(a))

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit (EV charger circuit — no distinct EV-charger fee line exists)Chapter 4 Rules Regulating Construction, Section 1.8.E 'All Other Permits: No fees.' This blanket no-fee provision explicitly covers all Electrical Permits (see the electrical-permit entry in this file); Campbell County has never published a distinct EV charger/EVSE line item because it charges no fee for residential electrical permits generally. Re-checked the current Chapter 4 PDF (ccgov.net/DocumentCenter/View/211) on 2026-07-20 specifically for 'EV', 'electric vehicle', or 'EVSE' language — none exists; the general no-fee electrical permit provision is the only applicable mechanism.
No fee

Review timeline

Plan reviewTypical estimate — confirm current times with the Unincorporated Campbell County building department
~1–10 business days

How long did your EV Charger / EVSE Permit permit actually take in Unincorporated Campbell County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Wiring/conduit for the EV charger circuit installed before walls closed, if applicable

  2. 2

    Final

    Charger circuit/equipment installed, breaker sized correctly, system energized

See the full Unincorporated Campbell County inspection guide — scheduling & re-inspection fees →

Tips

  • Campbell County has no EV-charger-specific permit or fee — apply for a standard Electrical Permit (no charge) using the county's Building Permit & Zoning Certificate Application.
  • An Electrical Permit for the EV charger circuit is required even for rural (unplatted) dwellings that are exempt from a Building Permit under Chapter 4 § 1.4.A.3.
  • Unlike most Wyoming jurisdictions that default to the state's Chief Electrical Inspector program, Campbell County runs its own electrical inspection program at no charge — confirm this distinction before assuming the WSFM's statewide fee schedule applies.

Frequently asked questions

Unincorporated Campbell County requires an ev charger / evse permit for: Electrical Permit required for the EV charger's dedicated circuit/service work — required even where the associated Building Permit is exempt (e.g., rural/unplatted dwellings); Service disconnecting means must be installed at a readily accessible location within 50 feet, in plain view from outside the building (Chapter 4 § 10.A.1, amending NEC 230.70(A)(1)) if the install involves new/upgraded service equipment; Installation must comply with NFPA 70 (National Electrical Code), 2026 Edition, per Chapter 4 Section 10; County Building Division inspectors perform the electrical inspection locally (Chapter 4 § 10.B.5(a)). If your project isn't listed, confirm with Campbell County Department of Public Works — Building, Planning & Zoning Division at (307) 682-1970 before starting work.

In Unincorporated Campbell County, the published Electrical Permit (EV charger circuit — no distinct EV-charger fee line exists) is: No fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Plan review for an ev charger / evse permit in Unincorporated Campbell County typically runs 1–10 business days. This is an estimate, not a published figure — confirm current review times with Campbell County Department of Public Works — Building, Planning & Zoning Division at (307) 682-1970.

You'll need: Building Permit & Zoning Certificate Application. See the required-documents checklist on this page for details on each.

Unincorporated Campbell County requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through Campbell County Department of Public Works — Building, Planning & Zoning Division ((307) 682-1970).

Apply through Campbell County Department of Public Works — Building, Planning & Zoning Division at 500 S. Gillette Ave., Suite 1500, Gillette, WY 82716. Phone: (307) 682-1970, email: septic@campbellcountywy.gov (Small Wastewater System applications); planning@campbellcountywy.gov (Planning & Zoning); general Public Works (307) 685-8061. Office hours: Mon–Fri, 8:00 a.m.–5:00 p.m.. Official information: https://www.ccgov.net/286/Building-Division.

Unincorporated Campbell County, Wyoming has adopted: 2024 International Building Code (IBC) — including Appendices C and J, adopted by Campbell County Chapter 4 Rules Regulating Construction, Section 3 (Amended June 2026); 2024 International Residential Code (IRC) — including Appendices A, B, C and E, adopted Chapter 4 Section 4 (Amended June 2026); 2024 International Mechanical Code (IMC) — including Appendix A, adopted Chapter 4 Section 5; 2024 International Plumbing Code (IPC) — including Appendices A and B, adopted Chapter 4 Section 6 — NOTE: Campbell County uses the IPC, not the Uniform Plumbing Code; 2024 International Fuel Gas Code (IFGC) — all appendices, adopted Chapter 4 Section 7; 2024 International Fire Code (IFC), adopted Chapter 4 Section 8 (enforced by Campbell County Fire Department for Fire Code permits); 2024 International Existing Building Code (IEBC), adopted Chapter 4 Section 9; National Electrical Code (NFPA 70), 2026 Edition — including Informative Annex H, adopted Chapter 4 Section 10; Liquefied Petroleum Gas Code (NFPA 58), 2020 Edition, adopted Chapter 4 Section 11; Wyoming DEQ Water Quality Rules and Regulations Chapter 25 (Septic Tanks, Soil Absorption Systems, and Other Small Wastewater Systems) — adopted as Chapter 4 Appendix 1, administered by Campbell County under delegated authority from Wyoming DEQ (W.S. 35-11-304). Local amendments apply — see the Unincorporated Campbell County overview page for the full list.

No. There is no EV charger/EVSE permit type or fee. Installing an EV charger circuit is handled under the county's general Electrical Permit (NEC 2026 Edition), issued at no charge per Chapter 4 Section 1.8.E ('All Other Permits: No fees').

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Campbell County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.