EV Charger / EVSE Permit (Electrical Permit) — Douglas, Arizona · Requirements sheet
Verified 2026-07-20 · Source: https://douglasaz.gov/DocumentCenter/View/5479/City-of-Douglas-Development-Services-FAQ-Bilingual
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit (Electrical Permit) in Douglas, Arizona
Installation of an electric vehicle charging station in Douglas, Arizona is electrical work, submitted on the same Residential Building Permit Application (Mechanical-Electrical/RME permit type) used for this file's general electrical-permit entry. The City of Douglas Development Services fee schedule (FAQ Bilingual, DocumentCenter View 5479, directly fetched and reviewed page-by-page this session) lists flat trade-permit fees by category (Plumbing, Electrical, Mechanical, Solar/PV Systems & Wind Turbines, Re-Roof, Paving, Demolition, etc.) but has NO distinct 'EV charger,' 'electric vehicle,' or 'EVSE' line item — an EV charger circuit falls under the general flat 'Electrical' fee line, the same one used for any other electrical work (panel upgrades, wiring, outlets).
Verified 2026-07-20 · Source
When you need this permit
- Submitted via the Residential Building Permit Application, Mechanical-Electrical (RME) permit type, checking the electrical scope box — same form used for this file's general electrical-permit entry
- Governed by the City's adopted 2005 National Electrical Code (NEC/NEL)
- Confirmed directly against the City of Douglas Development Services FAQ (Bilingual) fee table: the 'Electrical' line item is a flat fee by Residential/Commercial category with no distinct EV-charger/EVSE sub-line
- Application must indicate the specific electrical scope (e.g., new circuit, panel upgrade amperage) in the Electrical section, the same as any other electrical permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed (if applicable)
- 2
Final
Charger circuit/unit installed, panel labeled, protections verified per 2005 NEC
See the full Douglas inspection guide — scheduling & re-inspection fees →
Tips
- There is no distinct 'EV charger permit' in Douglas — apply through the Residential Building Permit Application's Mechanical-Electrical (RME) permit type, the same as any other electrical work, using the fee table's flat 'Electrical' line.
- Douglas's fee schedule lists Solar/PV Systems & Wind Turbines as its own $50.00 flat line separate from the general Electrical line — but EV chargers are not called out separately the way solar is, so they remain under the general Electrical fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Douglas building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Douglas
EV Charger / EVSE Permit (Electrical Permit) in other cities
Compare ev charger / evse permit (electrical permit) fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Douglas project checklist
Describe your project once and get every permit, document, and fee it triggers in Douglas — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →