Demolition Permit — Town of Payson, Arizona · Requirements sheet
Verified 2026-08-16 · Source: https://www.paysonaz.gov/departments/community-development/building-division
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Town of Payson, Arizona
Required for demolition of any structure in Payson. Fee is a flat charge valid for a limited window from issuance.
Verified 2026-08-16 · Source
When you need this permit
- Building permit required before demolishing a structure within Town of Payson limits
- Permit is good for only 30 days from the date issued
- General demolition requirements apply per Payson Code of Ordinances § 154-09-003 (site plan, declared use, and compliance documentation)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
$50.00. Town of Payson Fees and Charges Schedule FY2026-2027 (Resolution No. Show full citationHide
$50.00. Town of Payson Fees and Charges Schedule FY2026-2027 (Resolution No. 2026-020, effective July 1, 2026), Exhibit B, Building Division, 'Other Permit Fees', printed p.9. The FY2026-2027 line reads simply 'Demolition Permit... $50.00' with no validity period stated; the FY2021-2022 schedule's version of the line read 'Demolition Permit... $50.00, good for only 30 days from the date issued,' and no current Town source restates that 30-day limit. Confirm the permit's validity period with the Building Division (928-474-5242) before relying on any window.Review timeline
Inspection process
- 1
Final
Verifies site condition and completion of demolition within the 30-day permit validity window
See the full Town of Payson inspection guide — scheduling & re-inspection fees →
Tips
- The Demolition Permit is a flat $50.00 fee, unchanged from the FY2021-2022 schedule through the current FY2026-2027 schedule (Resolution No. 2026-020, effective July 1, 2026). A 30-days-from-issuance validity qualifier appeared on the FY2021-2022 schedule line but is NOT printed on the FY2026-2027 line, so it is not asserted here. Confirm the current validity period with the Building Division (928-474-5242).
- The Town's general 10-working-day published review timeframe (Building Division FAQs) is used here as the Town does not publish a separately shorter timeframe specific to demolition.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-16.
Fee schedules
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Town of Payson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Town of Payson's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Town of Payson yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Town of Payson lands. Privacy.
Other permits in Town of Payson
Demolition Permit in other cities
Compare demolition permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Town of Payson project checklist
Describe your project once and get every permit, document, and fee it triggers in Town of Payson — in one checklist. Free, for any city and any number of projects.
Get started →