Residential Building Permit (New Construction) in Town of Payson, Arizona

Required for new single-family and two-family dwelling construction in the Town of Payson. Reviewed against the 2018 IRC and Town of Payson amendments. Applications are submitted at the Community Development Department / Building Division using the Residential Building Permit Application form.

Verified 2026-07-06 · Source

When you need this permit

  • Building permit required for new single-family and two-family dwelling construction within Payson town limits; no permit is issued in a new subdivision until all subdivision improvements have been accepted by the Town Council
  • Plans must comply with the 2018 IRC and Town of Payson amendments, including the amended Climatic and Geographic Design Criteria (48 lbs/sq ft ground snow load; 115/89 mph wind, Exposure B; Seismic Design Category B; 18-inch frost depth)
  • A registered design professional is NOT required for single- or two-family residential construction (per Building Division FAQs)
  • Site plan required showing lot dimensions, existing/proposed structure locations, easements, drainage, and parking/access
  • Applicant must provide evidence of an approved means of sanitary disposal where applicable (Northern Gila County Sanitary District, Gila County Health Department, or ADEQ)
  • Owner-builders may self-perform under A.R.S. §32-1121A.5/A.6 exemptions; the Handyman Exemption (§32-1121A.14) does not apply to permitted work or projects with $1,000+ in materials/labor Owner-builder
  • Building permit fee is valuation-based (Chapter 150 Table 3-A); plan review fee is 65% of the calculated Building Permit fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Valuation Table 3-ATown of Payson Fees and Charges Schedule, Chapter 150 Table 3-A (most recently available full copy: FY2021-2022 schedule); reconfirm against the current Resolution 3438 (effective 7/1/2025) fee exhibit for exact present-day figures
$0 ($1-$1,000); $25 + $3/additional $100 to $2,000; $69 + $11/additional $1,000 to $40,000; $487 + $9/additional $1,000 to $100,000; $1,027 + $7/additional $1,000 to $500,000; $3,827 + $5/additional $1,000 to $1,000,000; $6,327 + $3/additional $1,000 to $5,000,000; $18,327 + $1/additional $1,000 above $5,000,000
Plan Review FeeTown of Payson Fees and Charges Schedule, Exhibit B, New Home & Commercial Fee Calculation step D
65% of the calculated Building Permit Fee
Investigation Fee (work commenced before permit issuance)Payson Code of Ordinances § 150.20 IRC amendment (4) / § 150.21 IBC amendment (5)
Equal to the permit fee that would have applied; minimum $70

Review timeline

Plan reviewTown of Payson’s published plan-review target
10–10 business days

How long did your Residential Building Permit (New Construction) permit actually take in Town of Payson?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Footing depth, width, and reinforcement inspected before concrete placement

  2. 2

    Framing

    Structural framing, connections, and egress per 2018 IRC and Town amendments

  3. 3

    Final

    Completed work verified against approved plans prior to Certificate of Occupancy

See the full Town of Payson inspection guide — scheduling & re-inspection fees →

Tips

  • Per the Town of Payson Building Division FAQs, a single-family residential or duplex project typically takes 10 working days to obtain a permit after plans are submitted for review — this timeframe is the Town's own published A.R.S. § 9-835 licensing-timeframe figure for this permit category.
  • A registered design professional is not required for single- or two-family residential work — only for commercial buildings 3,000+ sq ft, buildings with 20+ occupant load, or structural members spanning 20+ feet outside an engineered system.
  • Fire sprinklers are not mandatory for single-family homes under 4,800 sq ft of livable area — Payson struck the blanket sprinkler-installation requirement from IRC §313.2.1.

Frequently asked questions

No. Per the Building Division FAQs, single- or two-family residential construction (including additions/alterations) does not require a registered design professional. A registered professional is required only for commercial buildings of at least 3,000 sq ft, buildings with an occupant load of 20 or more, or a structural member spanning at least 20 feet that is not part of an engineered system.

In Town of Payson, the published Building Permit Fee — Valuation Table 3-A is: $0 ($1-$1,000); $25 + $3/additional $100 to $2,000; $69 + $11/additional $1,000 to $40,000; $487 + $9/additional $1,000 to $100,000; $1,027 + $7/additional $1,000 to $500,000; $3,827 + $5/additional $1,000 to $1,000,000; $6,327 + $3/additional $1,000 to $5,000,000; $18,327 + $1/additional $1,000 above $5,000,000. Additional published fees: Plan Review Fee — 65% of the calculated Building Permit Fee; Investigation Fee (work commenced before permit issuance) — Equal to the permit fee that would have applied; minimum $70. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Per the Town of Payson Building Division FAQs, a single-family residential or duplex project typically takes 10 working days to obtain a permit after plans have been submitted for review; commercial projects take longer (initial comments typically within 20 working days).

You'll need: Residential Building Permit Application; Residential Construction Checklist; Residential Grading and Drainage Plan Checklist; Site/Plot Plan. See the required-documents checklist on this page for details on each.

Town of Payson requires 3 inspection(s) for a residential building permit (new construction), in order: Footing/Foundation, Framing, Final. Schedule each through Town of Payson Community Development Department — Building Division (928-472-5030).

Apply through Town of Payson Community Development Department — Building Division at 303C N. Beeline Highway, Payson, AZ 85541. Phone: 928-472-5030, email: building@paysonaz.us. Office hours: Monday - Thursday, 7:00 a.m. - 5:30 p.m. (closed Fridays and Holidays); TDD Phone 928-472-6449. Building permit applications may be submitted at the Building Division counter; electronic/digital submittals are preferred for solar and other checklist-based permits.. Official information: https://www.paysonaz.gov/departments/community-development/building-division.

Town of Payson, Arizona has adopted: Arizona has NO statewide mandatory building code for general construction — code adoption is a per-jurisdiction (city/town/county) authority under state enabling statutes (A.R.S. Title 9 for municipalities). The Town of Payson independently adopts and administers its own construction codes through its Community Development Department / Building Division; it does NOT defer to Gila County for permitting within town limits. Gila County (which covers unincorporated areas around Payson) separately runs its own, older code cycle (2012 I-Codes / 2011 NEC per Gila County Building Safety) — the two are distinct code regimes. Source: Town of Payson Code of Ordinances, Chapter 150 (Standardized Building and Construction Codes), via American Legal Publishing code library; Gila County Building Safety 'Adopted Building Code' page.; 2018 International Building Code (IBC), published on or after August 31, 2017 by the International Code Council, Inc., adopted by reference (Payson Code of Ordinances § 150.21), with Town of Payson local amendments including: Section 101.4 revised so referenced codes mean only codes specifically adopted by the Town; Section 104.10.1 (flood hazard areas) not adopted; new § 105.8 requiring construction sites be kept reasonably clear of debris; Section 107.2.6.1 (flood hazard documentation) revised to route through the Town Engineering Department prior to Certificate of Occupancy; Section 109.4 work-commencing-before-permit adds a minimum $70 investigation fee; Section 412.4.5 (residential aircraft hangar height/area limits) not adopted; Section 903.2.8 sprinkler trigger exempts single-family detached and duplex structures under 4,800 sq ft livable area; Table 2902.1 adds a drinking-fountain footnote for occupant loads over 99; IBC Appendix chapters not specifically adopted. Source: Payson Code of Ordinances § 150.21, International Building Code (amlegal.com); Town of Payson 'Amendments-2018' Building Department document.; 2018 International Residential Code (IRC), published on or after August 31, 2017 by the International Code Council, Inc., adopted by reference (Payson Code of Ordinances § 150.20), with extensive Town of Payson local amendments — see Local Amendments below for the Climatic and Geographic Design Criteria (Table R301.2(1)) and fire-sprinkler provisions. IRC Appendix M (Home Day Care - R3 Occupancy), Appendix Q (Tiny Houses), Appendix R (Light Straw Clay Construction), and Appendix S (Straw Bale Construction) are specifically adopted. Source: Payson Code of Ordinances § 150.20, International Residential Code (amlegal.com).; 2017 National Electrical Code (NEC), as adopted by the Town of Payson (one edition behind the 2018 ICC set, consistent with the standard ICC/NEC publication offset). Source: Town of Payson Building Division / Residential Permit Application program materials (via web search of paysonaz.gov Building Division and Residential Permit Application pages, confirming 2017 NEC alongside the 2018 IBC/IRC).; Current Mechanical Code, Plumbing Code, Fire Code, and Electric Code 'as adopted by the town' are cross-referenced generally in the Unified Development Code's building-permit application requirements (Payson Code of Ordinances § 154-09-003(C)(4): 'all required structural, electrical, mechanical, plumbing, civil engineering and other drawings and documents necessary to meet the requirements of the current Building Code, Plumbing Code, Mechanical Code, Fire Code, Electric Code and other codes adopted by the town'). The specific edition years for the standalone Mechanical, Plumbing, Fuel Gas, Existing Building, and Fire Code sections of Chapter 150 (following the same numbering pattern as § 150.20 IRC and § 150.21 IBC) could not be independently re-verified against the live amlegal.com code library within this research pass after repeated rate-limiting/bot-challenge blocks on those specific sub-pages; the 2018 IBC/IRC and 2017 NEC editions ARE independently confirmed. Given the Town's Chapter 150 adopts the IBC/IRC as a matched 2018-cycle ICC set, the companion IMC/IPC/IFGC/IEBC sections are very likely also the 2018 ICC editions, but this specific file does not assert that as verified fact — see confidence notes on individual permit types below.; Manufactured homes, mobile homes, factory-built buildings, and Park Model living units are subject to a Town of Payson building permit for placement per IRC § 105.1 as locally amended: approved hold-down anchors are required at building corners, and hard-wired/exterior electrical and mechanical equipment requires a separate permit. Park Model Living Unit is separately defined in IRC § 202 as amended (factory-assembled portable unit with an Arizona RV seal, chassis-mounted, not more than 12 ft wide, not more than 400 sq ft, not less than 320 sq ft, permanently connected to utilities, no holding tank other than an approved water heater). Source: Payson Code of Ordinances § 150.20 IRC amendments (1)-(2), (8).. Local amendments apply — see the Town of Payson overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Town of Payson building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.