Residential Building Permit (New Construction / Custom Home) in Surprise, Arizona

Required for new single-family dwellings and custom residences in Surprise. Applications are submitted online through the Permits & Applications Portal (Clariti/Oncamino); after initial approval, plans are uploaded and reviewed via ProjectDox. Permit fees are valuation-based: a flat $100 base fee plus $6 per each $1,000 of valuation up to $999,999.99 (then $5 per $1,000 beyond the first $1 million), plus an administrative processing fee of 0.50% of valuation (for the first $1 million). Plan review is 65% of the permit fee. Custom homes submitted on or after January 1, 2026 must comply with the 2024 I-Codes as locally amended.

Verified 2026-06-29 · Source

When you need this permit

Required documents

Fee schedule

Fee typeAmountNotes
Building/Fire Permit Fee — base + valuation tiersBase: $100 per permit (Fee 1 of 3). Valuation $1.00–$999,999.99: $6.00 per each $1,000 of valuation (Fee 2 of 3). Valuation $1,000,000+: $5.00 per each $1,000 beyond the first $1,000,000 (Fee 3 of 3).Citywide Fee Schedule, Resolution #2026-16, effective 5/19/2026. Valuation is determined by the City based on ICC Building Valuation Data.
Building Permit Administrative Processing Fee0.50% of valuation (for first $999,999.99); 0.052% of valuation beyond the first $1,000,000.Citywide Fee Schedule, Resolution #2026-16, effective 5/19/2026.
Building/Fire/Landscape Plan Review Fee65% of the permit feeCitywide Fee Schedule, Resolution #2026-16, effective 5/19/2026. Applied per permit.
Re-inspection$100 per hour ($200.00 minimum)Citywide Fee Schedule, Resolution #2026-16, effective 5/19/2026.
After-hours inspection$100 per hour ($200.00 minimum); weekends/holidays/3rd shift: $100 per hour ($300.00 minimum)Citywide Fee Schedule, Resolution #2026-16, effective 5/19/2026. Subject to availability; requires After Hours Inspection Form submitted to Development Center and fee paid prior to appointment.

Review timeline

1530 business days

Surprise’s published plan-review target

Inspection process

  1. 1

    Foundation / Pre-pour

    Underground plumbing, electrical, rebar, and footings inspected before concrete is poured.

  2. 2

    Rough Framing and Trades

    Rough framing, electrical, plumbing, and mechanical inspected before insulation and drywall.

  3. 3

    Insulation

    Insulation inspected before drywall installation where required by energy code.

  4. 4

    Final

    All work complete per approved plans; all fixtures, devices, and systems inspected at final before Certificate of Occupancy is issued.

Tips

Frequently asked questions

How do I submit a new home permit in Surprise?
Submit your permit request online through the Permits & Applications Portal at app.oncamino.com/surprise-az. Once the submission is approved, you will receive login credentials to upload your construction documents via ProjectDox, where City staff will conduct the plan review. Source: City of Surprise Building Inspections & Plan Review page and Permits & Applications page, surpriseaz.gov.

Sources & verification

Verified against official sources. Last reviewed 2026-06-29.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Surprise building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Other permits in Surprise

Get the AI compliance checklist

Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.