Residential Building Permit (New Construction / Custom Home) — Surprise, Arizona · Requirements sheet
Verified 2026-06-29 · Source: https://surpriseaz.gov/permits-applications
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction / Custom Home) in Surprise, Arizona
Required for new single-family dwellings and custom residences in Surprise. Applications are submitted online through the Permits & Applications Portal (Clariti/Oncamino); after initial approval, plans are uploaded and reviewed via ProjectDox. Permit fees are valuation-based: a flat $100 base fee plus $6 per each $1,000 of valuation up to $999,999.99 (then $5 per $1,000 beyond the first $1 million), plus an administrative processing fee of 0.50% of valuation (for the first $1 million). Plan review is 65% of the permit fee. Custom homes submitted on or after January 1, 2026 must comply with the 2024 I-Codes as locally amended.
Verified 2026-06-29 · Source
When you need this permit
- Submit the permit request online through the Permits & Applications Portal at app.oncamino.com/surprise-az; after approval, upload construction documents via ProjectDox
- Plans must comply with the 2024 International Residential Code (for one- and two-family dwellings) or 2024 IBC (for commercial/multifamily), with Surprise local amendments adopted under Ordinance 2025-14, effective January 1, 2026
- A licensed Arizona contractor is generally required; property owners building their own primary residence may qualify for an owner-builder permit under applicable Arizona law Owner-builder
- Permit is valid for 24 months from issuance; work must commence within 180 days of issuance; more than 180 days between inspections will void the permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Pre-pour
Underground plumbing, electrical, rebar, and footings inspected before concrete is poured.
- 2
Rough Framing and Trades
Rough framing, electrical, plumbing, and mechanical inspected before insulation and drywall.
- 3
Insulation
Insulation inspected before drywall installation where required by energy code.
- 4
Final
All work complete per approved plans; all fixtures, devices, and systems inspected at final before Certificate of Occupancy is issued.
See the full Surprise inspection guide — scheduling & re-inspection fees →
Tips
- Custom home plans submitted on or after January 1, 2026 must comply with the 2024 I-Codes (Ordinance 2025-14); plans designed to the 2018 codes will not be accepted for new submittals after that date.
- Submit through the Clariti/Oncamino Portal first; plans are uploaded separately in ProjectDox only after the Portal submission is approved and login credentials are provided.
- The permit fee is valuation-based: for a $300,000 home, example fee = $100 + ($300 × $6) = $1,900 permit fee + $1,235 plan review (65%) + $1,500 admin processing (0.50%) = approximately $4,635 total.
- Permit validity is 24 months from issuance — all required inspections including final must occur before expiration.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Surprise building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Surprise
Residential Building Permit (New Construction / Custom Home) in other cities
Compare residential building permit (new construction / custom home) fees across Arizona →
Look up this fee in a different city →