EV Charger / EVSE Permit in Surprise, Arizona
The City of Surprise has no dedicated electric-vehicle-charging-station permit type or fee line. An EV charger installation is electrical work requiring a permit under the City's adopted 2023 NEC (with local amendments, Ordinance 2025-14), submitted through the same Permits & Applications Portal (Clariti/Oncamino) as any other electrical work, and billed under the standard valuation-based Electrical Permit fee documented in this file's Electrical Permit entry — no distinct EV/EVSE dollar figure was found on the Citywide Fee Schedule (Resolution #2026-16). The City's local code amendments (reviewed directly) list specific permit-exempt electrical work (receptacle/fixture replacement, code-compliant ceiling fans, solar attic fans, landscape timer circuits) but do not name EV chargers among the exemptions, confirming a permit is required.
Verified 2026-07-20 · Source
When you need this permit
- Submit permit through Permits & Applications Portal at app.oncamino.com/surprise-az with plans uploaded via ProjectDox
- All work must comply with the 2023 NEC and Surprise local amendments (Ordinance 2025-14, effective January 1, 2026)
- EV chargers are not among the permit-exempt electrical work categories listed in Surprise's local IRC R105.2 amendment (receptacle/fixture replacement, ceiling fans, solar attic fans, landscape timer circuits) — a permit is required
- No dedicated EV/EVSE line-item, application, or checklist was found on the City's Citywide Fee Schedule or Currently Adopted Building Codes page
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Charging circuit wiring and conduit inspected before walls are closed
- 2
Final Electrical
Charging equipment installed per approved plans; outlets, panel, and service inspected at final
See the full Surprise inspection guide — scheduling & re-inspection fees →
Tips
- Surprise's local amendment to IRC R105.2 lists specific permit-exempt electrical work (simple receptacle/fixture replacement, code-compliant ceiling fans, solar attic fans, landscape timer circuits) — EV chargers are not on that list, so a permit is required even for a straightforward Level 2 charger install.
- Budget the permit fee off your project's stated valuation (charger equipment plus any panel upgrade and labor cost) using the same $100 base + $6/$1,000 valuation + 0.5% administrative fee formula used for any other electrical work — there is no flat EV-specific fee.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Surprise building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Surprise
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Surprise project checklist
Describe your project once and get every permit, document, and fee it triggers in Surprise — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →