Change of Use / Change of Occupancy Permit — Unincorporated Maricopa County, Arizona · Requirements sheet
Reviewed 2026-08-15 · Source: https://www.maricopa.gov/1629/Construction-Permit-Information
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Change of Occupancy Permit in Unincorporated Maricopa County, Arizona
Maricopa County Planning and Development prices a flat 'Occupancy Change' permit in the Flat Rate Fees table of its adopted Local Additions and Addenda. A Zoning Clearance is separately required before any change of use under Zoning Ordinance Article 1204.4, and a Certificate of Occupancy is required for all permits under Local Additions and Addenda Section 111. Fire and life-safety review for the new occupancy is performed by the Fire Authority Having Jurisdiction, not by the county.
Reviewed 2026-08-15 · Source
When you need this permit
- 'It shall be unlawful to construct, alter, repair or improve, remove or demolish, or to commence the creation, construction, alteration, removal or demolition of a building, structure or use without first filing with the Zoning Inspector an application for and obtaining a Zoning Clearance' — the ordinance text expressly reaches a change of use, not only physical construction (Maricopa County Zoning Ordinance Article 1204.4, page 12-6)
- A Certificate of Occupancy is required for all permits; its stated purpose is 'to ensure that all department, Fire Jurisdiction, plan and safety inspection requirements have been met and the building has been deemed safe for occupancy and use' (Local Additions and Addenda, Section 111)
- Fire and life-safety review for the new occupancy is performed by the Fire Authority Having Jurisdiction under Chapter 9 of that authority's adopted Fire Code — Maricopa County amended IBC Section 901.1 to delegate it and adopts no fire code of its own (Local Additions and Addenda, Tab F, printed page 11)
- A Zoning Clearance expires 180 days from its effective date if the use or authorized building construction has not actually commenced, and is void if the Building Permit for which it was a requirement expires (MCZO Article 1204.6.1)
- A Zoning Clearance will not be issued unless the owner guarantees access to Maricopa County personnel and appropriate emergency service providers for building inspections, zoning enforcement, and the provision of emergency services (MCZO Article 1204.5)
- Apply online through Permit Center (https://maricopacountyaz-energovweb.tylerhost.net/apps/selfservice) — paper submittals are no longer accepted
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
See the full Unincorporated Maricopa County inspection guide — scheduling & re-inspection fees →
Tips
- The $75 Occupancy Change fee is only part of the cost — a Zoning Clearance ($100 residential / $250 commercial) is separately required before any change of use, and any physical alteration is billed on top at Table 1-A valuation (alterations are valued at 20% of new building value) plus 65% plan review.
- Maricopa County does not review fire and life safety for your new occupancy. The fire district serving the parcel does, under its own fire code — contact it early, because the county's Certificate of Occupancy is expressly conditioned on 'Fire Jurisdiction' approval.
- A Zoning Clearance is void 180 days after its effective date if the new use has not actually commenced, and it dies automatically if the associated Building Permit expires. Do not let entitlement work sit.
- Verify the $75 figure with Planning & Development (602-506-3301) before relying on it: the adopted Local Additions and Addenda prices it, but the department's June 2024 fee summary marks the row as not configured in its Permit Center system.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-15.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Maricopa County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Maricopa County
Change of Use / Change of Occupancy Permit in other cities
Compare change of use / change of occupancy permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Unincorporated Maricopa County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Maricopa County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →