Solar PV Permit (Roof-Mounted and Ground-Mounted Photovoltaic) in Unincorporated Maricopa County, Arizona
Required for residential photovoltaic (solar PV) system installations in the unincorporated areas of Maricopa County. Two distinct permit types apply: roof-mounted PV systems (minor residential electrical permit, flat fee of $300) and ground-mounted PV systems under 6 feet high (minor residential permit, flat fee of $500). Ground-mounted systems over 6 feet high are treated as accessory structures and have higher upfront fees. All applications submitted through Permit Center online.
Verified 2026-06-29 · Source
When you need this permit
- Roof-mounted PV: classified as a minor residential electrical permit; submit online through Permit Center using specific file naming conventions
- Ground-mounted PV less than 6 feet high: classified as a residential accessory permit; submit 3 sets of building plans and 7 sets of site plans online
- Ground-mounted PV over 6 feet high: treated as a residential accessory structure; upfront fees of $110 plus additional review fees during plan review
- Required documents for roof-mounted: Application Form (APPL-FORM.pdf); Building Plan Set including cut sheets, specs, and load calculations (BLDG-PLAN.pdf); Structural Calculations only if installed on a manufactured/mobile home (STRU-CALC.pdf)
- All roof-mounted submissions must include: project valuation on the PV application; site-specific roof design showing photovoltaic array locations; rack system details including mounting hardware; anchoring and fastening details; equipment locations; product listing information; compliance with Maricopa County's current adopted NEC edition; complete one- and three-line electrical drawings; manufacturer's product information; utility interconnection information
- Indicate compliance with the 2017 NEC on all submitted drawings
Required documents
- Req
Solar Permit Application Form (PDF)
Complete application form for roof-mounted solar permit; must be submitted as APPL-FORM.pdf; available at https://www.maricopa.gov/DocumentCenter/View/46333
- Req
Building Plan Set (BLDG-PLAN.pdf)
Cut sheets, specs, and load calculations — must all be in a single file, not submitted separately
- Opt
Structural Calculations (STRU-CALC.pdf)
Required only if solar system is installed on a manufactured/mobile home
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Roof-mounted residential solar PV (all-in flat fee) | $300 total | Per Section 208 of the Maricopa County Local Additions and Addenda. Includes all administrative, building plan review, and building inspection fees. Payment due upon acceptance. Source: https://www.maricopa.gov/1923/Go-Solar-for-Residential-Service and Local Additions and Addenda Section 208. |
| Ground-mounted residential solar PV less than 6 feet high (all-in flat fee) | $500 total | Per Local Additions and Addenda Section 208 and Maricopa County Zoning Ordinance Section 1602.1. Includes all administrative, zoning, building plan review, and building upfront inspection fees. Additional drainage fees may apply depending on site-specific engineering requirements. Source: https://www.maricopa.gov/1923/Go-Solar-for-Residential-Service |
| Ground-mounted residential solar PV over 6 feet high (accessory structure) | $110 upfront plus additional review fees assessed during plan review | System over 6 feet is treated as a residential accessory structure. Source: https://www.maricopa.gov/1923/Go-Solar-for-Residential-Service |
Review timeline
~1–10 business days
Typical estimate — confirm current times with the Unincorporated Maricopa County building department
Inspection process
- 1
Roof-mounted: Building Inspection
Included in flat-fee permit; scheduled through Permit Center. Verify installation per approved plans and 2017 NEC.
- 1
Ground-mounted: Pre-issuance / Upfront Inspection
Included in flat-fee permit for ground-mounted systems under 6 feet. Additional inspections may be required depending on site drainage conditions.
- 2
Final
System fully installed and operational; all wiring complete per 2017 NEC; utility interconnection verified
Tips
- Roof-mounted solar PV permits are all-in flat fee of $300 — this covers all plan review and inspection. For complete submittals received before 11:00 AM, permits are typically processed the same business day.
- Use the county's specific file-naming conventions for solar submittals: APPL-FORM.pdf for the application, BLDG-PLAN.pdf for the building plan set (load calcs must be included in this file, not separate), and STRU-CALC.pdf for structural calculations (manufactured homes only).
- All PDFs must be properly rotated, flattened, and optimized before upload for faster processing.
- If modifying an already-issued solar permit, submit the Modification Form as MODI-FORM.pdf along with the modified Building Plan Set.
Frequently asked questions
- What is the permit fee for rooftop solar in unincorporated Maricopa County?
- $300 flat fee, all-inclusive (covers all administrative, plan review, and inspection fees). This is set by Section 208 of the Maricopa County Local Additions and Addenda. Apply at https://maricopacountyaz-energovweb.tylerhost.net/apps/selfservice. Source: https://www.maricopa.gov/1923/Go-Solar-for-Residential-Service
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
- Maricopa County Planning and Development Department — official building department
- Go Solar for Residential Service | Maricopa County Planning & Development
- Local Additions and Addenda (TA2022001, 19 September 2022) — PDF (Section 208 solar fees)
- Summary of the Fee Schedule, June 2024 — PDF
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Maricopa County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Maricopa County
Get the AI compliance checklist
Upload your project scope, get a jurisdiction-specific checklist of everything you need. Coming soon.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.