Solar PV Permit (Roof-Mounted and Ground-Mounted Photovoltaic) in Unincorporated Maricopa County, Arizona
Required for residential photovoltaic (solar PV) system installations in the unincorporated areas of Maricopa County. Two distinct permit types apply: roof-mounted PV systems (minor residential electrical permit, flat fee of $300) and ground-mounted PV systems under 6 feet high (minor residential permit, flat fee of $500). Ground-mounted systems over 6 feet high are treated as accessory structures and have higher upfront fees. All applications submitted through Permit Center online.
Verified 2026-06-29 · Source
When you need this permit
- Roof-mounted PV: classified as a minor residential electrical permit; submit online through Permit Center using specific file naming conventions
- Ground-mounted PV less than 6 feet high: classified as a residential accessory permit; submit 3 sets of building plans and 7 sets of site plans online
- Ground-mounted PV over 6 feet high: treated as a residential accessory structure; upfront fees of $110 plus additional review fees during plan review
- Required documents for roof-mounted: Application Form (APPL-FORM.pdf); Building Plan Set including cut sheets, specs, and load calculations (BLDG-PLAN.pdf); Structural Calculations only if installed on a manufactured/mobile home (STRU-CALC.pdf)
- All roof-mounted submissions must include: project valuation on the PV application; site-specific roof design showing photovoltaic array locations; rack system details including mounting hardware; anchoring and fastening details; equipment locations; product listing information; compliance with Maricopa County's current adopted NEC edition; complete one- and three-line electrical drawings; manufacturer's product information; utility interconnection information
- Indicate compliance with the 2017 NEC on all submitted drawings
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Roof-mounted: Building Inspection
Included in flat-fee permit; scheduled through Permit Center. Verify installation per approved plans and 2017 NEC.
- 1
Ground-mounted: Pre-issuance / Upfront Inspection
Included in flat-fee permit for ground-mounted systems under 6 feet. Additional inspections may be required depending on site drainage conditions.
- 2
Final
System fully installed and operational; all wiring complete per 2017 NEC; utility interconnection verified
See the full Unincorporated Maricopa County inspection guide — scheduling & re-inspection fees →
Tips
- Roof-mounted solar PV permits are all-in flat fee of $300 — this covers all plan review and inspection. For complete submittals received before 11:00 AM, permits are typically processed the same business day.
- Use the county's specific file-naming conventions for solar submittals: APPL-FORM.pdf for the application, BLDG-PLAN.pdf for the building plan set (load calcs must be included in this file, not separate), and STRU-CALC.pdf for structural calculations (manufactured homes only).
- All PDFs must be properly rotated, flattened, and optimized before upload for faster processing.
- If modifying an already-issued solar permit, submit the Modification Form as MODI-FORM.pdf along with the modified Building Plan Set.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Maricopa County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Maricopa County
Solar PV Permit (Roof-Mounted and Ground-Mounted Photovoltaic) in other cities
Compare solar pv permit (roof-mounted and ground-mounted photovoltaic) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Unincorporated Maricopa County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Maricopa County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →