Required for new commercial construction and separate commercial site improvements in Youngtown. Unlike residential-lot permits, commercial construction permits are explicitly classified as 'licenses' under the Town's A.R.S. § 9-835 Review Timeframes Policy and carry a fully published administrative + substantive review timeline.

Verified 2026-07-07 · Source

When you need this permit

  • Building permit required for new commercial construction and separate commercial site improvements within Youngtown town limits
  • Explicitly classified as a 'license' subject to the Town's Review Timeframes Policy (A.R.S. § 9-835) — not exempt like residential-lot permits
  • Two (2) copies of plans required, submitted to the Community Development Department
  • Commercial fee schedules may be negotiable depending on the economic value of the development to the Town — contact the Community Development Manager for details
  • Sign review is integrated into the standard commercial plan review process rather than requiring a separate Sign Review Committee submittal
  • Nonresidential/commercial contractors must hold valid Arizona ROC licensure and a Town of Youngtown business license Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on ValuationTown of Youngtown Building Permit Fee Schedule page; commercial fee schedules 'may be negotiable, depending on the economic value' per the Community Development Manager
Same Town-wide valuation table as residential: $85 minimum ($0-$500 value) up to $5,660.25 + $3.65/additional $1,000 above $1,000,000
Plan Check FeeTown of Youngtown Building Permit Fee Schedule page
65% of Building Permit Fee

Review timeline

Plan reviewYoungtown’s published plan-review target
27–37 business days

How long did your Commercial Building Permit (New Construction / Site Improvement) permit actually take in Youngtown?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Administrative Completeness Review

    Preliminary completeness review against Town submission criteria/checklists (1st: 5 working days; 2nd: 2 working days)

  2. 2

    Substantive Review (1st)

    Full compliance review against Town regulations and requirements (20 working days for new commercial projects/site improvement)

  3. 3

    Substantive Review (2nd)

    Second substantive review after corrections (10 working days for new commercial projects/site improvement); Town must approve or deny after this review

  4. 4

    Final Inspection

    Final inspection and Certificate of Occupancy sign-off

See the full Youngtown inspection guide — scheduling & re-inspection fees →

Tips

  • Per the Town's Review Timeframes Policy, 'New Commercial Projects and Separate Commercial Site Improvement' carries a 5/2 working-day administrative review (1st/2nd) plus a 20/10 working-day substantive review (1st/2nd), for a stated Overall Timeframe of 37 working days (the Policy's own summary column); adding the component figures (5+2+20+10=37) confirms internal consistency, though some related categories in the same table show a components-sum that doesn't cleanly equal the stated 'Overall' column, so the Policy's own stated Overall Timeframe figures are used as authoritative.
  • Review timeframes in this table are 'working days' (24-hour periods excluding weekends and legal holidays), counted from the first full day after submittal, and are suspended entirely while a corrections request is outstanding.
  • Public-hearing-dependent commercial approvals (Conditional Use Permit, Preliminary/Final Plat, Minor Land Division — all non-residential) run on a separate 36 working-day overall timeframe (8/8 administrative, 12/8 substantive), and that Overall Timeframe is itself suspended during any required public hearing per A.R.S. § 9-835(C)(8)(c).
  • Tenant Improvements run a similar administrative timeframe (5/2) but a variable substantive review of 'up to 15/10' working days (32 working days overall), explicitly subject to Town discretion based on project complexity and staffing.

Frequently asked questions

Youngtown requires a commercial building permit (new construction / site improvement) for: Building permit required for new commercial construction and separate commercial site improvements within Youngtown town limits; Explicitly classified as a 'license' subject to the Town's Review Timeframes Policy (A.R.S. § 9-835) — not exempt like residential-lot permits; Two (2) copies of plans required, submitted to the Community Development Department; Commercial fee schedules may be negotiable depending on the economic value of the development to the Town — contact the Community Development Manager for details; Sign review is integrated into the standard commercial plan review process rather than requiring a separate Sign Review Committee submittal; Nonresidential/commercial contractors must hold valid Arizona ROC licensure and a Town of Youngtown business license. If your project isn't listed, confirm with Town of Youngtown Community Development Department (Building Inspector / Community Development & Public Infrastructure Manager) at 623-933-8286 ext. 200 (Building Inspector); ext. 101 (Building Inspector line on permit application) before starting work.

In Youngtown, the published Building Permit Fee — Based on Valuation is: Same Town-wide valuation table as residential: $85 minimum ($0-$500 value) up to $5,660.25 + $3.65/additional $1,000 above $1,000,000. Additional published fees: Plan Check Fee — 65% of Building Permit Fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Arizona's A.R.S. § 9-835(N) exempts residential-lot development review applications (including swimming pools, hardscape, property walls, subdivisions, and master-planned communities) from the statute's review-timeframe disclosure requirement, while commercial construction permits are explicitly classified as 'licenses' subject to the Law. Youngtown's Review Timeframes Policy therefore publishes timeframes only for commercial/non-residential application types.

You'll need: Commercial Building Permit Application; Site Plan. See the required-documents checklist on this page for details on each.

Youngtown requires 4 inspection(s) for a commercial building permit (new construction / site improvement), in order: Administrative Completeness Review, Substantive Review (1st), Substantive Review (2nd), Final Inspection. Schedule each through Town of Youngtown Community Development Department (Building Inspector / Community Development & Public Infrastructure Manager) (623-933-8286 ext. 200 (Building Inspector); ext. 101 (Building Inspector line on permit application)).

Apply through Town of Youngtown Community Development Department (Building Inspector / Community Development & Public Infrastructure Manager) at 12030 N. Clubhouse Square, Youngtown, AZ 85363. Phone: 623-933-8286 ext. 200 (Building Inspector); ext. 101 (Building Inspector line on permit application), email: garrington@youngtownaz.org (Gregory Arrington, Community Development Manager). Office hours: Monday - Friday, 8:00 a.m. to 4:00 p.m. Applications are submitted in person at Town Hall (two copies of plans required); a Building Permit Fee and a separate Plan Review Fee (65% of the Building Permit Fee) both apply and must be paid before a permit is issued.. Official information: https://www.youngtownaz.org/departments/community_development/permits_plan_review.php.

Youngtown, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town/county authority under state enabling statutes (A.R.S. Title 9). The Town of Youngtown is a small (~6,500 population) incorporated town, but it runs its own in-house Community Development Department with a dedicated Building Inspector and independently adopts and administers its own construction codes; it does NOT defer general building permitting to Maricopa County (though fire/life-safety plan review and inspection for construction within Youngtown town limits is performed by the Sun City Fire and Medical District, a special fire district, per that district's own construction-permit page). Source: Town of Youngtown Permits & Plan Review page; Town of Youngtown Construction Codes & Licensing page; Sun City Fire and Medical District Construction Permit page.; 2021 International Building Code (IBC), as adopted by the Town of Youngtown for commercial construction. Source: Town of Youngtown Construction Codes & Licensing page (youngtownaz.org).; 2021 International Residential Code (IRC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Existing Building Code (IEBC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Mechanical Code (IMC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Plumbing Code (IPC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Fuel Gas Code (IFGC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Energy Conservation Code (IECC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Fire Code (IFC), as adopted by the Town of Youngtown; fire/life-safety plan review and inspection within Youngtown town limits is administered by the Sun City Fire and Medical District, not the Town's own Community Development Department. Source: Town of Youngtown Construction Codes & Licensing page; Sun City Fire and Medical District Construction Permit page.; 2021 International Property Maintenance Code (IPMC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Pool and Spa Code (ISPSC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2020 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by the Town of Youngtown (note: electrical code cycle is one edition behind the 2021 ICC set). Source: Town of Youngtown Construction Codes & Licensing page.; 2013 AZBO (Arizona Building Officials) / Maricopa Association of Governments (MAG) Amendments, applied by the Town of Youngtown alongside the adopted ICC/NEC codes above. Source: Town of Youngtown Construction Codes & Licensing page.; Right-of-way / civil construction permits (Youngtown Municipal Code Section 17.72.040, adopted October 17, 2013): all civil construction projects must conform to the 1998 Maricopa Association of Governments (MAG) Uniform Standard Specifications and Details for Public Works Construction; right-of-way construction permit fees are 2% of the engineer's estimated job cost, minimum $15. Source: Town of Youngtown Residential Permit Application (rev. 4/26/2018), reverse-side Permit Fee Schedule citing YMC 17.72.040.; Manufactured homes, mobile homes, and factory-built buildings are regulated directly by the State of Arizona (A.R.S. § 41-4001 et seq., Arizona Department of Fire, Building and Life Safety / Office of Manufactured Housing) for construction/installation standards; the Town issues a separate on-site permit for placement, foundation/tie-down, zoning compliance, and site improvements, consistent with standard IBC Section 3113 treatment. Source: Arizona statutory framework as applied statewide; not independently re-confirmed on a dedicated Youngtown manufactured-housing page.. Local amendments apply — see the Youngtown overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Youngtown building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Youngtown.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.