Residential/Commercial Solar Photovoltaic (PV) Permit in Youngtown, Arizona

Required for installation of rooftop residential or commercial solar photovoltaic systems in the Town of Youngtown. There is no dedicated solar/PV permit type or fee line item published on the Town's Building Permit Fee Schedule page — confirmed directly against that page, which contains no mention of solar, photovoltaic, PV, or renewable energy. A solar installation is processed as a standard building permit, billed under the same valuation-based fee table used for other construction, and is subject to Arizona's statewide solar construction permit statute (A.R.S. § 9-468).

Verified 2026-07-20 · Source

When you need this permit

  • Building permit required for the structural/racking portion, submitted in person with two (2) copies of plans to the Community Development Department, per the Town's general permit submittal process
  • Electrical permit required for the PV wiring/interconnection portion; nonresidential/commercial contractors must hold valid Arizona ROC licensure and a Town of Youngtown business license Contractor
  • Per A.R.S. § 9-468, the Town's total fee for a solar construction permit may not exceed the actual cost of issuance, and the Town must provide an itemized cost breakdown upon request
  • Applications are submitted in person at Town Hall (12030 N. Clubhouse Square); both a Building Permit Fee and a separate Plan Review Fee (65% of the Building Permit Fee) apply and must be paid before a permit is issued

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Based on Valuation (no dedicated solar/PV line item)Town of Youngtown Building Permit Fee Schedule page — confirmed directly that no solar/photovoltaic/renewable energy line item exists; general valuation table applies
Same Town-wide valuation table as other construction: $85 minimum ($0-$500 value) up to $5,660.25 + $3.65/additional $1,000 above $1,000,000
Plan Check FeeTown of Youngtown Building Permit Fee Schedule page
65% of Building Permit Fee

Review timeline

Plan review
Not published — contact the department

How long did your Residential/Commercial Solar Photovoltaic (PV) Permit permit actually take in Youngtown?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final

    Racking, roof penetrations, and electrical connections verified

See the full Youngtown inspection guide — scheduling & re-inspection fees →

Tips

  • Youngtown has no dedicated solar/PV fee line item — confirmed directly against the Town's Building Permit Fee Schedule page, which contains no mention of solar, photovoltaic, or renewable energy. A solar installation is billed under the same valuation-based fee table as any other construction.
  • Arizona's statewide A.R.S. § 9-468 still caps whatever total fee Youngtown charges for a solar construction permit at the Town's actual cost of issuance — ask the Community Development Manager for an itemized cost breakdown if the calculated valuation-based fee seems high.
  • Commercial fee schedules 'may be negotiable, depending on the economic value' of the development to the Town per the Community Development Manager — worth asking about for a larger commercial solar installation.

Frequently asked questions

Youngtown requires a residential/commercial solar photovoltaic (pv) permit for: Building permit required for the structural/racking portion, submitted in person with two (2) copies of plans to the Community Development Department, per the Town's general permit submittal process; Electrical permit required for the PV wiring/interconnection portion; nonresidential/commercial contractors must hold valid Arizona ROC licensure and a Town of Youngtown business license; Per A.R.S. § 9-468, the Town's total fee for a solar construction permit may not exceed the actual cost of issuance, and the Town must provide an itemized cost breakdown upon request; Applications are submitted in person at Town Hall (12030 N. Clubhouse Square); both a Building Permit Fee and a separate Plan Review Fee (65% of the Building Permit Fee) apply and must be paid before a permit is issued. If your project isn't listed, confirm with Town of Youngtown Community Development Department (Building Inspector / Community Development & Public Infrastructure Manager) at 623-933-8286 ext. 200 (Building Inspector); ext. 101 (Building Inspector line on permit application) before starting work.

No. The Town's Building Permit Fee Schedule page contains no mention of solar, photovoltaic, or renewable energy. A solar installation is billed as a standard building permit under the same valuation-based fee table ($85 minimum, scaling up) plus a 65% Plan Check Fee, the same structure used for any other construction.

Youngtown does not publish a plan-review timeline for this permit. Contact Town of Youngtown Community Development Department (Building Inspector / Community Development & Public Infrastructure Manager) at 623-933-8286 ext. 200 (Building Inspector); ext. 101 (Building Inspector line on permit application) for current turnaround.

You'll need: Building Permit Application; Site/Electrical Plans. See the required-documents checklist on this page for details on each.

Youngtown requires 2 inspection(s) for a residential/commercial solar photovoltaic (pv) permit, in order: Rough Electrical, Final. Schedule each through Town of Youngtown Community Development Department (Building Inspector / Community Development & Public Infrastructure Manager) (623-933-8286 ext. 200 (Building Inspector); ext. 101 (Building Inspector line on permit application)).

Apply through Town of Youngtown Community Development Department (Building Inspector / Community Development & Public Infrastructure Manager) at 12030 N. Clubhouse Square, Youngtown, AZ 85363. Phone: 623-933-8286 ext. 200 (Building Inspector); ext. 101 (Building Inspector line on permit application), email: garrington@youngtownaz.org (Gregory Arrington, Community Development Manager). Office hours: Monday - Friday, 8:00 a.m. to 4:00 p.m. Applications are submitted in person at Town Hall (two copies of plans required); a Building Permit Fee and a separate Plan Review Fee (65% of the Building Permit Fee) both apply and must be paid before a permit is issued.. Official information: https://www.youngtownaz.org/departments/community_development/permits_plan_review.php.

Youngtown, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/town/county authority under state enabling statutes (A.R.S. Title 9). The Town of Youngtown is a small (~6,500 population) incorporated town, but it runs its own in-house Community Development Department with a dedicated Building Inspector and independently adopts and administers its own construction codes; it does NOT defer general building permitting to Maricopa County (though fire/life-safety plan review and inspection for construction within Youngtown town limits is performed by the Sun City Fire and Medical District, a special fire district, per that district's own construction-permit page). Source: Town of Youngtown Permits & Plan Review page; Town of Youngtown Construction Codes & Licensing page; Sun City Fire and Medical District Construction Permit page.; 2021 International Building Code (IBC), as adopted by the Town of Youngtown for commercial construction. Source: Town of Youngtown Construction Codes & Licensing page (youngtownaz.org).; 2021 International Residential Code (IRC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Existing Building Code (IEBC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Mechanical Code (IMC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Plumbing Code (IPC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Fuel Gas Code (IFGC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Energy Conservation Code (IECC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Fire Code (IFC), as adopted by the Town of Youngtown; fire/life-safety plan review and inspection within Youngtown town limits is administered by the Sun City Fire and Medical District, not the Town's own Community Development Department. Source: Town of Youngtown Construction Codes & Licensing page; Sun City Fire and Medical District Construction Permit page.; 2021 International Property Maintenance Code (IPMC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2021 International Pool and Spa Code (ISPSC), as adopted by the Town of Youngtown. Source: Town of Youngtown Construction Codes & Licensing page.; 2020 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by the Town of Youngtown (note: electrical code cycle is one edition behind the 2021 ICC set). Source: Town of Youngtown Construction Codes & Licensing page.; 2013 AZBO (Arizona Building Officials) / Maricopa Association of Governments (MAG) Amendments, applied by the Town of Youngtown alongside the adopted ICC/NEC codes above. Source: Town of Youngtown Construction Codes & Licensing page.; Right-of-way / civil construction permits (Youngtown Municipal Code Section 17.72.040, adopted October 17, 2013): all civil construction projects must conform to the 1998 Maricopa Association of Governments (MAG) Uniform Standard Specifications and Details for Public Works Construction; right-of-way construction permit fees are 2% of the engineer's estimated job cost, minimum $15. Source: Town of Youngtown Residential Permit Application (rev. 4/26/2018), reverse-side Permit Fee Schedule citing YMC 17.72.040.; Manufactured homes, mobile homes, and factory-built buildings are regulated directly by the State of Arizona (A.R.S. § 41-4001 et seq., Arizona Department of Fire, Building and Life Safety / Office of Manufactured Housing) for construction/installation standards; the Town issues a separate on-site permit for placement, foundation/tie-down, zoning compliance, and site improvements, consistent with standard IBC Section 3113 treatment. Source: Arizona statutory framework as applied statewide; not independently re-confirmed on a dedicated Youngtown manufactured-housing page.. Local amendments apply — see the Youngtown overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Youngtown building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.