Septic System Permit (Conventional and Alternative) in Unincorporated Navajo County, Arizona
Required for on-site wastewater disposal systems in unincorporated Navajo County. Conventional systems are reviewed directly by the county; alternative systems (composting toilet, pressure distribution, engineered pad, aerobic, and others) are administered by Navajo County under a delegation agreement with the Arizona Department of Environmental Quality (ADEQ).
Reviewed 2026-07-07 · Source
When you need this permit
- Conventional system: Construction Permit Application, ADEQ General Permit 4.02 Notice of Intent to Discharge, GP 4.02 Checklist, GP 4.02 Calculation Worksheet, ADEQ Site Investigation Report Form, Bill of Materials, Trench Detail, and a copy of the Onsite Findings Report (NCERA Form 310)
- Soil suitability for a conventional system requires a percolation rate of 10-120 minutes-per-inch (MPI), or a Soil Absorption Rating (SAR) of .2 or higher, with a 5-foot minimum separation from groundwater or an impermeable confining layer
- If percolation is slower than 120 MPI or SAR is below .2, an alternative on-site disposal system may be permitted through ADEQ, and Navajo County does permit several alternative system types
- Alternative system: Construction Permit Application, ADEQ GP 4.03 Notice of Intent to Discharge, Engineered System Design Plans, list of equipment/materials, Operation and Maintenance Plan, ADEQ Site Investigation Report Form, and NCERA Form 310
- Detailed site plan required including driving directions to the parcel
- No building, manufactured home, or meter-loop permit will be issued elsewhere until the septic system is approved and documented
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Site Suitability / Percolation Test
Soil percolation rate (10-120 MPI) or Soil Absorption Rating (.2+) verified before system design approval
- 2
Trench / System Installation Inspection
Septic system installation verified against approved plans before backfill
- 3
Final Septic Inspection
System in total working order; required before the associated building/manufactured home final inspection and Certificate of Occupancy
See the full Unincorporated Navajo County inspection guide — scheduling & re-inspection fees →
Tips
- Lot size can factor into site suitability determinations, but the county notes this applies only as it pertains to the suitability of the owner's specific plans, not as an independent minimum-lot-size septic rule.
- If your soil's percolation rate is outside the conventional-system range (10-120 MPI, or SAR below .2), do not assume you cannot build — Navajo County permits several ADEQ-delegated alternative system types (composting toilet, pressure distribution, engineered pad, aerobic systems, and others).
- A septic system must be approved and documented BEFORE the county will issue a building permit, manufactured home permit, or meter-loop (electrical hook-up) permit for the same property.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Navajo County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Navajo County
Septic System Permit (Conventional and Alternative) in other cities
Compare septic system permit (conventional and alternative) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Unincorporated Navajo County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Navajo County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →