Change of Use / Change of Occupancy Permit in Unincorporated Navajo County, Arizona
Navajo County expressly requires a permit to change the occupancy of a building or structure in the unincorporated county, and the Building Official must issue a Certificate of Occupancy before any change in the existing occupancy classification takes effect. The county publishes no distinct change-of-occupancy fee line; the work is priced as a Building Permit on the IBC/UBC Building Valuation Data and IRC 2018 charts adopted by Board of Supervisors Resolution 9-2022, plus Plan Review/Check at 35% of the total building permit fee. Fire and life-safety review for the new occupancy is performed by the fire district serving the parcel, not by Navajo County, which adopts no fire code.
Reviewed 2026-08-15 · Source
When you need this permit
- 'Any owner or authorized agent who intends to construct, alter, repair, move, convert, enlarge or change the occupancy of a building or structure... shall first make application and obtain the required permit' — Navajo County Addenda & Additions to the International Building Codes (amended 3-15-22), 'Permits Required IRC 105.1', printed page 8
- 'No building or structure shall be used or occupied, and no change in the existing occupancy classification of a building or structure or portion thereof shall be made until the Building Official has issued a Certificate of Occupancy' — same document, 'Certificate of Occupancy', printed page 6
- All required inspections must be performed, and the work approved, before issuance of a Certificate of Occupancy — same document, 'Required Inspections', printed page 8
- Where a conflict exists between codes adopted by Navajo County or the State of Arizona and the Addenda and Additions, the more restrictive provision prevails; the Navajo County Technical Advisory Board acts as the Board of Appeals — same document, printed page 5
- Fire and life-safety review of the new occupancy is performed by the fire district serving the parcel under that district's own adopted International Fire Code — Navajo County adopts no fire code and publishes no fire fee (see localAmendments)
- No building, manufactured home, or meter-loop permit will be issued unless hook-up to an approved sanitary system is available and documented — same document, 'Issuance of Permit', printed page 6
- Submit through Navajo County Planning & Development Services; area offices at Show Low (1100 E. Thornton Rd., 928-532-6040), Holbrook (100 W. Public Works Dr., 928-524-4100) and Overgaard (2188 W. Country Club Dr., 928-535-7110). The department works a four-day week, Monday through Thursday.
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Required inspections per the Addenda & Additions
The county's published inspection list (Addenda & Additions, 'Required Inspections', printed page 8) covers septic systems, foundation piers/trenches, rough plumbing/mechanical/gas/electrical prior to covering, floodplain, fire resistance where required, footing steel, stem steel, under-slab, under-floor framing, roof sheathing and shear panel nail-off, rough-in framing/electrical/plumbing/venting/heating, drywall nailing and final; which of these apply depends on the scope of the occupancy change. Additional inspections may be required for specialized projects.
- 2
Final — Certificate of Occupancy
'All inspections must be performed, and work approved before issuance of a Certificate of Occupancy' (Addenda & Additions, printed page 8). No change in the existing occupancy classification is effective until the Building Official has issued the Certificate of Occupancy (printed page 6).
See the full Unincorporated Navajo County inspection guide — scheduling & re-inspection fees →
Tips
- Navajo County does not review fire and life safety for your new occupancy — it adopts no fire code. The fire district serving your parcel (for example Timber Mesa Fire and Medical District or Pinetop Fire District) runs its own plan review, issues its own construction permit and bills you directly. Start that conversation before you submit to the county.
- There is no published change-of-occupancy fee. The county prices the work as a building permit on the adopted valuation charts plus 35% plan review, so a change of use with little or no construction value has no published price — call Planning & Development Services at 928-532-6040 for a project-specific quote.
- Planning & Development Services works Monday through Thursday only. Emergency inspections are offered Fridays at $75.00 per hour with a Thursday 3:00 p.m. scheduling cutoff.
- An approved septic system or a Letter of Release from a Sanitary District is a hard prerequisite to permit issuance — if the new occupancy increases fixture load, resolve wastewater capacity first.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-15.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Navajo County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Navajo County
Change of Use / Change of Occupancy Permit in other cities
Compare change of use / change of occupancy permit fees across Arizona →
Look up this fee in a different city →