Residential Building Permit (New Construction, Addition, Accessory Structure) — Unincorporated Navajo County, Arizona · Requirements sheet
Reviewed 2026-07-07 · Source: https://www.navajocountyaz.gov/289/Building-Information
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction, Addition, Accessory Structure) in Unincorporated Navajo County, Arizona
Required for new single-family dwellings, townhouses, additions, remodels, garages, and accessory structures in the unincorporated areas of Navajo County (outside the incorporated cities/towns of Show Low, Winslow, Holbrook, Pinetop-Lakeside, Snowflake, and Taylor, and outside Navajo Nation/Hopi tribal trust land). Reviewed against the 2018 IRC/IBC (with local exclusions) and the county's Addenda & Additions by Navajo County Planning & Development Services / Building & Safety.
Reviewed 2026-07-07 · Source
When you need this permit
- Required for new single-family/townhouse construction, additions, remodels, garages, and accessory structures exceeding 200 sq ft (or any size if it has utilities or sleeping quarters) in unincorporated Navajo County
- Proof of a Navajo County Assessor's Parcel Number required to process any permit application
- Two (2) sets of building plans required at minimum: floor plan, building cross-section, roof plan, foundation plan, electrical plan, two (2) elevations, plus any required engineering specifications
- Detailed, accurate site plan required showing setbacks, utilities, septic system (including reserve area), well(s), driveways, and existing buildings on all four sides, with driving directions to the parcel
- Proof of ownership (property parcel number) required
- Proof of an approved septic system, OR a Letter of Release from a Sanitary District, required before a building permit is issued
- All permits must first pass a flood hazard evaluation before permission to build is granted
- Submit application and required documents at any Navajo County Building Department location (Show Low, Holbrook, or Heber/Overgaard); applications are reviewed by both Flood Control and the Building Department
- Payment for issued permits must be made by check or money order only
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing / Foundation Steel
Foundation piers, trenches, or basement excavation and erected forms; footing rebar placed 6 inches below the surface of poured concrete and 3 inches minimum from soil. No footing/foundation inspection given without property lines and required yard setbacks clearly marked.
- 2
Stem Wall Steel
CMU stem wall reinforcement per the Addenda's foundation/pier tables (rebar sizing and spacing vary by wall height)
- 3
Under-Slab / Under-Floor
Under-slab copper, sewer, and electrical before concrete placement; under-floor framing before floor sheathing
- 4
Rough-In Framing, Electrical, Plumbing, Venting, Heating
Combined rough-in inspection; house must be weather-sealed prior to this inspection
- 5
Roof Sheathing / Shear Panel Nail-Off
Roof sheathing nail spacing (6 inches on edges, 12 inches in field) inspected before roofing material placement
- 6
Drywall Nailing
Fastener spacing and type per the Addenda's drywall fastener schedule, before taping/finishing
- 7
Final Inspection
Full Final Inspection Checklist per the Addenda (septic/plumbing operable, electrical panels labeled, GFCI protection verified, smoke detectors, 911 address posted, and more); all utilities must be on and working. A Temporary Certificate of Occupancy may be issued for a single-family dwelling pending minor corrections, contingent on completion within 60 days.
See the full Unincorporated Navajo County inspection guide — scheduling & re-inspection fees →
Tips
- Inspections can generally be scheduled with 24-hour notice, Monday through Friday, by calling the Building Department number on the permit; have the permit number, name on the permit, inspection type, address, and a contact phone number ready.
- No footing, foundation, or septic system inspection will be given without property lines and required yard setbacks clearly marked on-site.
- Once a building is fully enclosed, someone must be on the premises to receive further inspections.
- Deed restrictions and HOA CC&Rs are explicitly NOT enforced by Navajo County — check separately with your Homeowners Association or Architectural Committee.
- Design/climatic criteria (wind, seismic, snow load) vary significantly by area within the unincorporated county — confirm the correct design table for your specific location (Heber/Overgaard, Pinetop/Lakeside, Show Low/Linden, White Mountain Lake, Clay Springs, Pinedale, Snowflake/East, Taylor/Shumway, or the Holbrook/Joseph City/Winslow/Woodruff area) before finalizing structural plans.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Navajo County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Navajo County
Residential Building Permit (New Construction, Addition, Accessory Structure) in other cities
Look up this fee in a different city →
Now live
Build your Unincorporated Navajo County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Navajo County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →